Exam Home Website
中文 English
0
/100
FAIL
Correct: 0/100 Total Questions: 100 Time Spent: 60min0sec
Passing: 80
Retake History
Answer Review
✗
Question 1. What should be noted when using the echo sounder to monitor under-keel clearance?
Your Answer: (Not answered)
Correct Answer: B (Use it with draught and tidal information, remembering that readings are affected by aeration under the hull and the nature of the seabed)
💡 Echo sounder readings may be affected by aeration beneath the hull, water temperature and salinity and the nature of the seabed, and give the depth below the ship. They must be used with the draught, tide and chart to judge under-keel clearance, and a shoal area must not be entered on the strength of the sounder alone.
✗
Question 2. What are the requirements on the use of the emergency steering position?
Your Answer: (Not answered)
Correct Answer: A (steering taken on there quickly when bridge control fails, communication with the bridge kept, and the crew made familiar with the position and its handling by drill)
💡 The emergency position is in the steering gear space and exists so the ship can still be steered when control from the bridge has failed. It must be lit and fed from a supply that does not depend on the main source, have a sound means of communication with the bridge, show the position of the rudder, and be operated in a way the person on watch can take at once, direct control of the valves or the gear as the case may be, after practice. The drill programme covers the changeover from bridge control and how long it takes. To leave the work to the engineer alone with the officer writing down times, or to treat the position as a drill item never to be used in earnest, misses what it is there for.
✗
Question 3. The carriage of grain in bulk shall follow:
Your Answer: (Not answered)
Correct Answer: B (the International Grain Code)
💡 SOLAS VI/6: the carriage of grain in bulk shall follow the International Grain Code.
✗
Question 4. What does SOLAS address regarding boarding arrangements for survival craft?
Your Answer: (Not answered)
Correct Answer: C (Boarding positions must allow persons to enter safely, with handholds and non-slip provision where necessary)
💡 SOLAS requires boarding positions to allow persons to enter safely, with handholds, non-slip surfaces and lighting where necessary, reducing the risk of a person falling or going into the water during abandonment.
✗
Question 5. How should a safety culture be built on board?
Your Answer: (Not answered)
Correct Answer: A (Through leadership by example, open communication, training and encouragement, making safety the crew's own practice)
💡 The effectiveness of a safety management system depends on its culture: the master and officers setting an example, open communication and reporting encouraged, continuous training and encouragement and attention to safety performance, so that safety becomes the crew's own behaviour rather than passive compliance with rules.
✗
Question 6. What shall the Ship Security Plan contain?
Your Answer: (Not answered)
Correct Answer: B (Security organisation, duties, measures and training)
💡 Security organisation, duties, protective measures and training.
✗
Question 7. A PSCO checked the chart updating of ECDIS. What does SOLAS require?
Your Answer: (Not answered)
Correct Answer: D (Electronic charts must be kept up to date and consistent with the ENCs in use)
💡 SOLAS requires the electronic charts used in ECDIS to be kept corrected to the latest state and consistent with the ENCs in use. Late updating means missing recent navigational warnings and increases the risk of grounding, a common deficiency.
✗
Question 8. What is the usual maximum validity of a Cargo Ship Safety Radio Certificate?
Your Answer: (Not answered)
Correct Answer: B (Five years, with periodical surveys)
💡 Under SOLAS I/12 the Cargo Ship Safety Radio Certificate has a usual validity of not more than five years, with periodical surveys as required. The performance and provision of the radio installation, including distress alerting, communications and the reserve source of energy, are the focus of the survey.
✗
Question 9. What is the primary fire safety objective of SOLAS Chapter II-2?
Your Answer: (Not answered)
Correct Answer: A (To prevent the occurrence and spread of fire)
💡 The primary objective is to prevent fires and limit their spread.
✗
Question 10. What do SOLAS and the ISM Code address regarding safety meetings and training on board?
Your Answer: (Not answered)
Correct Answer: D (Regular safety training and meetings to raise crew awareness, with records kept)
💡 The ISM Code and good practice require regular safety meetings and training on board, dealing with the ship's own situation such as recent incidents, problems found in drills and new requirements, with records kept, raising the crew's safety awareness and practical ability.
✗
Question 11. What does SOLAS require for the maintenance and testing of radio equipment?
Your Answer: (Not answered)
Correct Answer: A (Regular testing with records kept so that the equipment remains ready for use at all times)
💡 SOLAS IV/15 requires prescribed daily and periodic tests with records kept, keeping the equipment in a state of readiness. Waiting for the annual survey is not sufficient.
✗
Question 12. A survey is carried out two months early. What is the effect under SOLAS?
Your Answer: (Not answered)
Correct Answer: C (The next due date is still counted from the original anniversary, not postponed by the early survey)
💡 The SOLAS window allows flexibility in scheduling but does not change the due date, which is counted from the certificate anniversary. An early survey does not postpone the next one, preventing effective extension of the certificate by surveying early.
✗
Question 13. Which systems shall be used to receive navigational warnings?
Your Answer: (Not answered)
Correct Answer: C (Maritime safety information systems such as NAVTEX and SafetyNET)
💡 Systems such as NAVTEX and SafetyNET.
✗
Question 14. Which ships does the International Safety Management Code reach?
Your Answer: (Not answered)
Correct Answer: A (every class of ship to which the Convention applies, together with their companies - passenger ships, tankers, chemical carriers and bulk carriers included)
💡 The Code runs along the Convention's own scope rather than sorting by ship type: passenger ships, cargo ships (tankers, chemical and gas carriers, bulk carriers among them) and mobile offshore drilling units required by the Convention, together with the companies that operate them, must all have a system. The certificate is issued to the ship (the Safety Management Certificate), but the system is built at company level, which is why companies and ships enter the scope together. Reading the Code as reaching one type of ship only usually means it has been confused with the ship-type technical provisions.
✗
Question 15. What preparation is required before new equipment is brought into use?
Your Answer: (Not answered)
Correct Answer: A (Familiarisation training completed, procedures and checklists revised and the item included in the maintenance programme)
💡 Before new or replacement equipment is brought into use, the crew should complete familiarisation training covering operation, emergencies and maintenance, the relevant procedures and checklists be revised, the item included in the maintenance programme and the effect on the system documentation considered, preventing errors from unfamiliarity.
✗
Question 16. A cargo ship safety equipment certificate expires while the ship is still at sea on her return voyage. What may the Administration do?
Your Answer: (Not answered)
Correct Answer: A (Grant an extension of not more than three months so the ship may reach her port of survey)
💡 SOLAS I/14 permits an extension of up to three months for a certificate expiring during a voyage, so that the ship may reach the port where she is to be surveyed.
✗
Question 17. A self-igniting light on a lifebuoy is found inoperative because its battery has failed. The finding is?
Your Answer: (Not answered)
Correct Answer: C (The lifebuoy has lost its night-marking capability, a life-saving equipment deficiency to be replaced)
💡 The self-igniting light is used at night to mark the position of a person overboard and is a key attachment of the lifebuoy. A failed battery makes the lifebuoy unidentifiable at night. This is a functional deficiency of life-saving equipment; the battery or light should be replaced so that it is always ready for use.
✗
Question 18. What is the relationship between lifejackets and immersion suits in survival craft?
Your Answer: (Not answered)
Correct Answer: A (A lifejacket provides buoyancy while an immersion suit provides thermal protection and buoyancy; they have different functions)
💡 A lifejacket principally provides buoyancy and a face-up attitude in the water, while an immersion suit provides both thermal protection and buoyancy. Their functions differ. In cold waters the ship should carry immersion suits while lifejackets remain required for every person; the two are used together.
✗
Question 19. What launching and recovery time must a rescue boat achieve under SOLAS?
Your Answer: (Not answered)
Correct Answer: A (Launch and recover within not more than 5 minutes in moderate sea conditions)
💡 SOLAS requires a rescue boat to be launched and recovered within not more than 5 minutes in moderate sea conditions, so that a person in the water is recovered as quickly as possible. A longer time significantly reduces the chance of success.
✗
Question 20. What should be done if a launching appliance fails during a drill?
Your Answer: (Not answered)
Correct Answer: B (Stop the operation at once, establish the cause and arrange repair, recording the defect and assessing availability)
💡 If a launching appliance fails during a drill, such as a slipping brake, seized release gear or an abnormal fall, the operation should stop at once, the cause established and repair arranged, with the defect recorded and the availability of the craft assessed. Measures should be taken to maintain the life-saving capability and the company informed.
✗
Question 21. What should be done if insulation on a fire division becomes damp, falls off or is removed?
Your Answer: (Not answered)
Correct Answer: D (Repair or replace promptly to restore the fire rating, using approved material)
💡 Damp, missing or removed insulation on a class A division reduces its fire performance and should be replaced promptly with approved material to restore the original rating. Substituting ordinary material or timber destroys the protective function of the division.
✗
Question 22. What does SOLAS V require of the master when heavy weather is encountered at sea?
Your Answer: (Not answered)
Correct Answer: D (To take appropriate measures to safeguard the ship, altering course or speed if necessary, and to report to the company)
💡 SOLAS V/33 places responsibility for the safety of the ship and persons on board on the master, who must take measures such as sheltering, altering course or reducing speed, and must report under the SMS.
✗
Question 23. In a crossing situation, what principle governs the stand-on vessel's action?
Your Answer: (Not answered)
Correct Answer: C (keep course and speed at first; but once it is clear the give-way vessel is not acting as the rules require, take avoiding action alone)
💡 Where one of two vessels is to keep out of the way the other keeps course and speed - not a bar on moving but a predictable target offered to the other. The keeping has a condition: as soon as the stand-on vessel finds the give-way vessel plainly not acting as the rules require, she should act alone in the way best to avoid collision, and a turn to starboard generally serves better than one to port, which would put her across his bow. When collision cannot be avoided by the give-way vessel's action alone, she may depart from the rules. Easing ahead across his bow, doing his keeping-out-of-the-way for him, or stopping on the spot all throw away the predictability.
✗
Question 24. What information must the master have before departure?
Your Answer: (Not answered)
Correct Answer: B (Approved stability information including damage stability)
💡 Approved stability information, including damage stability, shall be available to the master.
✗
Question 25. Passenger ships of 4 000 GT and above shall be provided with at least how many independently driven fire pumps?
Your Answer: (Not answered)
Correct Answer: B (3)
💡 SOLAS II-2/10 requires at least three independently driven fire pumps for passenger ships of 4 000 GT and above.
✗
Question 26. Which statement about the decision to abandon ship is correct?
Your Answer: (Not answered)
Correct Answer: C (The decision rests with the master, who orders abandonment only when the ship is beyond saving)
💡 The decision to abandon ship rests with the master, who orders it only when the ship is beyond saving and remaining on board endangers personnel. Before abandoning, every effort should be made to call for assistance, prepare the craft and their equipment, muster and account for all persons, and give the abandon-ship signal for orderly boarding.
✗
Question 27. Where must the closing devices of main machinery space ventilation openings be operable?
Your Answer: (Not answered)
Correct Answer: A (From a readily accessible position outside the machinery space, clearly marked)
💡 SOLAS requires the closing devices of the main inlets and outlets of machinery space ventilation to be operable from a readily accessible position outside the machinery space, clearly marked, so that ventilation can be shut off in a fire without entering the space.
✗
Question 28. Besides rocket parachute flares and hand flares, which other pyrotechnic is required among the lifeboat's distress signals?
Your Answer: (Not answered)
Correct Answer: A (Buoyant smoke signals)
💡 SOLAS III/7.2 requires the lifeboat to carry distress signals comprising rocket parachute flares, hand flares and buoyant smoke signals. Extinguishers and first aid kits are separate items of equipment.
✗
Question 29. How does the position of the centre of gravity affect cargo stowage?
Your Answer: (Not answered)
Correct Answer: D (The higher the cargo, the higher the centre of gravity, the smaller the initial metacentric height and the poorer the stability; cargo should not be concentrated high)
💡 The higher the cargo, the higher the ship's centre of gravity, the smaller the initial metacentric height and the less the reserve of stability, making capsize more likely in rough weather. Stowage should avoid concentrating cargo high up, particularly on a tween deck, and the resulting height of the centre of gravity should be checked against the permissible value.
✗
Question 30. What periodic testing does the bilge system require?
Your Answer: (Not answered)
Correct Answer: D (Periodic water tests confirming that each compartment suction drains effectively, with strainers and valves checked)
💡 SOLAS and good practice require periodic water tests of the bilge system, confirming that the suction in each compartment drains effectively, that strainers are clear and valves operate reliably, with the results recorded, preventing the system from failing when needed.
✗
Question 31. What minimum speed must a powered rescue boat be capable of maintaining in calm water with its full complement aboard?
Your Answer: (Not answered)
Correct Answer: B (6 knots)
💡 SOLAS III/17 requires a powered rescue boat to maintain at least 6 knots for not less than 4 hours. Four knots is a frequently confused figure.
✗
Question 32. What radio communication measures are required when operating in polar regions?
Your Answer: (Not answered)
Correct Answer: A (Take account of limited satellite coverage and provide means such as HF unaffected by the region, with enhanced watchkeeping)
💡 Geostationary satellite coverage is limited in polar regions, above about 75 degrees latitude, so SOLAS and the Polar Code require means such as HF communication to be provided with a watch maintained and, where necessary, relaying through a coast station or another ship, ensuring that distress communication gets through.
✗
Question 33. What assessment and improvement follows emergency drills?
Your Answer: (Not answered)
Correct Answer: A (Analyse the problems found, assess the effectiveness of the procedures and revise them, forming a closed loop)
💡 The ISM Code and good practice require drills to be assessed: the problems found, such as slow response, unclear duties or unavailable equipment, analysed, the effectiveness of the existing procedures and training evaluated and revisions made, so that drills genuinely drive improvement of the system in a closed loop.
✗
Question 34. What does SOLAS address regarding the relationship between the rated capacity of survival craft and the persons on board?
Your Answer: (Not answered)
Correct Answer: C (The total rated capacity must meet the needs of all persons on board, with the prescribed margin)
💡 SOLAS requires the total rated capacity of the survival craft, under the rules for each side or the whole ship, to accommodate all persons on board with the prescribed margin. Insufficient capacity would leave some persons with nowhere to go on abandonment, a serious deficiency.
✗
Question 35. What is the basic SOLAS II-1 requirement for the position of the collision bulkhead on a cargo ship?
Your Answer: (Not answered)
Correct Answer: A (At a distance from the forward perpendicular of not less than 5 per cent of the ship's length, or 10 m, whichever is the less)
💡 SOLAS II-1 requires the collision bulkhead to be not less than 5 per cent of the ship's length or 10 m, whichever is less, from the forward perpendicular, so that flooding forward protects the spaces abaft.
✗
Question 36. What do SOLAS and good practice address regarding watertight doors kept open while in port?
Your Answer: (Not answered)
Correct Answer: A (They may be opened as required for operations, but must remain capable of immediate closing with attention to changes in the ship's condition)
💡 Some watertight doors may be opened in port for cargo work or access, but must remain capable of being closed at once, with their status indicated on the bridge, and must be closed again if the ship's condition changes, such as draught change during cargo work, preventing inadvertent flooding.
✗
Question 37. What is the main purpose of thickness measurement in the enhanced survey?
Your Answer: (Not answered)
Correct Answer: B (To assess corrosion and remaining structural strength)
💡 Thickness measurement quantifies plate loss and the remaining strength of the structure.
✗
Question 38. What does SOLAS address regarding automatic operation of emergency lighting after loss of the main source?
Your Answer: (Not answered)
Correct Answer: A (Emergency lighting must come on automatically after failure of the main source, without manual action)
💡 SOLAS requires emergency lighting to operate automatically when the main source fails, so that the crew has illuminated guidance at the moment of the blackout. A system requiring manual change-over would be delayed by confusion during the blackout, a common deficiency.
✗
Question 39. Which statement about immersion suits is correct?
Your Answer: (Not answered)
Correct Answer: C (immersion suits reduce body heat loss in cold water)
💡 SOLAS III/32 requires immersion suits for rescue boat crew to reduce body heat loss in cold water.
✗
Question 40. A ship holding a certificate extended under SOLAS I/14:
Your Answer: (Not answered)
Correct Answer: B (may proceed to a port of survey, but shall not carry cargo beyond the specified limitations)
💡 SOLAS I/14: a ship holding an extended certificate may proceed to a port of survey but shall not carry cargo beyond the specified limitations.
✗
Question 41. In what state must fire doors be kept at sea under SOLAS?
Your Answer: (Not answered)
Correct Answer: D (Closed, opened only for passage of persons, and fitted with self-closing devices)
💡 SOLAS requires fire doors to be kept closed at sea, opened only when someone passes through, and to be fitted with self-closing devices. Holding them open with rope or wedges is a common PSC deficiency and defeats the fire protection of the division.
✗
Question 42. What reporting is required for a security incident?
Your Answer: (Not answered)
Correct Answer: A (Report at once under the procedure to the company, the Administration and the relevant parties, recording the circumstances)
💡 A security incident such as unauthorised boarding, the introduction of weapons, theft or sabotage requires immediate reporting under the ship security plan to the company, the Administration where necessary and the port facility security officer, recording the course of the incident, the action taken and the result, with analysis and improvement to follow.
✗
Question 43. What does SOLAS require of the water ingress detection and alarm system on a bulk carrier?
Your Answer: (Not answered)
Correct Answer: B (Detection in cargo holds, ballast tanks and dry spaces, with an audible and visual alarm on the bridge)
💡 SOLAS XII/12 requires a bulk carrier to have water ingress detection in cargo holds, ballast tanks and dry spaces, with an audible and visual alarm on the bridge, enabling the watchkeeper to detect flooding promptly and act.
✗
Question 44. What is required for monitoring deviation from the planned route?
Your Answer: (Not answered)
Correct Answer: B (Check the position against the planned route regularly, correcting any deviation promptly and recording the reason)
💡 During the voyage the position should be checked regularly against the planned route, together with the course and speed, with the cause of any deviation, such as wind and current set or a steering error, established and corrected at once, analysing the trend where necessary to prevent continuing offset leading to grounding.
✗
Question 45. What is the meaning and use of an H class division?
Your Answer: (Not answered)
Correct Answer: A (The highest grade of fire-resisting division in the standard test, used for high risk boundaries such as pump rooms on tankers)
💡 An H class division is the highest grade of fire-resisting division under SOLAS, used for high risk boundaries such as the boundaries of cargo pump rooms on tankers. It exceeds class A performance and must retain structural integrity after the test.
✗
Question 46. In addition to ventilation, what shall be fitted in paint lockers and flammable liquid stores?
Your Answer: (Not answered)
Correct Answer: D (A fixed fire-extinguishing system)
💡 SOLAS II-2/10.6.3: paint lockers and flammable liquid stores shall have a fixed fire-extinguishing arrangement.
✗
Question 47. What is the purpose of isolation valves on the fire main required by SOLAS?
Your Answer: (Not answered)
Correct Answer: B (To isolate a damaged section so the rest of the main can continue to supply water)
💡 SOLAS requires isolation valves on the fire main so that if a section, for example in the machinery space, is damaged, it can be isolated while the remainder still supplies the hydrants, preserving at least part of the firefighting capability.
✗
Question 48. What is the purpose of the water ingress detection system required on a bulk carrier?
Your Answer: (Not answered)
Correct Answer: B (To give an alarm when water enters the cargo holds and fore and aft spaces, enabling the crew to detect and deal with it promptly)
💡 Under SOLAS XII/12 a bulk carrier should have water ingress detection and alarm systems for the cargo holds and the forepeak and similar spaces, giving an alarm on the bridge promptly when water enters so that the crew can detect the ingress early and take pumping, leak-hunting and damage control measures, preventing the situation from worsening. The testing of the system should be kept effective.
✗
Question 49. What should be noted about fog signals in restricted visibility?
Your Answer: (Not answered)
Correct Answer: A (Sound fog signals as COLREG prescribes and listen attentively to other vessels' signals to judge bearing and movement)
💡 In restricted visibility fog signals should be sounded as COLREG prescribes, for example one prolonged blast at intervals of not more than two minutes for a power-driven vessel under way, while listening carefully to other vessels' signals to judge their approximate bearing and movement, combined with radar observation. Sounding must not be delayed.
✗
Question 50. For a ship loading grain, what should its stability mainly address?
Your Answer: (Not answered)
Correct Answer: D (The heel and stability loss caused by grain shift, with stability calculated as required and measures taken to restrain movement)
💡 Under SOLAS VI/6 and the International Grain Code, when loading grain the assumed heel and stability loss caused by grain shift should be calculated and measures taken such as trimming, longitudinal divisions or strapping to restrain movement, ensuring the required stability criteria are met during the voyage. Grain flows, so it is a focus of stability.
✗
Question 51. What are the key points in lowering a lifeboat during an abandon ship drill?
Your Answer: (Not answered)
Correct Answer: A (Check the brake and release gear, lower under the procedure and take account of the ship's condition)
💡 Lowering a lifeboat in a drill requires checking the brake and release gear, lowering under the procedure with account taken of list and sea conditions and the work done by not fewer than two persons. Rapid release or solo operation is a principal cause of casualties in drills.
✗
Question 52. Enhanced Surveys (ESP) apply to:
Your Answer: (Not answered)
Correct Answer: C (bulk carriers and oil tankers to which the requirements apply)
💡 SOLAS XI-1/2: Enhanced Surveys apply to bulk carriers and oil tankers to which the requirements apply.
✗
Question 53. What determines the number of fireman's outfits to be carried?
Your Answer: (Not answered)
Correct Answer: A (The gross tonnage)
💡 The number of fireman's outfits is determined by the gross tonnage.
✗
Question 54. What fire precautions are required before bunkering?
Your Answer: (Not answered)
Correct Answer: A (Confirm firefighting equipment in place, close relevant openings, clear deck of oil and establish communication with the barge)
💡 Before bunkering, firefighting equipment such as extinguishers, hoses and absorbents should be in place, openings through which oil could enter should be closed and the deck kept free of oil, with communication and an agreed emergency stop arranged with the supplier, preventing overflow and fire.
✗
Question 55. What does SOLAS address regarding fixed fire detection in ro-ro spaces?
Your Answer: (Not answered)
Correct Answer: B (A fixed fire detection and fire alarm system capable of detecting a fire in the vehicle space promptly)
💡 SOLAS requires ro-ro and vehicle spaces to have a fixed fire detection and fire alarm system. Because these spaces are large and vehicles carry fuel, fire spreads rapidly, and periodic rounds alone would not detect it in time.
✗
Question 56. What safety is required for work at height at sea?
Your Answer: (Not answered)
Correct Answer: C (Use of safety harness and fall arrest equipment, warning signs and a standby person, taking account of ship movement)
💡 Work at height such as on masts, cranes and hatch coamings requires a safety harness and fall arrest equipment secured to a reliable point, warning signs and a standby person, with account taken of ship movement and wind. Hazardous work in heavy weather is prohibited.
✗
Question 57. What interval applies to launching lifeboats into the water during drills on a cargo ship?
Your Answer: (Not answered)
Correct Answer: C (At least once every three months the boat is lowered into the water and manoeuvred, where reasonable and practicable)
💡 SOLAS III/19 requires a launching drill at least every three months and, where reasonable and practicable, the boat to be lowered into the water and manoeuvred at least once in that period, so that the crew acquires practical skill.
✗
Question 58. What compass equipment must a lifeboat carry under SOLAS?
Your Answer: (Not answered)
Correct Answer: A (A compass with suitable mounting in each lifeboat)
💡 SOLAS requires each lifeboat to carry a compass with a suitable mounting, so that a course can be held after abandonment. Its absence or poor mounting reduces the chance of being found.
✗
Question 59. Who is responsible for the maintenance of life-saving appliances under SOLAS?
Your Answer: (Not answered)
Correct Answer: B (A suitably qualified person on board for routine maintenance, with complex servicing by an approved service station)
💡 SOLAS requires a suitably qualified person on board to be responsible for routine inspection and maintenance, with complex servicing of inflatable liferafts, launching appliances and similar items carried out by an approved service station.
✗
Question 60. What is the principle of zoning for a fixed fire detection and fire alarm system?
Your Answer: (Not answered)
Correct Answer: A (The system should detect by zone and indicate the affected zone so that the fire can be quickly located and action taken)
💡 Under SOLAS II-2/7 a fixed fire detection and fire alarm system should be arranged in sections so that the alarm indicates the section in which a fire or fault has occurred, enabling the crew quickly to locate the fire and take action. A fault in the detection system should be capable of being indicated, isolated and reset.
✗
Question 61. What does SOLAS address regarding the arrangement for boarding survival craft?
Your Answer: (Not answered)
Correct Answer: A (Boarding in order according to the list, with numbers not exceeding the rated capacity, avoiding crowding and overload)
💡 Boarding should follow the prepared list and order, with the number in each craft not exceeding the rated capacity and persons detailed to let go the lifelines, handle the boat and attend to casualties, avoiding confusion, crowding and overloading which would affect the safety of the craft.
✗
Question 62. What is required of watertight doors during navigation?
Your Answer: (Not answered)
Correct Answer: B (Kept closed, opened only for necessary passage)
💡 SOLAS II-1/22: watertight doors shall be kept closed during navigation, opened only for passage.
✗
Question 63. What may result from insufficient height of the hatch coaming?
Your Answer: (Not answered)
Correct Answer: B (Water shipping into the hold)
💡 The coaming height is set so that shipping or sea water cannot enter the hold.
✗
Question 64. The double-side-skin requirement for new bulk carriers does not apply to every bulk carrier. What triggers it?
Your Answer: (Not answered)
Correct Answer: B (new bulk carriers of 150 metres in length and upwards, of single skin construction, intended to carry solid bulk cargo of a density of 1000 kg per cubic metre or greater)
💡 The line is drawn by length and cargo density: new bulk carriers of 150 metres in length and upwards, of single skin construction and intended for solid bulk cargo of a density of 1000 kg per cubic metre or greater, must have double side spaces, so that a breach in the side leaves reserve buoyancy and slows flooding. Carriers of lighter grain and ships under that length fall outside the regulation while still meeting other stability and structural requirements.
✗
Question 65. Besides the damage control plan, what should the damage control information include?
Your Answer: (Not answered)
Correct Answer: D (A damage control booklet or notes for the master, including measures for cross-flooding, listing control and regaining stability)
💡 SOLAS II-1/23 requires, besides the damage control plan, information for the master such as a damage control booklet covering cross-flooding, heel control and restoring stability, for use in a damage situation.
✗
Question 66. What is the servicing interval for inflatable liferafts?
Your Answer: (Not answered)
Correct Answer: A (Not exceeding 12 months, at an approved servicing station)
💡 Inflatable liferafts must be serviced at an approved station at intervals not exceeding 12 months, unless a longer interval is approved for specially designed rafts.
✗
Question 67. What does SOLAS require regarding the receipt of navigational warnings and meteorological information at sea?
Your Answer: (Not answered)
Correct Answer: D (They must be received and processed continuously by the prescribed means, with timely assessment of their effect on the voyage)
💡 SOLAS V requires continuous reception of navigational warnings and weather information by the appropriate means, with the watchkeeper assessing their effect on route and speed and acting accordingly.
✗
Question 68. What is the purpose of the safety contour and safety depth settings in ECDIS?
Your Answer: (Not answered)
Correct Answer: A (To warn automatically of shoal water and dangers by triggering safety alarms)
💡 The safety contour and safety depth define the navigable safe area and trigger automatic alarms when the ship approaches shoal water or dangers. They are central to passage monitoring.
✗
Question 69. How must the rated capacity of a lifeboat be marked under SOLAS?
Your Answer: (Not answered)
Correct Answer: A (Clearly and legibly marked on the boat, consistent with the capacity approved at survey)
💡 SOLAS requires the rated capacity to be clearly and durably marked on the boat so that the crew can tell at once whether it is overloaded. Recording it only on the certificate or advising orally does not comply.
✗
Question 70. When a fire breaks out, which sequence of actions should be completed first under the muster list?
Your Answer: (Not answered)
Correct Answer: C (Raise the fire alarm, report to the bridge, muster as per the list and begin locating the fire and initial firefighting)
💡 On discovering a fire the alarm should first be raised and the bridge informed, then personnel mustered as per the muster list, the seat and extent of the fire located, initial firefighting begun with escape routes assured and ventilation closed. Raising the alarm has priority in all procedures and cannot follow mustering or informing the company.
✗
Question 71. For a tanker fitted with an inert gas system, the deck foam system application rate shall be not less than:
Your Answer: (Not answered)
Correct Answer: C (1.0 L/min·m²)
💡 SOLAS II-2/20 requires the foam application rate to be not less than 1.0 L/min·m² for tankers with an inert gas system.
✗
Question 72. What shall be fitted in all accommodation, service spaces and control stations on a passenger ship?
Your Answer: (Not answered)
Correct Answer: D (A fixed fire detection and alarm system)
💡 SOLAS II-2/7: passenger ships shall be fitted with a fixed fire detection and alarm system in all such spaces.
✗
Question 73. What is the main purpose of ship reporting systems?
Your Answer: (Not answered)
Correct Answer: A (To provide information on ship movements for search and rescue and safety of navigation)
💡 SOLAS V/11 establishes ship reporting systems to supply movement information for search and rescue and safety of navigation, not for commercial or charging purposes.
✗
Question 74. What checks are required after cargo operations on a tanker?
Your Answer: (Not answered)
Correct Answer: A (Confirm valves closed, lines depressurised and drained properly and the deck free of oil before standing down)
💡 After cargo operations on a tanker the procedure requires confirmation that the relevant valves are closed, the lines depressurised and drained, residual oil and drips dealt with, the deck clean and free of oil and the inert gas system normal, with a record made, before standing down, preventing danger from residual vapour.
✗
Question 75. Who issues and endorses certificates after surveys are completed?
Your Answer: (Not answered)
Correct Answer: C (The Administration or a recognised organisation duly authorised by it, with endorsement as required)
💡 SOLAS requires statutory certificates to be issued by the Administration or a duly authorised recognised organisation, and endorsed after surveys. Neither the master, the port State nor the owner may issue them.
✗
Question 76. How is the value of the subdivision index R related to ship type?
Your Answer: (Not answered)
Correct Answer: D (For passenger ships it is determined by length and zone of service, and there are prescribed values for cargo ships)
💡 SOLAS II-1 prescribes values of the subdivision index R by ship type — for passenger ships by length and zone of service, and prescribed values for cargo ships. It is neither uniform nor a matter of choice.
✗
Question 77. In what form must the safe working load information for mooring equipment be kept under SOLAS?
Your Answer: (Not answered)
Correct Answer: D (On board in an accessible form identifying each fitting and its safe working load)
💡 SOLAS requires information on the arrangement, identification and safe working load of mooring and towing equipment to be kept on board, such as a mooring arrangement plan and load table, for correct use and inspection.
✗
Question 78. When navigating in polar waters, what should be paid particular attention to under the Polar Code?
Your Answer: (Not answered)
Correct Answer: A (The effects of low temperature on equipment and personnel, ice conditions and ice class, and the procedures and limitations in the Polar Ship's Operational Manual)
💡 The polar environment is special, so particular attention should be paid to the effects of low temperature on equipment such as life-saving appliances, firefighting, fuel and hydraulic systems and on personnel, to ice conditions and the ship's ice class limits, and to the operational procedures and limitations in the Polar Ship's Operational Manual, with specific training and preparation carried out.
✗
Question 79. The security drills required by the ship security plan are found not held at the required intervals. The finding is?
Your Answer: (Not answered)
Correct Answer: A (Security drills should be held and recorded at the required intervals; failure is a security management deficiency)
💡 The ship security plan requires security drills to be held at regular intervals and recorded, keeping the crew familiar with security threats and emergency procedures. Failure to hold or record them shows the security measures are not being implemented properly. It is a deficiency to be corrected.
✗
Question 80. What is the purpose of the weak link in a liferaft arrangement?
Your Answer: (Not answered)
Correct Answer: D (To part once the raft has inflated and floats, freeing it from the sinking ship)
💡 The weak link has a designed breaking strength so that it parts once the raft has inflated and is lifted by the water, freeing it from the sinking ship. If too strong the raft may be dragged under; if too weak it may part before inflation.
✗
Question 81. When a pilot is on board, how is responsibility allocated?
Your Answer: (Not answered)
Correct Answer: A (The pilot provides pilotage and advice but does not relieve the master of responsibility for the safety of the ship)
💡 A pilot on board provides local pilotage and manoeuvring advice but does not relieve the master of responsibility for the safety of the ship. The master and officer of the watch should still monitor the ship's movement and, if the pilot's orders are likely to cause danger, should speak up promptly and take necessary action.
✗
Question 82. How should abnormal engine revolutions or speed be judged?
Your Answer: (Not answered)
Correct Answer: B (Taking account of current, wind, draught and hull fouling, with the cause established if abnormal)
💡 Abnormal speed or engine revolutions may result from current, wind, a change of draught, fouling of the hull or propeller or a fault in the engine or shafting. They should be judged against the navigational conditions and the cause established, since a marked loss of speed affects the voyage plan and safety.
✗
Question 83. What are the duties of the deck watch during cargo operations on a tanker?
Your Answer: (Not answered)
Correct Answer: B (Monitor piping, valves and tanks, detecting leaks, overflow or abnormalities and taking action)
💡 During cargo operations on a tanker a deck watch must be maintained, monitoring pipeline joints for leakage, tank levels and pressures, overflow and unusual noise, with communication kept with the engine room and the terminal, so that abnormalities are detected and dealt with promptly.
✗
Question 84. What fire detection arrangement is required for category A machinery spaces?
Your Answer: (Not answered)
Correct Answer: A (A fixed fire detection and fire alarm system capable of detecting a fire and indicating its location)
💡 SOLAS II-2/7 requires a fixed fire detection and alarm system in category A machinery spaces, giving early detection and indicating the location on the bridge or at a control station.
✗
Question 85. What is required for manholes and flush covers in the freeboard deck?
Your Answer: (Not answered)
Correct Answer: C (Kept closed and secured, preventing sea water entering spaces below when the deck is swept)
💡 SOLAS and the Load Line Convention require manholes and flush covers in the freeboard deck leading to spaces below to be kept closed and secured, with gaskets and fastenings, preventing sea water from entering when the deck is swept or the ship lists. A simple plate is not watertight.
✗
Question 86. Each lifeboat shall be provided with equipment including:
Your Answer: (Not answered)
Correct Answer: B (a complete set including oars, compass, sea anchor, first-aid kit, etc.)
💡 SOLAS III/34 lists lifeboat equipment including oars, compass, sea anchor, first-aid kit, food and water.
✗
Question 87. What is the purpose of a company's periodic visits and inspections of its ships?
Your Answer: (Not answered)
Correct Answer: A (To verify the effective implementation of the system on board, identify and help resolve problems and promote continual improvement)
💡 The ISM Code requires the company to inspect its ships periodically, through internal audits and visits, in order to verify that the system works effectively on board, identify non-conformities and opportunities for improvement and provide support, not merely to assess the crew. Problems found should be followed up to closure.
✗
Question 88. What is the usual maximum validity of a Passenger Ship Safety Certificate?
Your Answer: (Not answered)
Correct Answer: D (Twelve months)
💡 Under SOLAS I/12 a Passenger Ship Safety Certificate has a usual validity of not more than twelve months, unlike the certificates of a cargo ship, with the relevant surveys completed within the period. Because a passenger ship carries many people, its surveys and certificate management are more frequent.
✗
Question 89. What must the emergency preparedness procedures contain?
Your Answer: (Not answered)
Correct Answer: A (Identification of the emergencies possible and the alarm and response procedures, duties and external contacts)
💡 The ISM Code requires the emergency preparedness procedures to cover the identification of the emergencies possible, such as fire, flooding, collision, pollution and injury, the alarm and response steps, the duties of each position and shore support and external contacts with search and rescue, the port and the company, with regular drills.
✗
Question 90. What principle should the officer of the watch follow in using ECDIS in confined waters or a port approach?
Your Answer: (Not answered)
Correct Answer: B (Adjust the display scale appropriately and keep the chart updated, avoiding over-reliance on a single display for position)
💡 ECDIS should be used with the scale adjusted to the leg of the passage, charts kept updated and the position cross-checked. Switching off safety alarms or fixing one scale weakens the warning function and increases the risk of grounding.
✗
Question 91. What checking is required of the electrical insulation of firefighter's boots?
Your Answer: (Not answered)
Correct Answer: C (Check the soles for damage, perforation and loss of insulating properties, replacing them at once if defective)
💡 Firefighter's boots should be checked for damage, perforation, ageing and loss of insulating properties in the soles. Damaged boots expose the firefighter to injury in a live electrical or high temperature environment and must be replaced at once, forming part of the routine inspection of the outfit.
✗
Question 92. When inerting the cargo tanks of a tanker, what is the usual upper limit for the oxygen content of the tank atmosphere?
Your Answer: (Not answered)
Correct Answer: A (Not more than five per cent by volume)
💡 Under SOLAS II-2/4 and the related requirements, when the cargo tanks of a tanker are inerted the oxygen content of the tank atmosphere should be held below five per cent by volume so that a flammable mixture cannot form. The inert gas system should maintain a positive tank pressure and monitor the oxygen content, and the operation should stop if the limit is exceeded.
✗
Question 93. When a deficiency found in a PSC inspection is judged to be a non-detainable one, how is it normally handled?
Your Answer: (Not answered)
Correct Answer: B (Rectify within the specified period, generally without affecting departure, keeping evidence of rectification)
💡 A non-detainable deficiency is normally required to be rectified within the specified period, before departure or subsequently, and does not necessarily lead to detention, but the ship should keep evidence of rectification such as photographs, repair records and service reports for re-inspection and future checks. A detainable deficiency must be rectified before departure.
✗
Question 94. A watertight door is found unable to be closed remotely from the bridge. The finding is?
Your Answer: (Not answered)
Correct Answer: A (Watertight doors must be remotely closable with indication of their open or closed position; failure affects subdivision integrity)
💡 Where subdivision requires it a watertight door, especially a remotely controlled one, must be capable of remote closure from the central control station on the bridge with position indication there. Loss of remote control affects the ability to close doors rapidly and maintain subdivision integrity in the event of flooding. It is a deficiency to be corrected.
✗
Question 95. For how long must the GMDSS reserve source of energy supply the radio installation when the main source fails under SOLAS IV/9?
Your Answer: (Not answered)
Correct Answer: C (At least one hour, for both passenger and cargo ships)
💡 SOLAS IV/9 requires the reserve source to supply the radio installation for at least one hour. The 18-hour figure applies to emergency lighting on cargo ships under a different regulation.
✗
Question 96. Why shall spaces where flammable gases may accumulate be ventilated?
Your Answer: (Not answered)
Correct Answer: B (To prevent gases reaching dangerous concentrations)
💡 To prevent accumulation of flammable gases to dangerous concentrations.
✗
Question 97. With regard to traffic separation schemes, ships shall:
Your Answer: (Not answered)
Correct Answer: D (navigate in the appropriate traffic lane in accordance with the scheme)
💡 SOLAS V/10 requires ships to navigate in the appropriate lane of a traffic separation scheme.
✗
Question 98. What is the cycle for safety management system audits?
Your Answer: (Not answered)
Correct Answer: D (Internal audits normally not exceeding 12 months, annual verification of the DOC and intermediate verification of the SMC)
💡 The ISM Code requires internal audits at intervals not exceeding 12 months, annual verification of the Document of Compliance to keep it valid and intermediate verification of the Safety Management Certificate within its period of validity. Failure to verify in time affects the validity of the certificates.
✗
Question 99. A fire drill must do more than muster and call names. What else has to happen?
Your Answer: (Not answered)
Correct Answer: D (mustering to the station bill and reporting, doors, dampers, outfits and communication examined, a fire simulated and water streamed)
💡 The drill has to be worked through for real: mustering to the station bill and reporting the numbers and the positions taken; fire doors and dampers closed and their closing confirmed; the firemen's outfits ready to be put on, the cylinders charged, the communication gear tested; a fire simulated, the way found and approached, the fire pump started and water streamed from a hydrant, so that pump, pipe, nozzle and people are proved together. A fire party drilling alone while the rest wait in their cabins, or a lecture in place of the exercise, tests nothing about the duties the station bill assigns and leaves a record no inspector can accept.
✗
Question 100. With regard to openings in the collision bulkhead, which is correct?
Your Answer: (Not answered)
Correct Answer: D (the number of openings shall be reduced to a minimum and no doors or manholes shall be fitted)
💡 SOLAS II-1/12 requires openings in the collision bulkhead to be reduced to a minimum, with no doors, manholes or ventilation ducts.