Question 1. What should the pilot information exchange cover?
Your Answer: (Not answered)
Correct Answer: A (manoeuvring characteristics, equipment state, draught and berthing plan)
💡 Exchange covers handling, equipment, draught and the berthing plan so pilot and bridge share one picture.
✗
Question 2. If a master is blamed after a safety decision per the SMS, the proper response is?
Your Answer: (Not answered)
Correct Answer: C (the SMS should protect compliant decisions, review not just blame)
💡 A just culture protects compliant decisions, avoiding a chilling effect.
✗
Question 3. The ISM Code requires the company to designate a shore-based link between the ship and the shore. What is that post called?
Your Answer: (Not answered)
Correct Answer: B (the designated person, usually written as DPA)
💡 Rule 4 turns on the arrangement, not the title: the link bypasses the commercial chain, the master can reach highest management at any time, and the designated person must carry enough authority and resources. Equating the post with the company security officer or a safety manager is the usual confusion found in audits.
✗
Question 4. What does ISM Chapter 1 (General) mainly provide?
Your Answer: (Not answered)
Correct Answer: A (definitions, objectives, scope and certification link)
💡 Chapter 1 sets purpose, SMS definition, ship scope and the DOC/SMC certification link.
✗
Question 5. A Second Officer drafts the year's drill schedule with fire drills quarterly and abandon-ship drills monthly. What does SOLAS and the system actually require?
Your Answer: (Not answered)
Correct Answer: A (abandon-ship and fire drills at least monthly each, combined where reasonable, with familiarisation within 24 hours of taking duties)
💡 Regulation 19 of Chapter III requires abandon-ship and fire drills at least monthly for each ship, held together where reasonable and practicable, so the quarterly fire drill is simply wrong; on cargo ships a lifeboat is launched with its assigned crew every three months, and every new arrival gets familiarisation within 24 hours of joining or taking duties.
✗
Question 6. Violent yawing at anchor from a sudden strong current; what applies?
Your Answer: (Not answered)
Correct Answer: A (veer more cable, stand by engines, report and assess whether to shift)
💡 Strong current yawing raises dragging risk; veer cable, stand by engines, report and shift or weigh anchor if needed.
✗
Question 7. Under ISM, a "critical operation" means?
Your Answer: (Not answered)
Correct Answer: C (an operation whose error would immediately endanger safety or cause pollution)
💡 Rule 7: critical operations are those whose error would immediately threaten safety or cause pollution.
✗
Question 8. Accommodation and catering requirements typically cover?
Your Answer: (Not answered)
Correct Answer: C (space, ventilation, lighting, sanitation, food quality and potable water)
💡 The Annex sets space, ventilation, sanitation, food quality, drinking water and cook qualifications.
✗
Question 9. What is the focus of maintaining watertightness of decks and hatch covers?
Your Answer: (Not answered)
Correct Answer: B (seals, cleats and drainage in good working order)
💡 Watertightness depends on seal elasticity, cleat loading and clear drains; inspect, test and renew aged parts.
✗
Question 10. An abnormally rising temperature is found in a compartment at sea; you should?
Your Answer: (Not answered)
Correct Answer: C (locate the heat source, monitor closely and act per cargo or equipment procedure)
💡 Rising heat may be cargo, machinery or electrical; find the source, monitor and cool or isolate per procedure.
✗
Question 11. What is the relationship between classification survey and the safety management system?
Your Answer: (Not answered)
Correct Answer: B (survey looks at the hardware and so corroborates the maintenance element of the system, but does not stand in place of an audit)
💡 Classification looks at hull, machinery and equipment against the rules of the society, and what it reports is the technical state of the hardware; the management system is about how that state is held — the maintenance plan, the testing and inspection of critical equipment, the closing out of deficiencies and non-conformities, and the crew being familiar with what they operate. Survey records are therefore good corroboration that the equipment element works, but they are not an audit and cannot substitute for the internal review or for the review by top management. The document of compliance and the safety management certificate rest on auditing the system, carried out or delegated by an organisation recognised by the administration, not on classification; suspension of class and withdrawal of the certificate are different outcomes and neither covers the other, and what the crew does when a machine fails still comes from the system.
✗
Question 12. Stowaways are found in port; the master should?
Your Answer: (Not answered)
Correct Answer: B (report company and port authorities, keep them under security control and follow procedures)
💡 Stowaways are a security and immigration matter; report, control, keep evidence and let authorities handle it.
✗
Question 13. The purpose of a close-up survey is?
Your Answer: (Not answered)
Correct Answer: B (inspect structural details closely for cracking, corrosion and deformation)
💡 It lets the surveyor inspect welds, brackets and stress areas closely, finding damage general surveys miss.
✗
Question 14. Facing a serious injury on board, how does the ship reach a doctor ashore?
Your Answer: (Not answered)
Correct Answer: B (reach the shore medical service through the prescribed radio or satellite channel and act on the doctor's advice)
💡 Asking the shore medical authority through the prescribed channel is the ordinary practice: put together a short history first - name, age, how the illness or injury came about, the signs, consciousness and breathing, medicine already given, any allergy - and on that the doctor advises on treatment on board, drugs, and whether evacuation is needed. What the ship must hold is the medicine inventory, the equipment, the case records and the crew health file, with the means of communication, radio or satellite, named in the system documentation and kept serviceable. Waiting for a port without doing anything may let the window close, and asking another ship for a doctor or sending for a helicopter is a separate arrangement, not the first step.
✗
Question 15. On a crew member found drinking or using drugs aboard, the SMS should?
Your Answer: (Not answered)
Correct Answer: D (remove from duty, handle properly and report per procedure, ensuring safety)
💡 Alcohol/drugs threaten safety; immediate off-duty and procedural handling are required.
✗
Question 16. What is the basic rule for discharging oily mixtures in a special area?
Your Answer: (Not answered)
Correct Answer: D (prohibited in principle, with a narrow exception for treated low concentrations while underway)
💡 Special areas are far stricter: discharge is prohibited except under narrow conditions while underway and must be logged.
✗
Question 17. Crew bring unauthorised persons aboard in port; the master should?
Your Answer: (Not answered)
Correct Answer: D (refuse and require them to leave, investigate and act under security procedures)
💡 Unauthorised persons breach security and create risk; refuse, remove them, investigate and report.
✗
Question 18. The usual validity of a SIRE inspection report is?
Your Answer: (Not answered)
Correct Answer: B (usable for about six months before re-inspection is needed)
💡 Reports are generally accepted within six months, after which a fresh inspection keeps vetting data current.
✗
Question 19. The SMC "renewal audit" before expiry should be?
Your Answer: (Not answered)
Correct Answer: B (completed before expiry to issue a new 5-year certificate)
💡 Renewal is completed before expiry, confirming continued conformity, to issue a new certificate.
✗
Question 20. What does the system require for emergency preparedness?
Your Answer: (Not answered)
Correct Answer: C (identify potential emergencies and set response procedures and drills)
💡 Preparedness identifies possible emergencies, sets response procedures and tests them through drills.
✗
Question 21. Missing many required maintenance/training records leads PSC to conclude?
Your Answer: (Not answered)
Correct Answer: C (the SMS is not effectively operating—systemic non-conformities)
💡 Missing records break operational evidence; the system is not truly implemented.
✗
Question 22. If dangerous goods leak into the drains, what applies?
Your Answer: (Not answered)
Correct Answer: B (seal off, collect and report, never flush overboard)
💡 Seal and collect, never flush overboard, and report for proper disposal to prevent wider pollution.
✗
Question 23. On an engine room bilge alarm, the crew should?
Your Answer: (Not answered)
Correct Answer: B (find the leak, start emergency pumping and report, preparing damage control if needed)
💡 Find the source, start emergency pumping, report and prepare plugging and closing to protect buoyancy.
✗
Question 24. At sea the rudder angle indicator disagrees with the actual angle; what applies?
Your Answer: (Not answered)
Correct Answer: A (change to emergency steering, report and manage it as a system defect)
💡 A false rudder indicator undermines handling; change to emergency steering, report and manage as a defect until fixed.
✗
Question 25. What does the system require of shore staff?
Your Answer: (Not answered)
Correct Answer: C (have the competence to support ship safety and pollution prevention)
💡 Shore staff must be competent and resource the ship; ship and shore together make the system work.
✗
Question 26. The audit team finds a defect on the bridge and wants to class it as a major non-conformity. What would support that finding?
Your Answer: (Not answered)
Correct Answer: A (the muster list not renewed for years and no boat lowered in practice, the means of escape never having been exercised)
💡 A major non-conformity is judged by consequence, not by bulk: a key requirement missing or ineffective, safety of people, ship or environment directly at stake, or the rule being incapable of application at all. Lifesaving arrangements existing only on paper are of that order and usually justify detention. A missing signature, or a pump two weeks late with the job already booked, is an ordinary non-conformity for the report and a correction plan.
✗
Question 27. Repeated unanswered calls to the DPA lead PSC to judge?
Your Answer: (Not answered)
Correct Answer: B (ship-shore emergency link broken, a major non-conformity)
💡 The DPA is the 24/7 ship-shore hub; silence breaks emergency support.
✗
Question 28. The ISM Code makes the company establish emergency-preparedness procedures. What are they to cover?
Your Answer: (Not answered)
Correct Answer: B (the foreseeable emergencies — collision, grounding, fire, casualty, oil spill, abandon ship)
💡 The emergency-preparedness section asks the company to identify: the emergencies that ship, area and cargo can meet, a plan for each with duties, communications and resources, drills to prove the plan works, and the drill findings fed back into revision. Substituting piracy for every case, letting a port State defect list stand in for identification, or trimming drills when they inconvenience, all leave the procedure on paper.
✗
Question 29. Large areas of floating debris are met at sea; what applies?
Your Answer: (Not answered)
Correct Answer: B (slow down, keep watch, keep clear and report, minding the propeller and sea suction)
💡 Debris can foul the propeller or block sea suctions; slow, keep clear, watch closely and check the sea system afterwards.
✗
Question 30. How do global PSC regimes coordinate to avoid duplication and gaps?
Your Answer: (Not answered)
Correct Answer: D (regional Memoranda (MoU, e.g. Tokyo, Paris) sharing info and blacklists)
💡 MoUs share info and target ships, raising coverage and fairness.
✗
Question 31. How should the effect of energy efficiency measures be assessed?
Your Answer: (Not answered)
Correct Answer: C (comparable data on the same basis under comparable conditions)
💡 Remove differences in load, weather and speed and compare like with like, or conclusions mislead decisions.
✗
Question 32. Rolling increases on the fringe of a typhoon; you should?
Your Answer: (Not answered)
Correct Answer: A (adjust course and speed to avoid resonance and secure cargo)
💡 Alter course and speed away from resonance, secure cargo and gear, keep weather reception and reporting.
✗
Question 33. The significance of the display requirement for certificates is?
Your Answer: (Not answered)
Correct Answer: A (allow crew and inspectors to verify validity readily)
💡 Displaying key certificates lets crew track validity and inspectors verify quickly, avoiding delays.
✗
Question 34. The focus of the duty officer's role during cargo work is?
Your Answer: (Not answered)
Correct Answer: B (monitor draught, trim, list and mooring loads keeping terminal contact)
💡 Watch draught, list, moorings and gangway with terminal contact, stopping work if anything looks wrong.
✗
Question 35. The relationship between SOLAS Chapter IX and the ISM Code?
Your Answer: (Not answered)
Correct Answer: B (SOLAS Chapter IX makes ISM mandatory)
💡 SOLAS Chapter IX incorporates the ISM Code, making it mandatory for applicable ships.
✗
Question 36. Under Chapter 10 of the ISM Code, what should the company establish to keep the ship and her equipment fit for safe operation?
Your Answer: (Not answered)
Correct Answer: D (a planned maintenance system with scheduled tests and records)
💡 Chapter 10 asks for a system, not a logbook: makers' manuals, statutory items and the ship's own experience combined into a schedule with owners, intervals and completion marks, including tests of critical equipment. A break-down record only proves something failed, a budget sheet manages money, and a charter-party does not shift the company's duty.
✗
Question 37. What is the main problem with prolonged low load operation?
Your Answer: (Not answered)
Correct Answer: D (fouling, deposits and poor combustion leading to later failures)
💡 Low load fouls combustion spaces and turbochargers and causes cold corrosion; follow maker guidance on operation and maintenance.
✗
Question 38. Where should ballast water management system operations be recorded?
Your Answer: (Not answered)
Correct Answer: B (the Ballast Water Record Book)
💡 Ballast operations are logged in the Ballast Water Record Book with area, system operation and anomalies for port State checks.
✗
Question 39. Company communication with crew about an incident should?
Your Answer: (Not answered)
Correct Answer: B (transparent, timely with follow-up actions to maintain trust)
💡 Brief the crew transparently on developments and safeguards to prevent rumours and preserve trust.
✗
Question 40. Which is NOT a purpose of the ship's technical files?
Your Answer: (Not answered)
Correct Answer: B (replacing on-scene inspection and judgement)
💡 Technical files support decisions but never replace on-scene inspection and professional judgement.
✗
Question 41. What does "ready for use" mean for emergency equipment?
Your Answer: (Not answered)
Correct Answer: C (fixed location, serviceable, clearly marked and crews trained to use it)
💡 Emergency gear needs fixed stowage, checks, marking and trained users; missing one fails at the critical moment.
✗
Question 42. What document must the ship hold before loading dangerous goods?
Your Answer: (Not answered)
Correct Answer: B (the dangerous goods declaration and the document of compliance for carriage)
💡 Before loading, hold the shipper's declaration and the ship's compliance document, matching name, class, quantity and stowage.
✗
Question 43. Who normally owns the survey expiry alert?
Your Answer: (Not answered)
Correct Answer: A (shared by the company SMS owner and the master)
💡 The company keeps the register and books surveys; the master tracks validity and reminds the company.
✗
Question 44. The ISPS Code is made mandatory under which SOLAS chapter, and when did it enter force?
Your Answer: (Not answered)
Correct Answer: A (Chapter XI-2, in force 1 July 2004)
💡 The ISPS Code is mandatory under SOLAS Chapter XI-2, in force 1 July 2004.
✗
Question 45. Management of onboard first aid kits and medicines should?
Your Answer: (Not answered)
Correct Answer: D (kept by a responsible person, expiry checked and restocked, prescription drugs on medical advice)
💡 A designated officer checks expiry and stock with records; controlled drugs need dual custody and medical advice.
✗
Question 46. The relationship between interim and permanent measures is?
Your Answer: (Not answered)
Correct Answer: A (interim measures control risk first; permanent ones remove the cause and replace them)
💡 Control risk temporarily first such as speed limits or isolation, then apply permanent fixes and verify.
✗
Question 47. The correct way to correct an error in the deck logbook is?
Your Answer: (Not answered)
Correct Answer: C (strike through keeping the original legible, annotate and sign with date)
💡 Strike one line leaving the original readable, annotate and sign with date; never erase, tear or cover.
✗
Question 48. When sailing near a high-threat port, security level rises 2 to 3; the ship should?
Your Answer: (Not answered)
Correct Answer: C (immediately apply SSP Level 3 measures, check restricted areas and comms)
💡 Level change must trigger specific SSP extras: patrols, boarding limits, comms.
✗
Question 49. The role of positive feedback in supervision is?
Your Answer: (Not answered)
Correct Answer: D (reinforce correct practice, raise engagement and balance correction)
💡 Fault-finding alone makes people avoid supervision; recognising good practice raises engagement and openness.
✗
Question 50. Are technical management and ship energy efficiency the same thing?
Your Answer: (Not answered)
Correct Answer: C (hull and propeller condition and the engine's state set the baseline; neglect cancels saving)
💡 The efficiency figure is computed from the technical state the ship is in: hull condition and the antifouling, the propeller's finish and geometry, the engine's injection and turbocharger state, shaft load and waste-heat use together fix how much fuel a given speed costs. Fouling and roughness under the water, pitted blades, dirty scavenge spaces and poor injectors eat back what slow steaming, route optimisation and add-on devices have saved. Technical management is therefore the base work under energy efficiency, and the efficiency monitoring points back at the plant: fuel and speed logged per voyage, condition assessed, cleaning intervals planned, and an anomaly chased in the equipment before it is chased in the numbers.
✗
Question 51. Execution of critical operations (e.g. enclosed-space entry, bunkering) shall be?
Your Answer: (Not answered)
Correct Answer: C (record key steps and confirmations per instruction)
💡 Critical operations require recorded steps and sign-offs for verification and traceability.
✗
Question 52. Key actions in a master's takeover are?
Your Answer: (Not answered)
Correct Answer: A (check certificates and open items, learn people and equipment and complete records)
💡 Systematically check certificates, open NCs, equipment and people, sign the handover and note actions and risks.
✗
Question 53. What is the main risk of excessive speed on berthing?
Your Answer: (Not answered)
Correct Answer: A (impact energy rises sharply, damaging ship and shore structures)
💡 Impact energy rises with the square of speed; speed control with tugs and engines is the core of safe berthing.
✗
Question 54. What mainly determines whether a spare is critical?
Your Answer: (Not answered)
Correct Answer: D (whether failure would cause loss of control, detention or an accident)
💡 Critical spares are judged by consequence: propulsion, steering, fire, lifesaving and pollution prevention.
✗
Question 55. The role of a designated spokesperson in an emergency is?
Your Answer: (Not answered)
Correct Answer: A (unify external messaging so multiple people do not contradict each other)
💡 A single spokesperson prevents contradiction and speculation, releasing only verified information and protecting credibility.
✗
Question 56. Under the ISM Code, who bears the ultimate responsibility for ship safety and pollution prevention?
Your Answer: (Not answered)
Correct Answer: A (the Company (shipowner or bareboat charterer))
💡 ISM Rule 5: the Company (shipowner or bareboat charterer) bears ultimate responsibility for safety and pollution prevention.
✗
Question 57. When safety spend conflicts with profit, the SMS requires?
Your Answer: (Not answered)
Correct Answer: C (safety floor first, resources tilted to major risks)
💡 Safety is a non-negotiable floor, never sacrificed to short-term profit.
✗
Question 58. Once the company emergency response team (ERT) activates, its first task is?
Your Answer: (Not answered)
Correct Answer: C (establish the situation, stabilise shipboard conditions, protect personnel and coordinate resources)
💡 The ERT first supports the ship: establish facts, stabilise, protect lives and mobilise resources.
✗
Question 59. When deficiencies are listed and signature requested, the master should?
Your Answer: (Not answered)
Correct Answer: B (sign after confirming facts, noting disagreement in writing if any)
💡 Signature confirms receipt not liability; note reservations in writing, never refuse or alter the report.
✗
Question 60. The correct positioning of energy efficiency management in the SMS is?
Your Answer: (Not answered)
Correct Answer: A (embed efficiency into SMS objectives, procedures and assessment)
💡 Companies should set efficiency targets with measures, owners, monitoring and review within the SMS.
✗
Question 61. How long should crew change documents and records be kept?
Your Answer: (Not answered)
Correct Answer: C (kept for the period set by company and law for inspection and disputes)
💡 Crew change records are evidence for inspection and disputes; keep them for the required period and retrievable.
✗
Question 62. Ship technical files (drawings, certificates, TM, repairs) should be?
Your Answer: (Not answered)
Correct Answer: B (systematically archived and traceable, supporting maintenance and transfer)
💡 Complete technical files underpin maintenance and transactions.
✗
Question 63. A corrective action plan should contain?
Your Answer: (Not answered)
Correct Answer: A (the action, responsible person, deadline and verification method)
💡 Include what, who, by when and how effectiveness will be verified so items can be tracked and closed.
✗
Question 64. Shore technical support to the ship should show in?
Your Answer: (Not answered)
Correct Answer: A (timely advice, repair plans and spares, tracking defect closure)
💡 Shore technical backing keeps equipment reliable.
✗
Question 65. How does safety leadership show at shore management level?
Your Answer: (Not answered)
Correct Answer: C (safety first in decisions, resources provided, personal participation)
💡 Shore leadership shows in trade-offs, resourcing and personal involvement, not in slogans alone.
✗
Question 66. When a newbuild or heavily converted ship enters service, the system should?
Your Answer: (Not answered)
Correct Answer: C (adapt documents, run familiarisation training and evaluate during the trial period)
💡 New or converted ships differ greatly; adapt documents, train crews and validate the system during trials.
✗
Question 67. When asked to demonstrate equipment on the spot, the correct response is?
Your Answer: (Not answered)
Correct Answer: D (have a competent crew member demonstrate properly and state routine frequency)
💡 Let trained crew demonstrate and explain routine use; never let the unfamiliar improvise and expose more gaps.
✗
Question 68. What distance from land and depth apply to ballast water exchange?
Your Answer: (Not answered)
Correct Answer: B (at least two hundred nautical miles from land and two hundred metres deep)
💡 Exchange must occur at least two hundred miles from land in two hundred metres of water, failing which other options apply.
✗
Question 69. Class requires defects found during survey to be rectified within a time limit; the SMS should?
Your Answer: (Not answered)
Correct Answer: A (record it as a non-conformity with corrective action, assign an owner and verify closure)
💡 External survey findings enter the non-conformity system with owner, deadline and verified closure.
✗
Question 70. Who first knows that something is wrong with the machinery?
Your Answer: (Not answered)
Correct Answer: B (the watchkeeper and those walking the rounds - whether they report and when decides whether the intervention comes before or after the failure)
💡 The first signs of a fault are usually with the watch, in the eye, ear and hand: temperature, vibration, a smell, a weep, a change of note. Whether they report and how quickly settles whether intervention falls before the failure or after it. What the system therefore has to supply is not feeling but a standard to judge by - the round sheet, the parameter limits - a report route that costs little to use, and an answer that shows the report went somewhere; after twice of reporting into silence nobody reports. An alarm covers only the quantities it was designed to see, and a sensor drifting or a part wasting below its threshold makes no sound. The monthly return shows averages, which is exactly the data that smooths an anomaly away.
✗
Question 71. The usual system-level attribution of a technical failure is?
Your Answer: (Not answered)
Correct Answer: A (inadequate maintenance, missing spares, poor training or weak oversight)
💡 Most technical failures have system roots in maintenance intervals, spares, training or supervision.
✗
Question 72. Why must emergency messages be concise and accurate?
Your Answer: (Not answered)
Correct Answer: D (let recipients understand fast and decide correctly, avoiding misjudgement)
💡 Channels and time are scarce; messages must carry key facts briefly, since vagueness or length delays rescue.
✗
Question 73. What is the core requirement of a watch handover?
Your Answer: (Not answered)
Correct Answer: B (face to face, the state of the watch and what is outstanding said through, leaving no gap in the information)
💡 It has to be face to face and confirmed by both: the position and course held during the watch, weather and sea, traffic and hazards, anything abnormal or under a limitation in the equipment, when the pilot or tugs are due, what orders have been received, what remains to be done and which settings are not to be changed - each said through, and taken over only when the man coming on has asked or repeated it back. If he is not yet fit to carry the watch - tired, ill, under drink - the watch is not handed over and the master is told instead. A signature in a book is not a handover, a telephone call afterwards is a rescue rather than a practice, and sending the man to walk round by himself leaves the hardest information where it was, such as the pump that has been making that noise for two hours.
✗
Question 74. What does the passage plan have to take on before ice?
Your Answer: (Not answered)
Correct Answer: A (arrangements for handling and lookout in ice, protection against freezing, clearing ice from deck, and a plan of refuge)
💡 What the plan takes on for ice: how far the ship's ice class and structure let her go into the ice, where the ice report and the forecast come from, the limits on speed and steering (a ship cannot be handled in ice as in open water), how lookout and the uncertainty of position are managed, protection against freezing of cooling water lines and deck piping, non-slip and ice clearing on deck, what fire and life-saving gear does at low temperature, the behaviour of fuel and lubricating oil in cold, the way out if heavy ice is met and where to take refuge, and the contact with icebreaker or escort. None of this is recovered by improvising on the spot, and every line needs both a man who can do it and the gear to do it with.
✗
Question 75. Which sea areas does GMDSS mainly cover?
Your Answer: (Not answered)
Correct Answer: A (areas A1, A2, A3 and A4)
💡 GMDSS divides oceans into A1 (VHF), A2 (MF), A3 (satellite) and A4 (polar) with different carriage requirements.
✗
Question 76. How should watchkeeping be maintained while in port?
Your Answer: (Not answered)
Correct Answer: B (keep sufficient crew aboard with regular rounds meeting manning and response needs)
💡 Keep enough qualified crew aboard for rounds, manning minimums and emergency response, especially during cargo or bunkering.
✗
Question 77. Which best shows systematic ballast water management?
Your Answer: (Not answered)
Correct Answer: A (plan, duties, training, records and self-checks forming a closed loop)
💡 Systematic management means a closed loop of documents, duties, training, records and improvement, not equipment alone.
✗
Question 78. The role of operations scheduling within the SMS should be?
Your Answer: (Not answered)
Correct Answer: C (optimise the schedule within safety constraints and consult the master)
💡 Scheduling works within legal and SMS limits and consults the master; commerce never overrides safety.
✗
Question 79. On a major casualty/security event, the Company should activate?
Your Answer: (Not answered)
Correct Answer: D (a crisis team for unified external coordination and decisions)
💡 Crisis management centralises command, preventing conflicting orders.
✗
Question 80. The foundation of corrosion protection is?
Your Answer: (Not answered)
Correct Answer: A (proper surface preparation, correct coating system and timely touch-ups)
💡 Protection depends on surface prep, primer, system and film thickness plus prompt repair, not topcoat alone.
✗
Question 81. Why re-check cargo securing during the voyage?
Your Answer: (Not answered)
Correct Answer: C (lashings slacken with motion; re-tightening prevents cargo shift)
💡 Lashings slacken under motion, so re-tension them especially after heavy weather to prevent bulk cargo shift.
✗
Question 82. Can the Master's final responsibility onboard for safety/pollution be delegated to the C/O or C/E?
Your Answer: (Not answered)
Correct Answer: D (No; the Master personally retains final responsibility)
💡 The Master's final responsibility is statutory and non-delegable; tasks may be assigned but the responsibility remains.
✗
Question 83. In fog, how are the lookout and the engines handled?
Your Answer: (Not answered)
Correct Answer: C (post extra lookouts, work the radar, show the lights, sound the fog signal, ease off speed and get the engines ready)
💡 In restricted visibility the ship must strengthen seeing, hearing and being seen at the same time: extra lookouts including the bow and a listening watch, radar worked properly with plotting to identify neighbours and objects, navigation lights and fog signal as required, and speed reduced so that the ship can be stopped within what the visibility and the state of affairs then allow. The engines stand ready for immediate manoeuvring, the steering gear and emergency steering arrangements stay available, communications remain manned, and anchoring or waiting in safe water is used where sensible. Switching gear off to cut clutter, reading traffic off the displays alone, or lengthening the radar scale while keeping speed all hand the risk to the instruments.
✗
Question 84. When a man-overboard is not noticed immediately, afterwards you should?
Your Answer: (Not answered)
Correct Answer: A (act at once on MOB procedures, alert others and organise a search)
💡 Even if late, start MOB procedures, mark the position, alert VTS and nearby ships and search without delay.
✗
Question 85. When language barriers hinder communication, you should?
Your Answer: (Not answered)
Correct Answer: C (arrange someone with the needed or English language ability to assist)
💡 Provide a communicating crew member or shore interpreter; failed communication itself may become a deficiency.
✗
Question 86. A common consequence of being blacklisted is?
Your Answer: (Not answered)
Correct Answer: C (much more frequent inspection and lower acceptance by insurers and charterers)
💡 Blacklisting raises inspection frequency and insurance cost and cuts charterer acceptance, hard to reverse.
✗
Question 87. What is the order of priority in onboard medical first aid?
Your Answer: (Not answered)
Correct Answer: D (make the scene safe, then assess consciousness, breathing and circulation and treat)
💡 Make the scene safe for the rescuer first, then assess and treat airway, breathing and circulation to avoid secondary casualties.
✗
Question 88. The company asks for something that looks wrong. What should a seafarer do?
Your Answer: (Not answered)
Correct Answer: A (raise the concern through the channel the system provides, keep the record, go above the usual line if needed)
💡 This channel is what the system exists to protect: report along the line stated in the documents, to the master and the designated person ashore, writing down the time, the instruction, the operation involved and the concern, and keep a copy. Against an order touching safety or pollution prevention the master has both the right and the duty to withhold execution until conditions allow. Where the channel is blocked or the answer never comes, he may go above it - to senior management, the flag or port state, the union or a watchdog - and the protection of seafarer complaints means the company may not let the reporter the worse for it on board. Resigning only removes one man from one voyage; grumbling leaves no evidence and changes no operation.
✗
Question 89. How does hull fouling affect energy efficiency?
Your Answer: (Not answered)
Correct Answer: B (it raises resistance and fuel use, cutting speed and worsening carbon rating)
💡 Fouling raises frictional resistance, increasing fuel use and worsening carbon intensity; cleaning and underwater maintenance are system measures.
✗
Question 90. Observable signals of good versus poor safety culture include?
Your Answer: (Not answered)
Correct Answer: B (whether hazard reporting is encouraged and violations faced not hidden)
💡 Culture shows in whether problems are spoken, not in surface shine.
✗
Question 91. The common risk of schedule-driven haste is?
Your Answer: (Not answered)
Correct Answer: A (sacrificing safety margins causing aggressive handling and violations)
💡 Schedule pressure induces speeding, skipped checklists and deferred maintenance; contain it with explicit rules.
✗
Question 92. What is the master's first key role in an emergency?
Your Answer: (Not answered)
Correct Answer: A (establish command and an information hub keeping the overall picture)
💡 In emergencies the master commands, holds the whole picture and assigns tasks; operating gear himself loses overall control.
✗
Question 93. A feature of Inmarsat-C compared with FleetBroadband is?
Your Answer: (Not answered)
Correct Answer: C (low bandwidth messaging with distress priority)
💡 Inmarsat-C is low-rate store-and-forward messaging with EGC, reliable but not broadband voice or video.
✗
Question 94. What is required regarding notifying insurers after an incident?
Your Answer: (Not answered)
Correct Answer: B (notify promptly as the policy requires and preserve scene evidence and records)
💡 Policies require prompt notice; delay harms cover, so report at once and preserve evidence and records.
✗
Question 95. What is confirmed with the terminal before departure?
Your Answer: (Not answered)
Correct Answer: A (completion of cargo, signed documents and conditions for letting go lines)
💡 Confirm cargo is complete, documents are signed and conditions for letting go are met, coordinating tugs and sequence.
✗
Question 96. For a tanker SMS to truly work, it must?
Your Answer: (Not answered)
Correct Answer: B (be specific to this ship's type, equipment and trade, not a copied template)
💡 A template detached from the actual ship fails under tanker risk—a classic PSC finding.
✗
Question 97. A ship's Oil Record Book does not match reality and the master admits falsification. What should the company do?
Your Answer: (Not answered)
Correct Answer: A (report to the Administration, investigate and impose corrective accountability)
💡 Falsified statutory records are serious: report, investigate root causes and correct rather than conceal.
✗
Question 98. What is the purpose of periodic onboard drills?
Your Answer: (Not answered)
Correct Answer: A (maintain emergency response capability and reveal gaps in the plan)
💡 Drills maintain competence and test whether plans work, a key way to find problems and improve the system.
✗
Question 99. The first choice for external emergency communication is?
Your Answer: (Not answered)
Correct Answer: D (use VHF, MF/HF or satellite distress calling as appropriate to the area)
💡 Use the appropriate distress path for the area and equipment—DSC VHF, MF/HF or satellite—and keep watch.
✗
Question 100. Which ships must carry Emergency Towing Arrangements (ETA/EMT)?
Your Answer: (Not answered)
Correct Answer: D (large tankers etc. per rules at bow and stern)
💡 Large tankers must fit bow/stern emergency towing arrangements to aid salvage and prevent spills.