Question 1. Where must the water ingress alarm of a bulk carrier be displayed?
Your Answer: (Not answered)
Correct Answer: B (On the navigation bridge, so the watchkeeper learns at once of flooding in a hold)
💡 SOLAS XII/12 requires the water ingress detection alarm of a bulk carrier to be displayed on the bridge so the officer of the watch can identify the flooded hold and act immediately. Display elsewhere delays response.
✗
Question 2. What are the limitations on the use of the automatic pilot?
Your Answer: (Not answered)
Correct Answer: B (Hand steering must be resumed in restricted visibility, dense traffic, narrow channels or when frequent manoeuvring is required)
💡 STCW and SOLAS require hand steering to be resumed in restricted visibility, dense traffic, narrow channels or when frequent manoeuvring is needed on ships using an automatic pilot. The autopilot does not reduce the number of look-outs required and the officer must be ready to steer by hand at any time.
✗
Question 3. What is the requirement for testing life-saving appliances?
Your Answer: (Not answered)
Correct Answer: C (They shall be examined and tested at prescribed intervals)
💡 All life-saving appliances shall be examined and tested at the prescribed intervals.
✗
Question 4. What must be recorded for an abandon ship drill under SOLAS?
Your Answer: (Not answered)
Correct Answer: C (The date, the details of the drill, the survival craft used and the persons taking part)
💡 SOLAS requires the date, details, equipment used and participation of abandon ship and fire drills to be recorded in the deck log for verification at surveys and PSC. A date or a head count alone is incomplete.
✗
Question 5. What is the general requirement for the location of embarkation stations?
Your Answer: (Not answered)
Correct Answer: A (Where persons can board safely, as far as practicable from the propulsion plant and dangerous goods)
💡 SOLAS requires embarkation stations to be located where persons can board safely, taking account of the need to be clear of propellers, thrusters, exhausts and dangerous goods, so that persons are not injured while boarding and the operation is possible even if the ship still has headway.
✗
Question 6. From what source must emergency lighting in accommodation spaces and escape routes be supplied?
Your Answer: (Not answered)
Correct Answer: C (From the emergency source, automatically connected when the main source fails)
💡 SOLAS requires emergency lighting in escape routes and accommodation to be supplied from the emergency source and connected automatically when the main source fails, without manual switching. Main source supply would not illuminate when power is lost.
✗
Question 7. The watertight door indicator showed a door open while it was in fact closed. What is the finding?
Your Answer: (Not answered)
Correct Answer: B (A deficiency; the indicator must accurately reflect the actual status, as a false indication misleads the assessment of watertight integrity)
💡 The watertight door indicator on the bridge must accurately reflect the actual open or closed status. A false indication would lead the watchkeeper to a wrong appreciation of watertight integrity and to incorrect measures after damage, so it is a deficiency affecting safety.
✗
Question 8. What is required for backup power of the firefighting system?
Your Answer: (Not answered)
Correct Answer: C (The emergency fire pump must have a source of power independent of the main fire pumps, so water is available on a blackout or machinery space fire)
💡 SOLAS requires the emergency fire pump to be independently driven, such as by a dedicated diesel engine or an independent power supply, so that it can still supply water if a blackout or a fire in the machinery space puts the main fire pumps out of action. It is essential to the redundancy of the firefighting system.
✗
Question 9. What corridor length limit does SOLAS address in the escape requirements for accommodation spaces?
Your Answer: (Not answered)
Correct Answer: B (An enclosed corridor exceeding 13 m must have escape routes at both ends)
💡 SOLAS II-2/13 requires an enclosed corridor more than 13 m long to have access to escape routes at both ends, so that persons are not trapped in a long corridor with a single exit.
✗
Question 10. What preparation is required before new equipment is brought into use?
Your Answer: (Not answered)
Correct Answer: A (Familiarisation training completed, procedures and checklists revised and the item included in the maintenance programme)
💡 Before new or replacement equipment is brought into use, the crew should complete familiarisation training covering operation, emergencies and maintenance, the relevant procedures and checklists be revised, the item included in the maintenance programme and the effect on the system documentation considered, preventing errors from unfamiliarity.
✗
Question 11. What is the principal purpose of port State control?
Your Answer: (Not answered)
Correct Answer: B (Ensuring compliance and eliminating substandard ships)
💡 Port State control aims to eliminate substandard shipping, not to raise revenue.
✗
Question 12. Lifeboat and liferaft launching appliances shall be capable of operating when the ship is trimmed by:
Your Answer: (Not answered)
Correct Answer: A (not more than 10°)
💡 SOLAS III/16 requires launching appliances to operate with the ship trimmed up to 10° and listed up to 20°.
✗
Question 13. What does SOLAS require for communication between the bridge and machinery space?
Your Answer: (Not answered)
Correct Answer: B (Reliable means must be provided so that the bridge and machinery space can communicate at all times)
💡 SOLAS requires reliable means of communication, such as telegraph or telephone, between the bridge and machinery space at all times. A mobile phone is not an acceptable compliant means.
✗
Question 14. How should launching drills be organised on a ship fitted with free-fall lifeboats?
Your Answer: (Not answered)
Correct Answer: A (Launch drills at least every three months, with actual release at the longer interval prescribed)
💡 SOLAS III/19.3.3 prescribes launch and recovery drills for free-fall lifeboats, with the interval for actual free-fall release being longer than that for conventional lifeboats, not monthly.
✗
Question 15. What checks are required after cargo operations on a tanker?
Your Answer: (Not answered)
Correct Answer: A (Confirm valves closed, lines depressurised and drained properly and the deck free of oil before standing down)
💡 After cargo operations on a tanker the procedure requires confirmation that the relevant valves are closed, the lines depressurised and drained, residual oil and drips dealt with, the deck clean and free of oil and the inert gas system normal, with a record made, before standing down, preventing danger from residual vapour.
✗
Question 16. Before a container is packed a packing certificate must be signed. Who issues this document?
Your Answer: (Not answered)
Correct Answer: B (The container packing certificate, issued by the person or organisation responsible for packing)
💡 SOLAS VII/6 requires the container packing certificate to be issued by the person or organisation that packed the container, confirming compliance with the IMDG Code. The master, who is not the packer, cannot issue it.
✗
Question 17. How many SARTs must a ship normally carry under SOLAS?
Your Answer: (Not answered)
Correct Answer: B (Two, normally sited on either side of the bridge for rapid access)
💡 SOLAS IV/7 requires two SARTs on cargo ships of 300 GT and above, normally sited on either side of the bridge for rapid access. A single SART cannot serve rescuing vessels approaching from either side.
✗
Question 18. A ship was detained by PSC and, after rectification, released following re-inspection by a recognised organisation. Under SOLAS, who issues the relevant certificate?
Your Answer: (Not answered)
Correct Answer: C (The Administration or a person duly authorised by it)
💡 The power to issue certificates rests with the Administration. A recognised organisation may act only within the scope of a formal authorisation given by that Administration.
✗
Question 19. What is the purpose of the automatic closing and hold-back release arrangements of fire doors?
Your Answer: (Not answered)
Correct Answer: D (To enable the doors to be held open for passage in normal service and to close automatically on a fire alarm to maintain the fire division)
💡 Under SOLAS II-2/9 fire doors required to be self-closing should be fitted with automatic closing arrangements and, where necessary, hold-back release arrangements that release the door on detection of a fire. The door may be held open in normal service for passage and ventilation and closes automatically on a fire alarm to maintain the fire division. The arrangements should be tested regularly.
✗
Question 20. During a PSC inspection the lifeboat engine is started and fails several times in a row. The finding is?
Your Answer: (Not answered)
Correct Answer: B (The lifeboat cannot be used reliably, a serious deficiency that may lead to detention)
💡 A lifeboat engine should start reliably at any time, being essential for manoeuvring and clearing the casualty after abandonment. Repeated failure shows the lifeboat cannot be reliably put into use, a deficiency seriously affecting life-saving capability that may normally lead to detention.
✗
Question 21. What does SOLAS require where a ventilation duct passes through a class B division?
Your Answer: (Not answered)
Correct Answer: B (Measures must be taken at the penetration to maintain the smoke and fire integrity of the division)
💡 SOLAS requires the integrity of a class B division to be maintained where a duct passes through, normally by a sleeve or fire-stopping arrangement. Otherwise the duct becomes a path for smoke and fire.
✗
Question 22. A PSC inspection found a pilot ladder with unevenly spaced steps. What does SOLAS require?
Your Answer: (Not answered)
Correct Answer: A (Pilot ladders must comply with the standard, which specifies step spacing, ropes and securing arrangements)
💡 SOLAS V/23 and the IMO standards prescribe step spacing, materials, rope diameter and securing arrangements for pilot ladders. Uneven spacing can cause a pilot to miss a step and fall, a common deficiency.
✗
Question 23. What does SOLAS address regarding the equilibrium condition in damage stability calculations?
Your Answer: (Not answered)
Correct Answer: B (After flooding the ship must satisfy the residual stability criteria in the equilibrium condition)
💡 SOLAS requires that, once the ship reaches equilibrium after flooding, taking account of the water entered and the resulting heel, the residual stability curve satisfies the prescribed criteria such as the range of righting levers and the maximum righting lever. Intact stability criteria alone are not a substitute.
✗
Question 24. What do SOLAS and STCW require regarding the use of the automatic pilot?
Your Answer: (Not answered)
Correct Answer: B (A proper look-out must be kept, and hand steering must be resumed in restricted visibility or dense traffic)
💡 STCW and SOLAS require a proper look-out to be maintained when the automatic pilot is engaged, and hand steering to be resumed in restricted visibility, dense traffic or narrow channels. Automatic steering does not permit relaxation of watchkeeping.
✗
Question 25. From where shall the valves of fuel oil tanks be capable of being closed?
Your Answer: (Not answered)
Correct Answer: A (Remotely from outside the space)
💡 SOLAS requires remote closing from outside the space so the fuel supply can be shut off in case of fire.
✗
Question 26. Who provides long-range identification and tracking information?
Your Answer: (Not answered)
Correct Answer: D (The flag State)
💡 The flag State.
✗
Question 27. What quantity of fresh water is provided per person in the equipment of a lifeboat?
Your Answer: (Not answered)
Correct Answer: A (Three litres per person)
💡 Under SOLAS III/34 and the equipment requirements for lifeboats, three litres of fresh water should be provided for each person the boat is permitted to accommodate. Fresh water and food are basic provisions for survival after abandonment and a drinking vessel should also be provided.
✗
Question 28. The double-side-skin requirement for new bulk carriers does not apply to every bulk carrier. What triggers it?
Your Answer: (Not answered)
Correct Answer: B (new bulk carriers of 150 metres in length and upwards, of single skin construction, intended to carry solid bulk cargo of a density of 1000 kg per cubic metre or greater)
💡 The line is drawn by length and cargo density: new bulk carriers of 150 metres in length and upwards, of single skin construction and intended for solid bulk cargo of a density of 1000 kg per cubic metre or greater, must have double side spaces, so that a breach in the side leaves reserve buoyancy and slows flooding. Carriers of lighter grain and ships under that length fall outside the regulation while still meeting other stability and structural requirements.
✗
Question 29. Between completing a renewal survey and the issue of a new certificate, what measure may allow the ship to complete her voyage?
Your Answer: (Not answered)
Correct Answer: A (An extension of the existing certificate in specified circumstances, enabling the ship to reach the port of survey or complete the current voyage)
💡 SOLAS permits a limited extension of a certificate in specified circumstances so the ship may complete the voyage or reach the port of survey. The extension must be within the rules and recorded; the old certificate may not be used indefinitely.
✗
Question 30. What does SOLAS require regarding local and remote operation of watertight doors?
Your Answer: (Not answered)
Correct Answer: B (They must be operable locally from both sides of the door and closable remotely from the bridge)
💡 SOLAS requires watertight doors to be operable locally from both sides of the door and closable by remote control from the bridge. Both means must be available; one alone does not comply.
✗
Question 31. Which systems may be used as fixed fire-extinguishing systems in machinery spaces?
Your Answer: (Not answered)
Correct Answer: C (approved gas, pressure water-spraying or foam systems)
💡 SOLAS II-2/10: approved fixed gas, pressure water-spraying or foam systems may be used in machinery spaces.
✗
Question 32. Which statement of the conditions for discharging food waste at sea is correct?
Your Answer: (Not answered)
Correct Answer: C (waste ground past the prescribed screen at three miles and more from land, unground at twelve miles and more)
💡 The Annex sets two standards for food waste: ground or comminuted enough to pass a screen of the prescribed aperture, no more than twenty-five millimetres, may go overboard three miles or more from the nearest land; food waste not so reduced must wait until twelve miles. Any discharge is to be made as far from land as practicable and is entered in the garbage record book; inside harbour limits, at anchor and in certain special areas the rules tighten, and some seas call for a finer screen, so what governs is the water the ship is in at the moment and the text then in force. Plastic is a different matter and may never be discharged at any distance or in any state. Answering "never allowed" or "allowed anywhere" misses the distinction the Annex draws.
✗
Question 33. What do SOLAS and the related standards address regarding electromagnetic compatibility of radio equipment?
Your Answer: (Not answered)
Correct Answer: C (Equipment must not cause harmful interference and must not be rendered ineffective by interference from other equipment)
💡 SOLAS and the IEC standards require ship radio equipment to be electromagnetically compatible, neither disturbing other equipment such as navigational aids nor being rendered ineffective by interference from them.
✗
Question 34. What is the period of validity of the International Ship Security Certificate?
Your Answer: (Not answered)
Correct Answer: C (Not more than five years)
💡 SOLAS XI-2 provides that the ISSC is valid for not more than five years, with intermediate verification arranged separately. It is not valid indefinitely.
✗
Question 35. How many lifebuoys must be fitted with a buoyant lifeline under SOLAS?
Your Answer: (Not answered)
Correct Answer: B (A prescribed number must have a buoyant lifeline, not fewer than the stated figure)
💡 SOLAS requires a prescribed number of lifebuoys to be fitted with a buoyant lifeline for recovering a person overboard. Not every lifebuoy needs one; fitting a lifeline and fitting a light are two separate requirements.
✗
Question 36. A portable fire extinguisher is found without its securing bracket and may topple and be damaged in rough weather. The finding is?
Your Answer: (Not answered)
Correct Answer: C (Extinguishers should be properly secured and readily available; failure to secure is a deficiency to be corrected)
💡 A portable fire extinguisher should be secured in its designated position so that it is readily available and does not topple, collide and be damaged or cause injury as the ship rolls. Failure to secure it affects both availability and the risk of damage. It is a deficiency to be corrected.
✗
Question 37. After a casualty, what does SOLAS require of the Administration?
Your Answer: (Not answered)
Correct Answer: B (To conduct an investigation and, where useful, submit the findings to the Organization)
💡 SOLAS requires the Administration to investigate any casualty and to submit the findings to IMO where they may assist in improving the Convention. It is not left to the company or the insurer.
✗
Question 38. What is required if a particular drill cannot be held in a month?
Your Answer: (Not answered)
Correct Answer: B (It should be held as soon as conditions permit, normally within 24 hours, with the reason for the delay recorded in the log)
💡 SOLAS requires a drill not held in a month because of navigational conditions to be held as soon as conditions permit, normally within the following 24 hours, with the reason for the delay recorded in the deck log. Missing drills over several months is a serious deficiency.
✗
Question 39. What safety is required for lifting appliances at sea?
Your Answer: (Not answered)
Correct Answer: D (Use within the rated load, periodic inspection of wires and brakes and operation by trained persons)
💡 Lifting appliances should be used within the rated safe working load, with periodic inspection of the wires, brakes and limit switches and records kept, operated by trained persons and the slings and cargo securing checked before lifting. Overloading or using defective equipment causes casualties.
✗
Question 40. A ship needed to enter a cargo hold. The PSCO enquired about the enclosed space entry permit system. What does SOLAS require?
Your Answer: (Not answered)
Correct Answer: A (A permit system with testing of oxygen and harmful gases before entry and retention of records)
💡 SOLAS II-1/3-6 and the IMO resolutions require an entry permit system for enclosed spaces, with testing of oxygen (normally between 19.5 and 23 per cent) and toxic and flammable gases before granting the permit, and records retained.
✗
Question 41. After an accidental DSC distress alert is transmitted, what is the correct action?
Your Answer: (Not answered)
Correct Answer: A (Immediately transmit a cancellation to the relevant coast station or RCC)
💡 SOLAS and ITU procedures require an accidental alert to be cancelled immediately by a follow-up message to the coast station or rescue coordination centre. It must never be ignored.
✗
Question 42. What is required regarding the deck log book?
Your Answer: (Not answered)
Correct Answer: C (Navigational, watchkeeping and significant events must be entered truthfully as required, without alteration or falsification)
💡 SOLAS and good practice require the deck log to record the position, course and speed, weather, equipment condition and significant events truthfully and promptly. The log is important evidence in navigation and casualty investigation, and alteration or falsification has serious consequences.
✗
Question 43. What fire rating does SOLAS normally require for the boundaries of main vertical zones?
Your Answer: (Not answered)
Correct Answer: B (A-60 class)
💡 SOLAS requires the boundaries between main vertical zones to be class A-60 divisions, confining a fire to the zone in which it starts and preventing spread to adjacent zones.
✗
Question 44. A 120 m cargo ship has one lifeboat on each side. What does SOLAS require?
Your Answer: (Not answered)
Correct Answer: B (The capacity on each side must accommodate all persons, with at least one boat serving as a rescue boat)
💡 SOLAS requires the capacity on each side of a cargo ship to accommodate all persons on board, with at least one boat meeting the rescue boat requirements. Counting the two boats together would not ensure escape if one side were lost.
✗
Question 45. What does the weather criterion of the intact stability code examine?
Your Answer: (Not answered)
Correct Answer: B (a gust heeling lever added to that of the steady wind, the angle of heel and the downflooding angle retaining adequate margin)
💡 The criterion splits the wind into a steady pressure and a gust: the ship heels under the steady heeling lever and the gust pushes her further, the area under the righting lever curve having to exceed that under the wind levers, the gust heel staying within the fraction of the downflooding angle and inside the stated limit. Metacentric height or roll period alone cannot answer that question.
✗
Question 46. What do SOLAS and good practice address regarding safety at the purifier?
Your Answer: (Not answered)
Correct Answer: C (Adequate ventilation and guarding, preventing accumulation of oil mist and the risk of fire from spray)
💡 The purifier room should be well ventilated with guards and an oil mist alarm, preventing oil mist from accumulating and being ignited, and should be provided with fixed or portable extinguishing equipment. It is one of the higher fire risk locations in a machinery space.
✗
Question 47. In which spaces must ceilings and linings be of non-combustible material?
Your Answer: (Not answered)
Correct Answer: A (In enclosures of stairways and corridors forming escape routes)
💡 SOLAS requires non-combustible linings and ceilings in critical spaces such as stairway enclosures and corridors serving as escape routes, limiting the spread of fire and keeping the escape route safe.
✗
Question 48. A ship has double side skin, a single deck, top side tanks and hopper side tanks and carries ore in bulk. What is she under SOLAS XII/1?
Your Answer: (Not answered)
Correct Answer: D (A bulk carrier subject to the requirements of Chapter XII)
💡 SOLAS XII/1 defines a bulk carrier as a ship with a single deck, top side tanks and hopper side tanks intended primarily to carry dry cargo in bulk. An ore carrier meets the definition and must comply with Chapter XII.
✗
Question 49. What does SOLAS address regarding the fire and weathertight requirements for ventilators?
Your Answer: (Not answered)
Correct Answer: D (Closing devices must be fitted, able to shut off ventilation when required and maintain weathertightness)
💡 SOLAS requires ventilators to have closing devices that both shut off ventilation to control a fire and maintain weathertightness against the entry of sea water. A rain hood alone meets neither requirement.
✗
Question 50. The purpose of ships' routeing systems is to:
Your Answer: (Not answered)
Correct Answer: B (promote safe navigation and reduce the risk of collision and grounding)
💡 SOLAS V/10 requires compliance with adopted routeing systems to promote safety of life at sea.
✗
Question 51. What valves and fittings does SOLAS require on fire pumps?
Your Answer: (Not answered)
Correct Answer: A (A relief valve and pressure gauge on each pump, preventing overpressure damage to the piping)
💡 SOLAS requires a relief valve and pressure gauge on each fire pump, preventing overpressure damage when the discharge valve is closed or the line is blocked, with the gauge enabling the watchkeeper to judge the water supply.
✗
Question 52. Who must confirm the securing arrangement for cargo units under SOLAS and the CSS Code?
Your Answer: (Not answered)
Correct Answer: A (The master or chief officer, in accordance with the approved cargo securing manual)
💡 SOLAS VI/5 and the CSS Code require the securing arrangement to be determined in accordance with the approved cargo securing manual and confirmed by the master or the responsible officer as to position, number and pre-tension. It is not left to the terminal or the cargo owner.
✗
Question 53. What steering gear checks should be made before navigating in confined waters?
Your Answer: (Not answered)
Correct Answer: C (Check the steering gear alarms, test rudder movement and the rudder angle indicator and confirm the power and control systems are in order)
💡 Before navigating in confined waters such as a narrow channel or when berthing, the steering gear should be tested, the rudder angle indicator checked and the alarms and the power and control systems verified. A sudden steering failure in confined waters has serious consequences.
✗
Question 54. What are the capacity and pressure requirements of the emergency fire pump?
Your Answer: (Not answered)
Correct Answer: A (Capacity not less than forty per cent of the required total of the main fire pumps and able to maintain the required main pressure in any condition)
💡 Under SOLAS II-2/10 the emergency fire pump should have a capacity not less than forty per cent of the required total of the main fire pumps and be able to maintain the required pressure on the fire main in any condition, including the most unfavourable draught and trim. It should have an independent source of power and self-priming capability.
✗
Question 55. If the Inmarsat equipment fails while a ship is in sea area A3, what alternative does SOLAS permit?
Your Answer: (Not answered)
Correct Answer: A (Using MF/HF equipment to meet the distress and safety communication requirements)
💡 Where the primary satellite equipment fails, the ship must use MF/HF to maintain distress and safety communication in sea area A3. Reliance on another ship or on repair is not acceptable.
✗
Question 56. In which circumstances must the ship security assessment be updated?
Your Answer: (Not answered)
Correct Answer: C (On major changes to the ship's structure, manning or operations, or on a change in the security situation)
💡 ISPS Code Part A/6 requires the ship security assessment to be reviewed and updated on major changes to the ship's structure, personnel or operations, or on a security incident or change of security level, keeping it consistent with the actual situation.
✗
Question 57. Safety practice for the carriage of solid bulk cargoes shall follow:
Your Answer: (Not answered)
Correct Answer: A (the IMSBC Code)
💡 SOLAS VI/6: the carriage of solid bulk cargoes shall follow the IMSBC Code.
✗
Question 58. Who is normally responsible for checking the securing of cargo during the voyage?
Your Answer: (Not answered)
Correct Answer: A (The cargo officer or second officer)
💡 Routine checks of cargo securing are made by those responsible for cargo operations.
✗
Question 59. What are common reasons for a finding of ISM system failure during a PSC inspection?
Your Answer: (Not answered)
Correct Answer: B (Repeated serious deficiencies of the same kind, records seriously inconsistent with the ship, or the crew unfamiliar with key operations or emergency duties)
💡 Findings of system failure commonly rest on the recurrence of serious deficiencies of the same kind, showing corrective action has been ineffective, records seriously inconsistent with the ship, such as falsified drill records, the crew unfamiliar with the equipment they operate or with their emergency duties, and critical equipment long out of repair, all showing that the system is not being implemented effectively.
✗
Question 60. SOLAS Chapter XII mainly applies to which type of ship?
Your Answer: (Not answered)
Correct Answer: D (Bulk carriers)
💡 Bulk carriers.
✗
Question 61. Into how many classes does the IMDG Code divide packaged dangerous goods?
Your Answer: (Not answered)
Correct Answer: D (Nine)
💡 The IMDG Code divides packaged dangerous goods into nine classes by hazard type, for example Class 1 explosives, Class 2 gases and Class 3 flammable liquids. The number is fixed at nine.
✗
Question 62. The sea anchor in a lifeboat is used to:
Your Answer: (Not answered)
Correct Answer: A (keep the boat head to wind and reduce drift in rough seas)
💡 SOLAS III/34 requires a sea anchor to keep the boat head to wind and reduce drift.
✗
Question 63. On what is the safe speed a ship should be carrying at a given moment determined?
Your Answer: (Not answered)
Correct Answer: D (speed settled by visibility, traffic density, manoeuvring performance, wind and sea, draught and background light, so that the ship can stop in the distance appropriate to the conditions)
💡 Rule 6 makes safe speed a capability rather than a figure: ability to stop within the distance appropriate to the conditions and to take effective collision action. Visibility, traffic density, the ship's own stopping distance and turning ability, background lighting by night, wind, sea and rain, draught against the available depth, all count, and engines must be ready in a narrow channel or in fog. A port limit is an extra constraint: keeping under it is not the same as keeping Rule 6, and keeping Rule 6 may call for less than the limit.
✗
Question 64. What is the minimum number of two-way VHF radiotelephone sets for a cargo ship?
Your Answer: (Not answered)
Correct Answer: A (Three, with at least one on each side)
💡 Under SOLAS IV/7 a cargo ship should carry at least three two-way VHF radiotelephone sets, with at least one on each side and the remainder stowed such as on the bridge, so that they can be taken into the respective survival craft for on-scene communication during abandonment.
✗
Question 65. The engine telegraph is used to:
Your Answer: (Not answered)
Correct Answer: C (transmit main engine manoeuvring orders from the bridge to the engine room)
💡 SOLAS II-1/31 requires an engine telegraph for transmitting orders from the bridge to the engine room.
✗
Question 66. Each ship shall carry how many lifejackets for every person on board?
Your Answer: (Not answered)
Correct Answer: D (one per person)
💡 SOLAS III/7 requires one lifejacket for every person on board, with additional child lifejackets as required.
✗
Question 67. In a crossing situation, what principle governs the stand-on vessel's action?
Your Answer: (Not answered)
Correct Answer: C (keep course and speed at first; but once it is clear the give-way vessel is not acting as the rules require, take avoiding action alone)
💡 Where one of two vessels is to keep out of the way the other keeps course and speed - not a bar on moving but a predictable target offered to the other. The keeping has a condition: as soon as the stand-on vessel finds the give-way vessel plainly not acting as the rules require, she should act alone in the way best to avoid collision, and a turn to starboard generally serves better than one to port, which would put her across his bow. When collision cannot be avoided by the give-way vessel's action alone, she may depart from the rules. Easing ahead across his bow, doing his keeping-out-of-the-way for him, or stopping on the spot all throw away the predictability.
✗
Question 68. An EPIRB was found with an expired battery. What is the finding?
Your Answer: (Not answered)
Correct Answer: B (A deficiency; the battery must be within its expiry date, as an expired battery affects distress alerting capability)
💡 An expired EPIRB battery means the equipment cannot sustain the prescribed transmission period, normally not less than 48 hours, in a distress. This is a deficiency affecting distress alerting capability, and the battery or the equipment should be replaced at once with the release mechanism checked.
✗
Question 69. Each lifeboat shall be provided with equipment including:
Your Answer: (Not answered)
Correct Answer: B (a complete set including oars, compass, sea anchor, first-aid kit, etc.)
💡 SOLAS III/34 lists lifeboat equipment including oars, compass, sea anchor, first-aid kit, food and water.
✗
Question 70. Which parameters should normally be tested before entry into an enclosed space?
Your Answer: (Not answered)
Correct Answer: B (Oxygen content, flammable gas and toxic gases such as hydrogen sulphide and carbon monoxide)
💡 Testing should cover oxygen content, flammable gas concentration and toxic gases, commonly hydrogen sulphide and carbon monoxide. Testing only one parameter may overlook a lethal hazard, and judging by smell is even less reliable.
✗
Question 71. Which of the following is the "Company" the ISM Code means?
Your Answer: (Not answered)
Correct Answer: A (the owner of the ship, or any other organisation or person who has taken on the responsibility for operating it and agreed to take over the obligations the rules impose)
💡 The definition rests on two conditions: having taken the responsibility for operating the ship from the owner, and having agreed to take on the duties and liability the rules lay out. Whoever meets them may be the owner, a manager or a bareboat charterer, so a management agreement does not of itself leave the position with the registered owner; and a supplier who does routine maintenance or finds crew alone does not become it by that. The one recognised as the Company is the one to whom the document of compliance is issued, the party named in the safety management certificate must match, and the agreement between them should mark out responsibility, authority and resources so that no gap opens where neither side answers. What the owner owes in respect of the ship does not disappear with the delegation, yet the running of the system sits with whoever carries the operating responsibility. The organisation that issues the certificate is the administration or one recognised by it, and is not the Company as defined.
✗
Question 72. What confidentiality applies to the ship security plan?
Your Answer: (Not answered)
Correct Answer: C (Unauthorised access to its contents must be prevented, with the document marked and distribution restricted)
💡 The ISPS Code requires the ship security plan to be a confidential document, marked as such, with restricted distribution and protected against unauthorised access, including electronic versions, preventing the security measures from being circumvented. It may be shown to authorised persons on inspection.
✗
Question 73. What is the maximum length of a fire hose for use on the open deck?
Your Answer: (Not answered)
Correct Answer: B (20 m)
💡 On the open deck and in accommodation spaces the hose shall not exceed 20 m.
✗
Question 74. What are the main requirements for air pipes on the freeboard deck?
Your Answer: (Not answered)
Correct Answer: D (Their openings should have effective closing appliances, and the pipes should be so arranged that water cannot enter the tanks when the ship heels)
💡 Air pipes ventilate the tanks and their opening height and closing appliances must meet the requirements, ensuring that in conditions of heeling and boarding seas water cannot enter the tanks and affect stability and liquid management. The closing appliances should be kept effective and closed as required.
✗
Question 75. What is the main purpose of ship reporting systems?
Your Answer: (Not answered)
Correct Answer: A (To provide information on ship movements for search and rescue and safety of navigation)
💡 SOLAS V/11 establishes ship reporting systems to supply movement information for search and rescue and safety of navigation, not for commercial or charging purposes.
✗
Question 76. What isolation is required between ballast and cargo hold piping?
Your Answer: (Not answered)
Correct Answer: D (The ballast system must not be connected to the cargo spaces, preventing contamination or cross-connection affecting stability)
💡 SOLAS and MARPOL require the piping between the ballast system and the cargo holds or cargo tanks to be effectively isolated, by isolating valves, blanks or separate piping, preventing ballast water and cargo from cross-connecting, which would contaminate the cargo, cause abnormal stability or lead to an illegal discharge.
✗
Question 77. What rescue arrangement is required when entering an enclosed space?
Your Answer: (Not answered)
Correct Answer: B (A standby person at the entrance with rescue equipment and continuous communication)
💡 Entry into an enclosed space requires a standby person at the entrance, continuous communication and rescue equipment including breathing apparatus, so that immediate rescue is possible. Solo entry is a principal cause of multiple fatalities.
✗
Question 78. What is required regarding the difference between indicated and actual rudder angle?
Your Answer: (Not answered)
Correct Answer: D (The difference must be within the permitted tolerance and corrected if exceeded)
💡 SOLAS and good seamanship require the difference between the indicated and actual rudder angle to be within the permitted tolerance. An excessive difference, such as more than five degrees, misleads the helmsman and the officer, and should be found and corrected at trials.
✗
Question 79. What should be noted about launching lifeboats while the ship has headway?
Your Answer: (Not answered)
Correct Answer: A (Reduce speed or stop if possible before launching, avoiding the boat being swept away or striking the hull)
💡 A lifeboat should be launched with speed reduced or the ship stopped where possible, since headway produces a flow that can sweep the boat away or dash it against the hull. If stopping is impossible in an emergency, the boat should be launched on the lee side with due preparation.
✗
Question 80. Which statement about fatigue management is correct?
Your Answer: (Not answered)
Correct Answer: B (Watches and work should be reasonably arranged to ensure crew have sufficient rest and avoid fatigue-induced errors)
💡 Fatigue is an important human factor in navigational accidents. The ship should reasonably arrange watches and work, ensure the crew obtain sufficient rest as required and monitor rest hour records to avoid judgement and operational errors caused by fatigue. Fatigue management is an important part of the safety management system.
✗
Question 81. What is required to restore survival craft after use?
Your Answer: (Not answered)
Correct Answer: A (Clean promptly after use or a drill, replenish consumables, re-secure and return to stowage, restoring immediate readiness)
💡 SOLAS requires survival craft to be cleaned promptly after a drill or use, the equipment and supplies consumed such as water and pyrotechnics replenished and the craft re-secured and returned to stowage, restoring immediate readiness. Long neglect would make the appliance unusable in an emergency.
✗
Question 82. On receiving a distress signal at sea, what shall the master do if the ship is able to assist?
Your Answer: (Not answered)
Correct Answer: A (Proceed with all speed to assist)
💡 SOLAS V/33: the master shall proceed with all speed to assist persons in distress when able to do so.
✗
Question 83. What does SOLAS address regarding the axe in a firefighter's outfit?
Your Answer: (Not answered)
Correct Answer: D (An axe suitable for breaking through must be provided and stowed with the rest of the outfit)
💡 SOLAS requires an axe to be provided in the firefighter's outfit for breaking through doors, windows and structure in smoke-filled or obstructed conditions, stowed with the rest of the outfit in an accessible position.
✗
Question 84. What safety requirements apply to compressed air systems?
Your Answer: (Not answered)
Correct Answer: D (Safety valves and drains, preventing accumulation of oil causing explosion, with piping pressure rated and inspected periodically)
💡 SOLAS and good practice require compressed air systems to have safety valves and drains, with condensate and oil removed periodically, preventing overpressure of receivers and piping and accumulation of oil which can cause an explosion, a common cause of scavenge box explosions, with the piping and fittings inspected periodically.
✗
Question 85. What does SOLAS address regarding stowage and immediate availability of survival craft?
Your Answer: (Not answered)
Correct Answer: C (Stowed where they can be reached and launched promptly, in a condition of immediate readiness)
💡 SOLAS requires survival craft to be stowed where they can be reached and launched promptly and to be in a condition of immediate readiness, with gravity davits able to be released without preparation. Dismantling them or stowing them in a hold makes them unusable on abandonment.
✗
Question 86. In addition to intact stability, a passenger ship must also satisfy:
Your Answer: (Not answered)
Correct Answer: B (Damage stability)
💡 SOLAS II-1/7: passenger ships must comply with both intact and damage stability requirements.
✗
Question 87. What lighting must accompany embarkation and launching of survival craft?
Your Answer: (Not answered)
Correct Answer: B (Adequate lighting at the embarkation station and on the water, supplied from the emergency source)
💡 SOLAS requires the embarkation station, the stowage position of the craft and the water alongside to be lit from the emergency source, ensuring safe abandonment at night or in poor visibility.
✗
Question 88. What is the purpose of a continuous fire shelter in the means of escape on a ship?
Your Answer: (Not answered)
Correct Answer: C (To provide a passage which remains usable in a fire, enabling persons to reach the embarkation stations safely)
💡 SOLAS requires a continuous fire shelter on certain ships — a passage enclosed and protected by class A divisions — so that it remains passable in a fire and persons can reach the embarkation stations safely.
✗
Question 89. Rescue boat recovery appliances shall be capable of recovering the rescue boat with persons and equipment at ship's headway of up to:
Your Answer: (Not answered)
Correct Answer: B (5 knots)
💡 SOLAS III/16 requires recovery at ship's headway of up to 5 knots.
✗
Question 90. What checking of the firefighting equipment list against the ship is required?
Your Answer: (Not answered)
Correct Answer: D (Periodically verify the list against what is actually on board, replacing anything missing and updating records)
💡 The ISM Code and SOLAS require periodic verification of the firefighting equipment list against what is actually on board, including extinguishers, firefighter's outfits, hoses and fittings, with anything missing, damaged or expired made good and the records updated, preventing a shortfall from being discovered only at an inspection.
✗
Question 91. The steering gear suddenly loses power while running. What alarm does SOLAS II-1/29 require?
Your Answer: (Not answered)
Correct Answer: D (An audible and visual alarm on the bridge on failure of the steering gear power unit)
💡 SOLAS II-1/29 requires an audible and visual alarm on the bridge when a steering gear power unit fails, so that the officer can immediately take emergency steering action.
✗
Question 92. What is the principal consideration for the foam concentrate quantity of a tanker deck foam system?
Your Answer: (Not answered)
Correct Answer: C (It must sustain the required period of extinguishing operation and meet the prescribed minimum quantity)
💡 SOLAS requires the foam concentrate on a tanker to sustain continuous extinguishing for the prescribed duration and to meet a specified minimum, ensuring adequate firefighting capability.
✗
Question 93. What communication is required between the ship security officer and the company security officer?
Your Answer: (Not answered)
Correct Answer: A (Report promptly on the security situation, incidents and implementation of the plan)
💡 The ISPS Code requires the ship security officer to maintain communication with the company security officer, reporting promptly on the security situation of the ship, security incidents, drills and training and the implementation of and need to revise the ship security plan, so that the company can oversee and support the ship's security.
✗
Question 94. What are the key points in simulating search and rescue in a fire drill?
Your Answer: (Not answered)
Correct Answer: B (Practise donning breathing apparatus, entering with firefighter's equipment to search and moving casualties)
💡 A fire drill should include simulated entry for search and rescue: donning breathing apparatus, taking the axe and safety lamp, using a hose for protection and searching for and moving casualties, so that the crew acquires the skills needed in a smoke filled environment.
✗
Question 95. What launching methods are acceptable for survival craft?
Your Answer: (Not answered)
Correct Answer: C (Davit, free-fall or others appropriate to the type, all ensuring safety)
💡 Methods appropriate to the type, such as davit or free-fall, are acceptable.
✗
Question 96. What condition regarding the suction of the emergency fire pump does SOLAS address?
Your Answer: (Not answered)
Correct Answer: D (It must be capable of drawing water under all operating draughts and trims of the ship)
💡 SOLAS requires the emergency fire pump suction to be arranged so that water can be drawn under all operating draughts and trims. Otherwise it may fail in a particular condition, a common ground for detention.
✗
Question 97. What should a maintenance programme for radio equipment include?
Your Answer: (Not answered)
Correct Answer: B (Daily checks, periodic tests, spares provision and repair arrangements, either ashore or on board)
💡 SOLAS requires the availability of radio equipment to be ensured by daily checks, periodic tests, spare parts and either a shore-based maintenance agreement or at-sea maintenance capability, with the maintenance programme reflecting these arrangements and verified at survey.
✗
Question 98. What shall be done if radio equipment fails?
Your Answer: (Not answered)
Correct Answer: D (Repair it as soon as practicable and report as required)
💡 It shall be repaired as soon as practicable and reported as required.
✗
Question 99. What do SOLAS and good practice address regarding fire hose nozzles?
Your Answer: (Not answered)
Correct Answer: B (Spray nozzles suit oil fires and cooling, while solid jet nozzles suit distant solid fires)
💡 A spray nozzle cools and smothers with fine droplets, suiting oil fires and protective cooling, while a solid jet has greater range and impact, suiting solid fires. Choosing the wrong nozzle reduces effectiveness or spreads the fire.
✗
Question 100. What stability concern does SOLAS address when a ship encounters deck seas or ice accretion?
Your Answer: (Not answered)
Correct Answer: B (Assess the adverse effect of water on deck and ice accretion on stability and freeboard and take measures)
💡 SOLAS and the Load Line Convention require account to be taken of the added weight of water on deck and ice accretion and their effect on stability and freeboard, with measures such as reducing deck cargo or altering course to reduce risk.