Question 1. For side scuttles in the shell below the freeboard deck, what is required as to type and closing appliances?
Your Answer:
(Not answered) Correct Answer:
D (A type complying with the requirements according to position and the limiting line, with effective closing appliances to prevent the entry of water)
💡 Under SOLAS II-1/26 and similar requirements, side scuttles in the shell below the freeboard deck should be of an appropriate type, such as a fixed light with a hinged deadlight, and have effective closing appliances, such as inside deadlights, ensuring that water does not enter the hull in flooding or boarding seas. Openings below the limiting line are more strictly restricted.
✗
Question 2. Earthing of electrical equipment on board serves to:
Your Answer:
(Not answered) Correct Answer:
C (Prevent electric shock and leakage)
💡 Earthing protects against electric shock and leakage causing fire.
✗
Question 3. Who issues and endorses certificates after surveys are completed?
Your Answer:
(Not answered) Correct Answer:
C (The Administration or a recognised organisation duly authorised by it, with endorsement as required)
💡 SOLAS requires statutory certificates to be issued by the Administration or a duly authorised recognised organisation, and endorsed after surveys. Neither the master, the port State nor the owner may issue them.
✗
Question 4. What is required for meeting and overtaking arrangements in a narrow channel?
Your Answer:
(Not answered) Correct Answer:
D (Coordinate the manner of passing with the other vessel or the vessel to be overtaken by VHF in advance, agreeing who gives way and on which side)
💡 Meeting and overtaking in a narrow channel should be coordinated in advance by VHF with the other vessel, agreeing the manner of passing and the responsibility to give way, with local requirements such as one-way periods observed, reducing misunderstanding and close-quarters situations.
✗
Question 5. What should be done with a fire hose after use?
Your Answer:
(Not answered) Correct Answer:
A (Clean and dry it, then roll and stow it in the proper manner in place, keeping it ready for use)
💡 After use a fire hose should be washed free of oil and salt water, dried and then rolled and stowed in the proper manner in its position, preventing rot and ageing which affect pressure resistance. Stowing it damp or exposing it long term shortens its life.
✗
Question 6. Which Convention governs the ship's handling of ballast water?
Your Answer:
(Not answered) Correct Answer:
B (The Ballast Water Management Convention)
💡 Ballast water is to be managed under the Ballast Water Management Convention.
✗
Question 7. What protection against freezing is required for bilge and fire piping in cold weather?
Your Answer:
(Not answered) Correct Answer:
C (Drain or insulate piping liable to freeze, preventing water in it freezing and bursting the pipe)
💡 In cold weather the bilge, fire and ballast piping liable to freeze should be protected by draining, insulation or trace heating, preventing trapped water from freezing and expanding to burst the pipe or valves and so impairing the supply and drainage capability needed in an emergency.
✗
Question 8. What is the purpose of the bilge water high level alarm in a machinery space?
Your Answer:
(Not answered) Correct Answer:
C (To give an alarm when the bilge level rises abnormally, indicating flooding or failure of the drainage system)
💡 SOLAS II-1 requires a bilge water high level alarm in machinery spaces so that the watchkeeper is warned of abnormal accumulation, indicating flooding or a failure of the drainage system.
✗
Question 9. What is the purpose of the magnetic compass?
Your Answer:
(Not answered) Correct Answer:
D (Providing magnetic heading and acting as a back-up to the gyro compass)
💡 It provides the magnetic heading and backs up the gyro compass.
✗
Question 10. What is the focus of survey for ageing bulk carriers under SOLAS and the ESP?
Your Answer:
(Not answered) Correct Answer:
C (The effect on hull strength of corrosion, fatigue cracking and structural deformation)
💡 The ESP and SOLAS require close-up examination of ageing bulk carriers for corrosion, fatigue cracking and deformation, with thickness measurement to assess remaining hull strength and decide on repair or reinforcement.
✗
Question 11. What does SOLAS address regarding short circuit protection in the electrical system?
Your Answer:
(Not answered) Correct Answer:
D (Protective devices on each circuit with selective operation, so a fault does not cause loss of the whole supply)
💡 SOLAS requires protection on each circuit with discrimination, so that a fault in one circuit does not trip the main switchboard or cause total loss of power, affecting propulsion and safety equipment supplies.
✗
Question 12. What is required for the batteries of two-way VHF radiotelephones in survival craft?
Your Answer:
(Not answered) Correct Answer:
D (Capacity meeting the required operating time, with periodic testing and replacement)
💡 SOLAS requires the batteries of two-way VHF sets to have capacity for the prescribed operating time, with periodic testing and replacement. Neglecting this means the equipment may not work on abandonment.
✗
Question 13. If a conversion reduces the lifeboats from two per side to one, what does SOLAS require?
Your Answer:
(Not answered) Correct Answer:
B (Assessment and approval by the Administration or classification society beforehand, confirming the capacity requirement is still met)
💡 SOLAS requires changes to the life-saving appliance arrangement to be assessed and approved by the Administration or the classification society, confirming that the requirements for capacity per side, rescue boat and equipment are still met. Reducing the lifeboats without authority means the ship cannot ensure all persons can escape if one side is lost.
✗
Question 14. In an overtaking situation, how are responsibility and duties allocated?
Your Answer:
(Not answered) Correct Answer:
C (The overtaking vessel must keep out of the way and the overtaken vessel keeps her course and speed)
💡 Under the collision regulations the overtaking vessel must keep out of the way of the vessel being overtaken in all situations until finally past and clear, while the overtaken vessel keeps her course and speed. A vessel approaching from more than twenty-two point five degrees abaft the beam of the vessel ahead is overtaking.
✗
Question 15. What abilities must the crew demonstrate during a SIRE inspection?
Your Answer:
(Not answered) Correct Answer:
C (Familiarity with the operation of equipment in their charge, their emergency duties and the relevant procedures, able to demonstrate in practice)
💡 A SIRE inspection focuses on the crew's practical command of equipment. Each member should be familiar with the equipment in his charge, the emergency procedures and the system requirements and be able to demonstrate, such as preparing a lifeboat for launching or donning a firefighter's outfit. Reciting answers will not suffice.
✗
Question 16. Ventilation must be shut down when a machinery space fire occurs. What does SOLAS II-2/12 require for closing ventilation openings of machinery spaces?
Your Answer:
(Not answered) Correct Answer:
D (They shall be capable of being closed rapidly from outside the space)
💡 SOLAS II-2/12 requires ventilation openings of machinery spaces to be capable of being closed rapidly from outside the space, so ventilation can be stopped without entering the fire area.
✗
Question 17. A survey is carried out two months early. What is the effect under SOLAS?
Your Answer:
(Not answered) Correct Answer:
C (The next due date is still counted from the original anniversary, not postponed by the early survey)
💡 The SOLAS window allows flexibility in scheduling but does not change the due date, which is counted from the certificate anniversary. An early survey does not postpone the next one, preventing effective extension of the certificate by surveying early.
✗
Question 18. What insulation monitoring is required for the electrical system?
Your Answer:
(Not answered) Correct Answer:
B (Insulation monitoring means such as a switchboard insulation resistance meter or monitor, detecting a fall promptly)
💡 SOLAS requires means of insulation monitoring, such as an insulation resistance meter on the main switchboard or an insulation monitor, giving continuous or periodic indication of the insulation to earth and an alarm when it falls, so that leakage and faults are found in time.
✗
Question 19. What is the core risk addressed by SOLAS regarding cargo containment systems on gas carriers?
Your Answer:
(Not answered) Correct Answer:
B (Cargo leakage, low temperature and accumulation of flammable or toxic gas)
💡 Gas cargoes are cryogenic, flammable or toxic. SOLAS and the IGC Code address leakage, low temperature embrittlement and the accumulation of gas in spaces, which could cause explosion or poisoning.
✗
Question 20. For the discharge of bilge water treated by an oily water separator, what is the general oil content limit?
Your Answer:
(Not answered) Correct Answer:
B (15 parts per million)
💡 Under MARPOL Annex I, bilge water treated by an oily water separator may generally be discharged only if its oil content does not exceed fifteen parts per million, with the 15ppm alarm and automatic stopping device. Tankers are subject to stricter distance and monitoring requirements.
✗
Question 21. For free-fall lifeboats, drills shall include:
Your Answer:
(Not answered) Correct Answer:
D (a free-fall launch at the required interval or an equivalent approved method)
💡 SOLAS III/19 requires free-fall lifeboats to be free-fall launched at the prescribed interval or by an approved equivalent method.
✗
Question 22. What should be done if the loading instrument of a bulk carrier computes abnormally?
Your Answer:
(Not answered) Correct Answer:
D (Stop relying on it and use an approved manual method or shore support, repairing and verifying it as soon as possible)
💡 If a loading instrument computes abnormally, such as results clearly differing from hand calculation or the program reporting errors, reliance on it should cease and an approved manual method or shore support used to complete the strength and stability checks, with the instrument repaired and verified as soon as possible, preventing a wrong result from causing overloading or structural damage.
✗
Question 23. What does a passenger drill on a passenger ship usually include?
Your Answer:
(Not answered) Correct Answer:
B (Demonstrating how to don a lifejacket, explaining muster stations and emergency procedures and indicating where appliances are stowed)
💡 SOLAS requires a passenger drill within 24 hours of embarkation, or an equivalent means, including demonstrating how to don a lifejacket, explaining the muster stations and emergency signals and indicating where appliances are stowed and the emergency procedures, so that passengers act correctly in an emergency.
✗
Question 24. What do SOLAS and good practice address regarding life-saving appliances during temporary repairs?
Your Answer:
(Not answered) Correct Answer:
D (Life-saving appliances must remain available; if affected, compensating measures must be taken and accepted by the Administration)
💡 If life-saving appliances must be temporarily removed or are affected during repairs, compensating measures such as adjusting the arrangement, limiting the number of persons or restricting the area of work must be taken and accepted by the Administration or the classification society. The ship must not sail with the deficiency unaddressed.
✗
Question 25. What shall the master do on encountering dangerous ice or derelicts?
Your Answer:
(Not answered) Correct Answer:
B (Communicate the danger immediately to ships in the vicinity and to the competent authority ashore)
💡 SOLAS V/31: the master shall communicate the danger immediately to nearby ships and to the competent authority.
✗
Question 26. What is the focus when navigating in or near ice under SOLAS V and related requirements?
Your Answer:
(Not answered) Correct Answer:
B (Enhanced look-out, reduced speed and attention to hull stress and changing ice conditions)
💡 Navigation in ice calls for enhanced look-out, controlled speed and continuous monitoring of ice conditions and hull condition to avoid damage. Increasing speed or switching off aids worsens the risk.
✗
Question 27. What does SOLAS II-2 require where the length of an enclosed corridor in accommodation spaces exceeds a certain figure?
Your Answer:
(Not answered) Correct Answer:
A (A corridor exceeding 13 m must have access to escape routes at both ends)
💡 SOLAS II-2/13 requires an enclosed corridor longer than 13 m to give access to escape routes at both ends, so that occupants are not trapped in a dead end.
✗
Question 28. A PSCO asks you to explain the term 'Administration' as used in SOLAS. What is the correct meaning?
Your Answer:
(Not answered) Correct Answer:
B (The Government of the State whose flag the ship is entitled to fly)
💡 SOLAS I/2 defines 'Administration' as the Government of the State whose flag the ship is entitled to fly. A classification society acts only as a recognised organisation authorised by the Administration.
✗
Question 29. Which of the following are common types of fixed fire detection systems?
Your Answer:
(Not answered) Correct Answer:
A (Smoke, heat and flame (radiation) detectors)
💡 SOLAS recognises fixed detection systems including smoke, heat and flame (radiation) types, selected according to the nature of the space and the fire characteristics expected.
✗
Question 30. What additional safety measure does SOLAS require for remote closing of watertight doors from the bridge?
Your Answer:
(Not answered) Correct Answer:
C (An audible and visual alarm before closing, so that persons can move clear)
💡 SOLAS requires an audible and visual alarm and a delay before remote closing of a watertight door from the bridge, giving persons nearby time to move clear and preventing injury. Visual confirmation is not sufficient when operating at a distance.
✗
Question 31. What is the principal risk addressed by the requirements for venting arrangements of tanker cargo tanks?
Your Answer:
(Not answered) Correct Answer:
B (Preventing overpressure or vacuum in the tanks caused by cargo operations and temperature changes)
💡 Venting arrangements equalise tank pressure during cargo operations and temperature changes, preventing structural damage from overpressure and deformation from vacuum.
✗
Question 32. The voyage plan shall be monitored by:
Your Answer:
(Not answered) Correct Answer:
A (the master overall, with the officer of the watch executing and monitoring it)
💡 SOLAS V/34 requires the master to be responsible and the OOW to execute and monitor the voyage plan.
✗
Question 33. What must be verified about the righting lever curve after loading?
Your Answer:
(Not answered) Correct Answer:
B (That the positive range of the curve and the maximum righting lever meet the criteria)
💡 The intact stability criteria require the righting lever at specified angles, such as 30 or 40 degrees, the maximum righting lever and its angle and the positive range of the curve all to meet the requirements. The initial metacentric height alone does not show stability at large angles of heel.
✗
Question 34. An escape route in the engine room is found permanently blocked by stores. The finding is?
Your Answer:
(Not answered) Correct Answer:
C (Escape routes must be kept clear; blockage seriously affects emergency evacuation, a serious deficiency)
💡 A machinery space should have two escape routes as widely separated as practicable, always available. A blocked escape route endangers the evacuation of engine room personnel in a fire or other emergency. It is a serious deficiency affecting personnel safety and the obstruction should be removed at once.
✗
Question 35. What are the key points of the monthly inspection of survival craft launching appliances?
Your Answer:
(Not answered) Correct Answer:
B (Check the brake, release gear, falls and sheaves and the securing arrangements for operation and condition)
💡 SOLAS III/20 requires a monthly inspection of the launching appliances of survival craft: checking that the brake holds reliably, the release gear operates correctly, the falls and sheaves are free of broken wires and wear and the securing arrangements release properly, with any defects found and the action taken recorded.
✗
Question 36. The stability information supplied to the master shall:
Your Answer:
(Not answered) Correct Answer:
D (be approved and include stability for various loading conditions)
💡 SOLAS II-1/5 requires approved stability information covering various loading conditions.
✗
Question 37. An echo sounder shall be fitted on:
Your Answer:
(Not answered) Correct Answer:
D (passenger ships on international voyages and cargo ships of 500 GT and above)
💡 SOLAS V/19: passenger ships on international voyages and cargo ships of 500 GT and above shall be fitted with an echo sounder.
✗
Question 38. The watertight door indicator showed a door open while it was in fact closed. What is the finding?
Your Answer:
(Not answered) Correct Answer:
B (A deficiency; the indicator must accurately reflect the actual status, as a false indication misleads the assessment of watertight integrity)
💡 The watertight door indicator on the bridge must accurately reflect the actual open or closed status. A false indication would lead the watchkeeper to a wrong appreciation of watertight integrity and to incorrect measures after damage, so it is a deficiency affecting safety.
✗
Question 39. A PSC inspection checked the enhanced survey documentation of a tanker. What document does SOLAS require?
Your Answer:
(Not answered) Correct Answer:
B (A survey programme identifying the scope of close-up survey and thickness measurement)
💡 The ESP requires the ship to hold a survey programme specifying the extent of close-up survey and thickness measurement, agreed by the class society and the owner. A survey or thickness report alone does not evidence the existence and execution of the programme.
✗
Question 40. What priority applies to distress communication under SOLAS and the Radio Regulations?
Your Answer:
(Not answered) Correct Answer:
D (Distress takes priority over urgency, and urgency over safety)
💡 SOLAS and the Radio Regulations set the order of priority as distress, urgency, safety and other communication. Distress traffic has absolute priority; other traffic must give way and must not occupy distress frequencies for unrelated communication.
✗
Question 41. What is the maximum interval between ship security drills required by the ISPS Code?
Your Answer:
(Not answered) Correct Answer:
C (Three months)
💡 ISPS Code Part A/13 and SOLAS XI-2 require ship security drills at intervals of not more than three months, with additional drills where the security level changes.
✗
Question 42. Which supply arrangements does SOLAS permit for the main source of electrical power?
Your Answer:
(Not answered) Correct Answer:
B (Supplied by main generators, possibly with a shaft generator or an emergency generator, provided reliability is assured)
💡 SOLAS requires the main source to meet the needs of normal operation and habitability, and it may comprise one or more main generators with shaft or emergency generators. The essential point is that reliability satisfies the Convention.
✗
Question 43. A cargo ship radio safety certificate was issued on 10 March 2021. With no extension granted, when does it expire at the latest?
Your Answer:
(Not answered) Correct Answer:
D (10 March 2026)
💡 Under SOLAS I/7 the cargo ship safety radio certificate is valid for not more than five years, expiring on 10 March 2026.
✗
Question 44. Enhanced Surveys shall be carried out in accordance with:
Your Answer:
(Not answered) Correct Answer:
D (the harmonized system of survey and certification and the Enhanced Survey Programme guidelines)
💡 SOLAS XI-1/2: Enhanced Surveys are carried out under the harmonized system of survey and certification and the ESP guidelines.
✗
Question 45. How must operating instructions and markings for equipment be managed?
Your Answer:
(Not answered) Correct Answer:
B (Clear instructions and warnings, available near the equipment and kept in good condition)
💡 Operating instructions and warning markings for critical equipment should be provided near the equipment, clear and in good condition, not fallen off or illegible, so that the operator can consult them at any time. Relying on memory without markings makes errors likely after a change of personnel or under pressure.
✗
Question 46. Why shall spaces where flammable gases may accumulate be ventilated?
Your Answer:
(Not answered) Correct Answer:
B (To prevent gases reaching dangerous concentrations)
💡 To prevent accumulation of flammable gases to dangerous concentrations.
✗
Question 47. What do SOLAS and good practice address regarding fuel in vehicles carried on board?
Your Answer:
(Not answered) Correct Answer:
D (Fuel tanks should be kept as low as practicable and checked for leakage before loading)
💡 SOLAS and industry guidance recommend limiting the fuel in vehicles carried, normally to a stated quantity, and checking for leakage before loading, reducing fire load and the risk of spillage. The ship should take part in the check and record it.
✗
Question 48. What do SOLAS and good practice address regarding connection of shore power in port?
Your Answer:
(Not answered) Correct Answer:
A (Confirm that voltage, frequency and phase sequence match and take measures against misoperation and electric shock)
💡 Before connecting shore power, the voltage, frequency and phase sequence should be confirmed to match the ship's system, with isolation, earthing and warning measures taken to prevent equipment damage and electric shock. Ship and shore should confirm the interface and condition.
✗
Question 49. Which measure complies with SOLAS for protection against electric shock?
Your Answer:
(Not answered) Correct Answer:
C (Live parts shall be protected against accidental contact)
💡 Live parts which may be accidentally touched shall be protected.
✗
Question 50. Which is not required when security level 2 is in force?
Your Answer:
(Not answered) Correct Answer:
A (Suspending all cargo operations)
💡 Level 2 tightens security and restricts areas but does not require cargo work to stop.
✗
Question 51. What is required for monitoring stability during loading and unloading?
Your Answer:
(Not answered) Correct Answer:
C (Monitor stability and strength at each stage against the loading plan, preventing excessive hogging or sagging or insufficient initial stability)
💡 SOLAS requires stability and hull strength to be monitored at each stage against the loading plan, preventing excessive hogging or sagging and insufficient initial stability. Calculating only afterwards cannot prevent structural damage during cargo work.
✗
Question 52. What is the principal concern of SOLAS XII regarding cargo hatch covers of bulk carriers?
Your Answer:
(Not answered) Correct Answer:
B (They must remain weathertight and structurally adequate, preventing sea water entering holds and causing structural failure)
💡 SOLAS XII requires hatch covers of bulk carriers to be weathertight and of adequate strength. Failure of hatch covers allowing sea water into the holds is a major cause of structural failure and loss of bulk carriers.
✗
Question 53. A PSCO tested ventilation closing devices and found some seized. What does SOLAS address?
Your Answer:
(Not answered) Correct Answer:
A (Closing devices of machinery space ventilators must close rapidly to cut off ventilation and air supply)
💡 SOLAS II-2 requires machinery space ventilator closing devices to close rapidly and remain effective, cutting off the air supply in a fire. Seized devices or a lack of regular testing are common deficiencies.
✗
Question 54. Where should the fire control plan be stowed on board?
Your Answer:
(Not answered) Correct Answer:
B (In a conspicuously marked weathertight enclosure outside the deckhouse, with a further copy on the bridge or equivalent position)
💡 SOLAS II-2/15 requires the fire control plan to be permanently stowed in a conspicuously marked weathertight enclosure outside the deckhouse, with another copy on the bridge or equivalent, for use by shore firefighters.
✗
Question 55. What does SOLAS address regarding boiler feed water and water level control?
Your Answer:
(Not answered) Correct Answer:
A (Water level indication with low water level alarm and protection, preventing damage from a dry boiler)
💡 SOLAS requires boilers to have water level indication with low water level alarm and protection, giving warning and shutting down the boiler if water is low, preventing overheating damage or explosion.
✗
Question 56. What is the role of the intermediate survey among the surveys of the cargo ship safety equipment certificate?
Your Answer:
(Not answered) Correct Answer:
D (It takes the place of one annual survey and examines specified items in greater depth)
💡 The cargo ship safety equipment certificate requires annual and intermediate surveys. The intermediate survey is held on the second or third anniversary date, replacing that annual survey and examining specified items in more depth.
✗
Question 57. How shall the number and capacity of lifeboats on a passenger ship be determined?
Your Answer:
(Not answered) Correct Answer:
B (To accommodate the total number of persons on board)
💡 The total capacity shall accommodate all persons on board.
✗
Question 58. What does SOLAS require for each fire hose?
Your Answer:
(Not answered) Correct Answer:
D (Each hose must have a nozzle and be stowed near its hydrant ready for use)
💡 SOLAS requires each fire hose to be fitted with a nozzle and stowed near its hydrant so that it can be connected and used at once. Stowing hoses and nozzles separately delays firefighting.
✗
Question 59. Cargo ships shall be provided with survival craft having a capacity for:
Your Answer:
(Not answered) Correct Answer:
D (100% of the total number of persons on board)
💡 SOLAS III/31 requires cargo ships to be provided with survival craft for 100% of the total number of persons on board.
✗
Question 60. In the subdivision of a passenger ship, what does the "subdivision load line" mean?
Your Answer:
(Not answered) Correct Answer:
D (An assumed load line used to determine subdivision requirements, not the ship's actual service load line)
💡 The subdivision load line is an assumed load line used in determining subdivision requirements such as bulkhead positions and the subdivision index. It is a different concept from the summer or tropical load lines actually used in service.
✗
Question 61. What should be done about failed lighting in an escape route?
Your Answer:
(Not answered) Correct Answer:
D (Repair or replace promptly; lighting in escape routes is vital for emergency evacuation)
💡 Lighting in escape routes, including emergency and low level lighting, is essential for evacuation in fire and dense smoke. Failed fittings must be repaired or replaced promptly; their absence greatly increases the difficulty of evacuation and the risk of casualties.
✗
Question 62. What does SOLAS permit when a certificate expires while the ship is at sea?
Your Answer:
(Not answered) Correct Answer:
B (An extension of not more than three months in specified circumstances, so the ship may complete the voyage or reach the port of survey)
💡 SOLAS I/14 permits an extension of not more than three months in the specified circumstances, where a certificate expires during a voyage and the ship has not been surveyed in time, so that she may reach the port where she is to be surveyed. The extension must be within the rules and recorded.
✗
Question 63. If the master finds a defect affecting safe navigation that cannot be repaired on board, the first action is to:
Your Answer:
(Not answered) Correct Answer:
A (Report to the Company and arrange repair)
💡 The master should report to the Company so that repair can be arranged and the voyage adjusted.
✗
Question 64. What is required regarding the deck log book?
Your Answer:
(Not answered) Correct Answer:
C (Navigational, watchkeeping and significant events must be entered truthfully as required, without alteration or falsification)
💡 SOLAS and good practice require the deck log to record the position, course and speed, weather, equipment condition and significant events truthfully and promptly. The log is important evidence in navigation and casualty investigation, and alteration or falsification has serious consequences.
✗
Question 65. What does SOLAS chapter II-2 require of the layout of fire mains and hydrants?
Your Answer:
(Not answered) Correct Answer:
D (at least two jets reaching any part of the space protected, one of them on a single length of hose, with the specified fire pumps working)
💡 The chapter fixes the number of jets and the pressure by ship type: cargo ships as a rule require at least two jets from different hydrants, one of them available on a single length of hose to any part of the space protected, with separate requirements for machinery spaces. Main diameter, pump capacity and nozzle size have to match, or the far hydrant loses pressure. Layout follows coverage and simultaneous use, not ease of maintenance or a ratio of floor area, which tells nothing about jets.
✗
Question 66. What is required for route monitoring when using electronic charts?
Your Answer:
(Not answered) Correct Answer:
B (Continuously monitor the deviation from the planned route, act on and acknowledge safety alarms and correct as necessary)
💡 When ECDIS is in use the deviation from the planned route should be monitored continuously and safety alarms such as off-track and approaching danger acted on and acknowledged, with course corrections as necessary. Setting the route and then neglecting to monitor it is not acceptable.
✗
Question 67. What limitation must the officer of the watch bear in mind when using ARPA?
Your Answer:
(Not answered) Correct Answer:
D (Target tracking may be lost or erroneous due to sea state, target manoeuvres or shadowing, so it cannot be relied upon entirely)
💡 ARPA tracking is affected by sea state, target manoeuvres, shadowing and input data accuracy, and targets may be lost or plotted in error. The officer must cross-check with the raw radar picture and visual look-out.
✗
Question 68. What oxygen level is normally required before entering an enclosed space?
Your Answer:
(Not answered) Correct Answer:
B (Between 19.5 and 23 per cent by volume)
💡 The oxygen content in an enclosed space should be between 19.5 and 23 per cent before entry. Below 19.5 per cent there is a risk of asphyxiation; above 23 per cent the risk of combustion and explosion increases. Both departures are unsafe.
✗
Question 69. Fire hoses shall be provided:
Your Answer:
(Not answered) Correct Answer:
B (for each hydrant in sufficient number, including spare hoses)
💡 SOLAS II-2/10: fire hoses shall be provided for each hydrant in sufficient number, including spare hoses.
✗
Question 70. What protection is required for personnel handling chemicals and oils?
Your Answer:
(Not answered) Correct Answer:
C (Appropriate personal protective equipment provided and correctly used, with prompt washing after contact and health surveillance where necessary)
💡 Personnel handling chemicals, oils or paints should be provided with and correctly use personal protective equipment as the safety data sheets require, including eye and face protection, gloves, protective clothing and respiratory protection, washing promptly after contact, with health surveillance and records where exposure is prolonged or symptoms appear.
✗
Question 71. If a vessel cannot give effective assistance to a ship in distress, it shall:
Your Answer:
(Not answered) Correct Answer:
C (Record it and report the situation to the appropriate authority)
💡 Record the matter and report to the appropriate authority.
✗
Question 72. What should be done if insulation on a fire division becomes damp, falls off or is removed?
Your Answer:
(Not answered) Correct Answer:
D (Repair or replace promptly to restore the fire rating, using approved material)
💡 Damp, missing or removed insulation on a class A division reduces its fire performance and should be replaced promptly with approved material to restore the original rating. Substituting ordinary material or timber destroys the protective function of the division.
✗
Question 73. Lifejackets stowed in lockers on deck or at the ship's side are intended to be:
Your Answer:
(Not answered) Correct Answer:
A (Easy to don and quickly accessible in an emergency)
💡 Lifejackets shall be easy to don and quickly accessible in an emergency.
✗
Question 74. What is the requirement for the safety lamp in a firefighter's outfit?
Your Answer:
(Not answered) Correct Answer:
D (An electric safety lamp capable of continuous illumination for at least three hours)
💡 SOLAS requires an electric safety lamp giving continuous illumination for at least three hours, safe in smoke and flammable atmospheres. Ordinary torches and flame lamps are not acceptable.
✗
Question 75. Means of escape shall:
Your Answer:
(Not answered) Correct Answer:
D (be continuous to the embarkation deck or muster station)
💡 SOLAS II-2/13 requires continuous means of escape to the embarkation deck or muster station.
✗
Question 76. What is required for testing the emergency lighting system?
Your Answer:
(Not answered) Correct Answer:
A (Periodic testing of automatic operation and duration, with records kept)
💡 SOLAS and good practice require periodic testing of the automatic operation of the emergency lighting and of its duration, for example by simulating failure of the main source, observing the lighting come on and timing it, verifying the prescribed period with records kept, preventing failure during an actual blackout.
✗
Question 77. What cleaning of bilges is required?
Your Answer:
(Not answered) Correct Answer:
D (Periodic removal of sludge and debris to keep suctions clear)
💡 Sludge and debris in the bilges block the suctions and reduce drainage capacity, so they should be removed periodically as part of the checks of the watertight doors and bilge system, with the strainers inspected. A record should be kept, particularly after carrying bulk cargoes that produce dust or debris.
✗
Question 78. Which of the following is the "Company" the ISM Code means?
Your Answer:
(Not answered) Correct Answer:
A (the owner of the ship, or any other organisation or person who has taken on the responsibility for operating it and agreed to take over the obligations the rules impose)
💡 The definition rests on two conditions: having taken the responsibility for operating the ship from the owner, and having agreed to take on the duties and liability the rules lay out. Whoever meets them may be the owner, a manager or a bareboat charterer, so a management agreement does not of itself leave the position with the registered owner; and a supplier who does routine maintenance or finds crew alone does not become it by that. The one recognised as the Company is the one to whom the document of compliance is issued, the party named in the safety management certificate must match, and the agreement between them should mark out responsibility, authority and resources so that no gap opens where neither side answers. What the owner owes in respect of the ship does not disappear with the delegation, yet the running of the system sits with whoever carries the operating responsibility. The organisation that issues the certificate is the administration or one recognised by it, and is not the Company as defined.
✗
Question 79. What checks are required for the shafting and propeller?
Your Answer:
(Not answered) Correct Answer:
A (Stern tube sealing for oil leakage, the propeller for damage or fouling and the shafting for abnormal vibration)
💡 The stern tube seal should be checked for oil leakage, which affects both lubrication and pollution, the propeller for deformation, damage or fouling by nets and ropes and the shafting and bearings for abnormal vibration and temperature rise, with problems dealt with promptly, preventing loss of propulsion.
✗
Question 80. What is the purpose of the water ingress detection system required on a bulk carrier?
Your Answer:
(Not answered) Correct Answer:
B (To give an alarm when water enters the cargo holds and fore and aft spaces, enabling the crew to detect and deal with it promptly)
💡 Under SOLAS XII/12 a bulk carrier should have water ingress detection and alarm systems for the cargo holds and the forepeak and similar spaces, giving an alarm on the bridge promptly when water enters so that the crew can detect the ingress early and take pumping, leak-hunting and damage control measures, preventing the situation from worsening. The testing of the system should be kept effective.
✗
Question 81. Which of the following is NOT among the statutory certificates normally obtained by a cargo ship after the relevant surveys?
Your Answer:
(Not answered) Correct Answer:
B (The International Ship Security Certificate, which is issued under the ISPS Code and Chapter XI-2)
💡 SOLAS I/7 lists the Cargo Ship Safety Construction Certificate, Safety Equipment Certificate and Safety Radio Certificate. The ISSC is issued under Chapter XI-2 and the ISPS Code and is not one of the three listed in I/7.
✗
Question 82. A lifejacket light shall be capable of continuous operation for at least:
Your Answer:
(Not answered) Correct Answer:
C (8 hours)
💡 SOLAS III/7 (LSA Code) requires a lifejacket light to operate continuously for at least 8 hours.
✗
Question 83. A steering gear compartment shall be provided with communication facilities:
Your Answer:
(Not answered) Correct Answer:
B (two-way communication between the navigation bridge and the steering gear compartment)
💡 SOLAS II-1/29 requires two-way communication between the navigation bridge and the steering gear compartment.
✗
Question 84. What is the usual maximum validity of a Passenger Ship Safety Certificate?
Your Answer:
(Not answered) Correct Answer:
D (Twelve months)
💡 Under SOLAS I/12 a Passenger Ship Safety Certificate has a usual validity of not more than twelve months, unlike the certificates of a cargo ship, with the relevant surveys completed within the period. Because a passenger ship carries many people, its surveys and certificate management are more frequent.
✗
Question 85. What principle should the officer of the watch follow in using ECDIS in confined waters or a port approach?
Your Answer:
(Not answered) Correct Answer:
B (Adjust the display scale appropriately and keep the chart updated, avoiding over-reliance on a single display for position)
💡 ECDIS should be used with the scale adjusted to the leg of the passage, charts kept updated and the position cross-checked. Switching off safety alarms or fixing one scale weakens the warning function and increases the risk of grounding.
✗
Question 86. What must the weekly inspection of life-saving appliances record under SOLAS?
Your Answer:
(Not answered) Correct Answer:
B (The availability of the craft and launching appliances, the completeness of equipment and the condition of the boat engines)
💡 SOLAS III/20 requires the weekly inspection to cover the craft, the launching appliances, the completeness of equipment and the condition of the engines, with the details and any defects found entered in the deck log as evidence of the working of the system.
✗
Question 87. What is the maximum interval for renewal surveys of the Cargo Ship Safety Construction Certificate?
Your Answer:
(Not answered) Correct Answer:
A (5 years)
💡 SOLAS I/10: renewal surveys shall be at intervals not exceeding 5 years.
✗
Question 88. What must a company do after a non-conformity is found in an internal or external audit?
Your Answer:
(Not answered) Correct Answer:
C (Analyse the root cause, take corrective action within the prescribed period and verify its effectiveness)
💡 The ISM Code requires non-conformities found at audit to be analysed for root cause, with corrective action taken and completed within the prescribed period and its effectiveness verified, preventing recurrence.
✗
Question 89. Under SOLAS V/26, radar shall be used:
Your Answer:
(Not answered) Correct Answer:
A (in restricted visibility and congested waters to maintain safe navigation)
💡 SOLAS V/26: radar shall be used in restricted visibility and congested waters to maintain safe navigation.
✗
Question 90. Which statement about the total capacity of the main fire pumps is correct?
Your Answer:
(Not answered) Correct Answer:
C (Each fire pump's capacity is not less than eighty per cent of the required total, and the main pressure is met)
💡 Under SOLAS II-2/10 the distribution of fire pump capacity should ensure that each pump provides not less than eighty per cent of the required total and that the main pressure is maintained with the required number of hydrants in simultaneous use. This ensures firefighting capability even if one pump fails.
✗
Question 91. What does SOLAS address regarding operation of emergency equipment when the ship is listed?
Your Answer:
(Not answered) Correct Answer:
B (The emergency generator, emergency fire pump and similar equipment must operate under the prescribed angles of list and trim)
💡 SOLAS requires essential emergency equipment such as the emergency generator and emergency fire pump to operate under the prescribed angles of list and trim. Since a ship is often listed after damage, failure of emergency equipment in that condition would seriously hamper the response.
✗
Question 92. What items does the stability assessment after loading include?
Your Answer:
(Not answered) Correct Answer:
D (Initial metacentric height, the righting lever curve, the maximum righting lever and the weather criterion)
💡 Intact stability assessment normally includes the initial metacentric height, the shape and range of the righting lever curve, the maximum righting lever and its angle and the weather criterion, the ratio of heeling to righting moment. Calculating the initial metacentric height alone does not ensure intact stability.
✗
Question 93. A watertight door open/closed indicator at the central control station shows the wrong state, a door actually open being indicated as closed. The finding is?
Your Answer:
(Not answered) Correct Answer:
D (A wrong indication may mislead the bridge as to the subdivision state; a deficiency to be corrected)
💡 The open/closed indicator at the central control station is an important basis for judging the actual state of each watertight door and deciding on closing measures. A wrong indication misleads the bridge as to subdivision integrity and may delay closure in the event of flooding. It is a deficiency to be corrected.
✗
Question 94. What does SOLAS address regarding the location of the emergency fire pump?
Your Answer:
(Not answered) Correct Answer:
A (Located outside the machinery space with independent power and a separate suction)
💡 SOLAS requires the emergency fire pump to be located outside category A machinery spaces with an independent source of power and a separate suction, so that it is not affected by a fire in that space and can draw water independently.
✗
Question 95. What do SOLAS and the related standards address regarding electromagnetic compatibility of radio equipment?
Your Answer:
(Not answered) Correct Answer:
C (Equipment must not cause harmful interference and must not be rendered ineffective by interference from other equipment)
💡 SOLAS and the IEC standards require ship radio equipment to be electromagnetically compatible, neither disturbing other equipment such as navigational aids nor being rendered ineffective by interference from them.
✗
Question 96. What does SOLAS address regarding action if the inert gas system fails?
Your Answer:
(Not answered) Correct Answer:
C (Stop the relevant operations immediately and notify the terminal and take emergency measures)
💡 SOLAS and industry guidance require the relevant operations to stop at once if the inert gas system fails, with the terminal informed and emergency measures taken, preventing explosion from carrying on operations with inerting lost.
✗
Question 97. Which VHF channel is used for distress and safety radiotelephony?
Your Answer:
(Not answered) Correct Answer:
A (Channel 16 (156.8 MHz))
💡 VHF channel 16 (156.8 MHz) is for distress and safety radiotelephony. Channel 70 is reserved for DSC calling and must not be used for speech.
✗
Question 98. What size should the international shore connection fitted on ships of 500 GT and above be?
Your Answer:
(Not answered) Correct Answer:
A (65 mm)
💡 The international shore connection is 65 mm in diameter.
✗
Question 99. What safety is required for deck work at sea?
Your Answer:
(Not answered) Correct Answer:
D (Safe working procedures including risk assessment, use of protective equipment and restrictions in heavy weather)
💡 SOLAS and the ISM Code require deck work such as checking securing, chipping and maintenance to follow safe working practices: a risk assessment before starting, covering ship movement, wind and sea, work at height and enclosed spaces, correct use of personal protective equipment and restriction or suspension of the work in heavy weather.
✗
Question 100. Indication on the navigation bridge of propeller speed and pitch shall:
Your Answer:
(Not answered) Correct Answer:
A (show propeller speed and, where applicable, pitch direction)
💡 SOLAS II-1/28 requires the bridge to have indicators for propeller speed, direction of rotation and, where applicable, pitch.