Exam Home Website
中文 English
0
/100
FAIL
Correct: 0/100 Total Questions: 100 Time Spent: 60min0sec
Passing: 80
Retake History
Answer Review
✗
Question 1. What marking shall survival craft have for night detection?
Your Answer: (Not answered)
Correct Answer: D (Lighting or retro-reflective material to aid detection)
💡 Lighting or retro-reflective material to aid detection.
✗
Question 2. What does SOLAS require regarding passenger drills on a passenger ship?
Your Answer: (Not answered)
Correct Answer: A (Held within 24 hours of embarkation, covering the use of lifejackets and the muster stations)
💡 SOLAS requires a passenger muster and drill within 24 hours of embarkation, covering the use of lifejackets, the muster stations and the emergency procedures. Passenger emergency instructions must also be provided, for example as a card in each cabin.
✗
Question 3. What does SOLAS address regarding the construction of side doors and cargo doors in the shell?
Your Answer: (Not answered)
Correct Answer: C (They must be of strength equivalent to the adjacent hull with reliable closing appliances, included in survey and records)
💡 SOLAS requires shell doors and cargo doors in a cargo ship to have strength and watertightness equivalent to the adjacent hull, with reliable closing appliances, and to be included in periodic survey and maintenance records, since such openings are a high risk point for flooding.
✗
Question 4. What preparation do SOLAS and BMP require before entering a high risk area?
Your Answer: (Not answered)
Correct Answer: C (Complete a security risk assessment, apply hardening and protective measures, conduct drills and report to the company, with reporting maintained)
💡 Before entering a high risk area a security risk assessment should be completed, protective and hardening measures applied in accordance with BMP, drills held, the company informed and reports made to the relevant bodies as required, so that the ship is prepared if threatened.
✗
Question 5. One space uses smoke detectors and another heat detectors. What is the main basis for choosing detector type?
Your Answer: (Not answered)
Correct Answer: A (The type and characteristics of fire likely in the space, such as smoke production or rapid temperature rise)
💡 SOLAS requires the detector type to suit the fire expected in the space: smoke detectors where smoke will be produced, heat detectors where rapid temperature rise without much smoke may occur. The wrong choice delays the alarm.
✗
Question 6. How often shall the Company carry out internal audits of the SMS?
Your Answer: (Not answered)
Correct Answer: A (At least once a year)
💡 At least once a year.
✗
Question 7. The firefighter's outfit store is found locked with the key not readily available, so difficult to obtain in an emergency. The finding is?
Your Answer: (Not answered)
Correct Answer: B (Firefighter's outfits must be readily available; improper stowage is a deficiency affecting firefighting readiness)
💡 The firefighter's outfits and their associated equipment should be stowed in a location that is easily reached and readily available. If locked with the key not promptly available it delays the donning and entry of the firefighters at the start of a fire. It is a deficiency affecting firefighting readiness.
✗
Question 8. What crew preparation is required before entering ice in polar waters?
Your Answer: (Not answered)
Correct Answer: D (Special polar operations training, clear emergency duties for ice conditions and drills of emergency procedures at low temperature)
💡 The Polar Code requires relevant training and familiarisation before entering polar waters, covering the contents of the PWOM, ice operating procedures and the use of emergency and life-saving equipment in low temperature, with the duties of each position in an ice emergency made clear and corresponding drills held.
✗
Question 9. What should be noted in steering and handling a lifeboat?
Your Answer: (Not answered)
Correct Answer: A (Familiarity with the rudder and propulsion controls, coordination with those on board and avoiding injury from wave impact)
💡 Handling a lifeboat involves familiarity with the way the rudder and propulsion respond, coordination with the persons on board such as even distribution, holding on and avoiding high speed in heavy seas, preventing persons being thrown about or lost over the side.
✗
Question 10. Lifeboat and liferaft launching appliances shall be inspected and tested at intervals not exceeding:
Your Answer: (Not answered)
Correct Answer: B (monthly)
💡 SOLAS III/20 requires launching appliances to be inspected weekly and tested monthly.
✗
Question 11. What is required for maintenance and inspection of radio equipment?
Your Answer: (Not answered)
Correct Answer: A (Periodic inspection and maintenance to keep it ready for use)
💡 Periodic inspection and maintenance to keep it available at all times.
✗
Question 12. Each person in a lifeboat shall be provided with fresh water of not less than:
Your Answer: (Not answered)
Correct Answer: A (3 litres)
💡 SOLAS III/34 requires not less than 3 litres of fresh water per person in a lifeboat.
✗
Question 13. What is the main purpose of the main engine and steering gear information required on board?
Your Answer: (Not answered)
Correct Answer: B (To enable the master to know the machinery and steering response and plan safe manoeuvres)
💡 SOLAS requires information on the main engine and steering gear so the master understands acceleration, deceleration and steering response, and can plan berthing and narrow channel manoeuvres.
✗
Question 14. What is the purpose of thermal protective aids among the lifeboat equipment?
Your Answer: (Not answered)
Correct Answer: C (Providing thermal protection for persons in the boat and reducing loss of body heat)
💡 Thermal protective aids in a lifeboat are used to keep persons warm and reduce loss of body heat, preventing hypothermia in cold conditions. They do not provide buoyancy.
✗
Question 15. What does SOLAS address regarding the helmet and boots of a firefighter's outfit?
Your Answer: (Not answered)
Correct Answer: C (A helmet able to withstand impact and protect the head, and boots resistant to puncture and electrically insulating)
💡 SOLAS requires a rigid helmet able to withstand impact with a face shield, and boots resistant to puncture and electrically insulating. An ordinary safety helmet and rubber boots do not meet the requirements for firefighting.
✗
Question 16. Which measure prevents static hazards in the cargo area of a tanker?
Your Answer: (Not answered)
Correct Answer: D (Earthing of piping and tanks and similar anti-static measures)
💡 Earthing of piping and tanks and other anti-static measures.
✗
Question 17. What does SOLAS address regarding openings in fire divisions?
Your Answer: (Not answered)
Correct Answer: A (The fire performance of an opening must be not less than that of the division, with closing appliances of equivalent rating)
💡 SOLAS requires openings such as doors, windows and manholes in a fire division to have fire performance not less than that of the division and to be fitted with closing appliances of equivalent rating. Any weak opening defeats the protection of the whole division.
✗
Question 18. Ships shall carry for distress communication:
Your Answer: (Not answered)
Correct Answer: A (radio personnel holding appropriate certificates, or watch officers with the required certificate)
💡 SOLAS IV/16 requires ships to carry radio personnel holding appropriate certificates for distress and safety communication.
✗
Question 19. Which extinguishing medium should be used on an electrical fire?
Your Answer: (Not answered)
Correct Answer: A (A non-conducting medium such as CO2 or dry powder, with the power cut first)
💡 An electrical fire requires a non-conducting medium such as CO2 or dry powder with the power cut as soon as possible. Water or foam risks electric shock and further damage to equipment, and cutting the power is the first step.
✗
Question 20. Insulation was removed from a fire division for work and not replaced. What is the finding?
Your Answer: (Not answered)
Correct Answer: B (A deficiency; missing insulation reduces the fire performance of the division and must be restored promptly)
💡 Insulation removed from a fire division, for example to gain access during work, and not replaced significantly reduces its fire performance, so heat and fire cannot be effectively contained. It is a deficiency affecting safety and must be restored promptly with approved material.
✗
Question 21. What rescue arrangement is required when entering an enclosed space?
Your Answer: (Not answered)
Correct Answer: B (A standby person at the entrance with rescue equipment and continuous communication)
💡 Entry into an enclosed space requires a standby person at the entrance, continuous communication and rescue equipment including breathing apparatus, so that immediate rescue is possible. Solo entry is a principal cause of multiple fatalities.
✗
Question 22. What departure preparations do SOLAS and good seamanship require to be confirmed?
Your Answer: (Not answered)
Correct Answer: B (Certificates and equipment condition, the passage plan and chart corrections, cargo securing and the draught and stability condition)
💡 Before departure, valid certificates, availability of critical equipment, the passage plan, corrected charts and a cargo and ballast condition within stability and strength limits should all be confirmed. Any omission may become an incident at sea.
✗
Question 23. What do SOLAS and the related standards require for the pressure containers of a fixed CO2 system?
Your Answer: (Not answered)
Correct Answer: B (Containers must be tested with capacity, charge and test date marked, and checked periodically)
💡 SOLAS and the pressure vessel standards require CO2 cylinders to be tested and clearly marked with charge and test date, and to be checked periodically for weight and pressure, since slow leakage leaves less agent than required.
✗
Question 24. What does SOLAS address regarding strainers on bilge suctions?
Your Answer: (Not answered)
Correct Answer: A (Strainers must be fitted and readily removable for cleaning, preventing blockage and loss of drainage capacity)
💡 SOLAS requires bilge suctions to be fitted with strainers readily removable for cleaning, preventing debris from blocking them and reducing drainage capacity. Welded-in strainers or ones never cleaned cause the drainage to fail, a common deficiency.
✗
Question 25. What is recommended when cargo in a hold self-heats and ignites?
Your Answer: (Not answered)
Correct Answer: C (Close the hold ventilation and openings and use the fixed extinguishing system or measures suited to the cargo)
💡 When cargo in a hold ignites, ventilation and openings should be closed to limit the oxygen available and the fixed extinguishing system, such as CO2, or measures suited to the cargo, such as flooding, used. Opening the hold for ventilation admits large quantities of air and feeds the fire, an incorrect response.
✗
Question 26. How must revisions of system documentation be managed?
Your Answer: (Not answered)
Correct Answer: D (Approved by authorised persons, issued promptly, superseded versions withdrawn and the crew informed)
💡 The ISM Code requires revisions of system documentation to be approved by authorised persons and issued in a controlled way, with the version and effective date shown and superseded versions withdrawn or marked as obsolete, and the crew informed so that they work to the latest version. Uncontrolled amendment leaves different versions in use on board.
✗
Question 27. What is required for the height of liferaft stowage?
Your Answer: (Not answered)
Correct Answer: A (Stowed at a height allowing the raft to float free and allowing persons to board and handle it)
💡 A liferaft should be stowed at a height that allows it to float free, clear of deck structures, and that permits persons to board and handle it, normally on a dedicated rack on the boat deck. Too high makes boarding difficult; too low risks damage by seas or prevents free floating.
✗
Question 28. What structural measure against inadvertent operation does SOLAS address in machinery spaces?
Your Answer: (Not answered)
Correct Answer: B (Clear identification of critical valves and switches to prevent accidents from incorrect operation)
💡 SOLAS and good practice require clear, durable identification of critical valves and switches in machinery spaces, preventing an accident from opening or closing the wrong item in an emergency. Temporary labels or reliance on memory do not comply.
✗
Question 29. What checking of survival craft stowage cradles is required?
Your Answer: (Not answered)
Correct Answer: C (Check the structure for corrosion and deformation and the lashings and limiters for reliability)
💡 Survival craft cradles should be checked for serious corrosion or deformation of the structure and for the reliability of the lashings and limiters, with the sliding surfaces smooth so that launching is unobstructed. Structural failure would prevent launching or allow the craft to move in a seaway, a serious hazard.
✗
Question 30. What checking of the firefighting equipment list against the ship is required?
Your Answer: (Not answered)
Correct Answer: D (Periodically verify the list against what is actually on board, replacing anything missing and updating records)
💡 The ISM Code and SOLAS require periodic verification of the firefighting equipment list against what is actually on board, including extinguishers, firefighter's outfits, hoses and fittings, with anything missing, damaged or expired made good and the records updated, preventing a shortfall from being discovered only at an inspection.
✗
Question 31. What does the ISM Code address regarding the link between drills and incident reporting?
Your Answer: (Not answered)
Correct Answer: D (Problems revealed in drills should be analysed and used for improvement, together with accident and near-miss reporting)
💡 ISM Code 9 requires non-conformities, accidents and hazardous occurrences to be investigated and analysed with corrective action. Problems revealed in drills should likewise be analysed and used for improvement, serving as a basis for raising the standard of safety management.
✗
Question 32. What interval applies to launching lifeboats into the water during drills on a cargo ship?
Your Answer: (Not answered)
Correct Answer: C (At least once every three months the boat is lowered into the water and manoeuvred, where reasonable and practicable)
💡 SOLAS III/19 requires a launching drill at least every three months and, where reasonable and practicable, the boat to be lowered into the water and manoeuvred at least once in that period, so that the crew acquires practical skill.
✗
Question 33. Under the ISM Code, the company shall designate person(s) (DPA) to be responsible for:
Your Answer: (Not answered)
Correct Answer: C (linking the company with the ship on safety and pollution prevention matters)
💡 SOLAS IX/6: the company shall designate person(s) (DPA) to link the company with the ship on safety and pollution prevention matters.
✗
Question 34. What is the usual maximum validity of a Cargo Ship Safety Construction Certificate?
Your Answer: (Not answered)
Correct Answer: C (Five years, with annual and intermediate surveys)
💡 Under SOLAS I/12 the Cargo Ship Safety Construction Certificate has a usual validity of not more than five years, with annual and intermediate surveys within it. It remains valid only if the surveys are carried out and endorsed, otherwise it lapses.
✗
Question 35. What does SOLAS address regarding stability when carrying timber deck cargo?
Your Answer: (Not answered)
Correct Answer: B (The increase in weight from water absorbed by the timber and ice accretion must be included, with the prescribed stability criteria applied)
💡 SOLAS and the Load Line Convention prescribe stability requirements for ships carrying timber deck cargo, requiring account to be taken of the weight gained from water absorbed, ice accretion and increased windage, assessed against the prescribed criteria, failing which capsize may occur.
✗
Question 36. Muster and embarkation stations shall:
Your Answer: (Not answered)
Correct Answer: D (be adequately illuminated and supplied from the emergency source)
💡 SOLAS III/11 requires adequate lighting of muster and embarkation stations from the emergency source.
✗
Question 37. Which type of portable extinguisher is suitable for electrical fires?
Your Answer: (Not answered)
Correct Answer: C (carbon dioxide)
💡 SOLAS II-2/10 requires extinguishers suitable for electrical fires, typically CO2 or dry powder.
✗
Question 38. What does SOLAS require regarding the verified gross mass of containers?
Your Answer: (Not answered)
Correct Answer: B (The shipper must provide the verified gross mass to the master before loading, and a container without a verified mass must not be loaded)
💡 SOLAS VI/2 requires the shipper to provide the verified gross mass before loading, and a container without a verified mass may not be loaded, preventing stack collapse, structural damage and injury from overweight containers.
✗
Question 39. After a renewal survey is completed, what must the Administration or recognised organisation do with the certificate?
Your Answer: (Not answered)
Correct Answer: C (Issue a new certificate stating completion of the survey and the period of validity)
💡 SOLAS requires a new certificate to be issued after a renewal survey, stating the date of completion and the period of validity. Extending the old certificate or leaving the master to enter dates does not comply.
✗
Question 40. Who is responsible for the preparation and execution of the voyage plan under SOLAS V and the related resolutions?
Your Answer: (Not answered)
Correct Answer: D (Prepared by the navigational officers and approved by the master, who bears responsibility)
💡 SOLAS V and the IMO resolutions require the voyage plan to be prepared by the navigating officers and approved by the master, who remains responsible. It cannot be prepared only ashore or by a pilot.
✗
Question 41. How long must dangerous goods documentation be kept on board?
Your Answer: (Not answered)
Correct Answer: A (For the prescribed period, normally until some time after discharge at the port of destination, for traceability and investigation)
💡 The documentation for dangerous goods, the manifest, stowage plan and special cargo information, must be retained for the prescribed period, normally until a certain time after discharge at the port of destination depending on the rules, so that the nature and stowage of the goods can be traced in the event of an incident or pollution.
✗
Question 42. The function of flame arresters in a tanker cargo tank venting system is to:
Your Answer: (Not answered)
Correct Answer: C (prevent external flame from entering the cargo tanks)
💡 SOLAS II-2/4 requires flame arresters to prevent external flame from passing through vent pipes into cargo tanks.
✗
Question 43. What does SOLAS address regarding the position of survival craft relative to the propulsion plant?
Your Answer: (Not answered)
Correct Answer: D (Stowed as far as practicable from the propulsion plant and other hazardous areas, avoiding interference from propellers or exhaust)
💡 SOLAS requires survival craft to be stowed as far as practicable from the propellers, thrusters and exhaust areas, preventing injury to persons or damage to the craft during launching, and allowing safe launching even while the ship still has headway.
✗
Question 44. Surveys required for ships include:
Your Answer: (Not answered)
Correct Answer: C (initial, renewal, intermediate, annual and additional surveys)
💡 SOLAS I/6: surveys include initial, renewal, intermediate, annual and additional surveys.
✗
Question 45. The isolating valve on the fire main serving the accommodation side has long been seized and cannot be operated. How should this be judged?
Your Answer: (Not answered)
Correct Answer: D (Fire main isolating valves must be operable at all times; being seized is a deficiency affecting the isolating function)
💡 Isolating valves on the fire main are used to isolate a damaged section of piping so that the rest of the system still receives water. They must be capable of manual operation at all times. Being seized deprives them of their isolating function and is a deficiency affecting the reliability of the firefighting system, which should be rectified.
✗
Question 46. On what basis should a maintenance programme be prepared?
Your Answer: (Not answered)
Correct Answer: C (The manufacturer's instructions, classification society requirements and the ship's actual service experience, revised as necessary)
💡 The ISM Code requires the maintenance programme to be based on the manufacturer's instructions and the requirements of the classification society and regulations, together with the actual service history of the equipment, failure history and survey findings, and to be revised after modification or failure, so that it remains effective.
✗
Question 47. A fixed detection system was tested with smoke. What action must follow detection under SOLAS?
Your Answer: (Not answered)
Correct Answer: B (An audible and visual alarm on the bridge or at the control station, indicating the space concerned)
💡 SOLAS requires detection to produce an audible and visual alarm on the bridge or at a continuously manned control station and to indicate the space involved. Automatic discharge is not necessarily required.
✗
Question 48. What do SOLAS and good practice address regarding the arrangement of GMDSS antennas?
Your Answer: (Not answered)
Correct Answer: C (Arranged so that equipment does not interfere with one another and essential communication capability remains if damage occurs)
💡 SOLAS and good practice require GMDSS antennas to be arranged to avoid interference between transmitting antennas and to retain back-up capability if the main antenna is damaged. Grouping them together means one failure disables all.
✗
Question 49. What is required regarding crew participation in improving the system?
Your Answer: (Not answered)
Correct Answer: D (Encourage the crew to suggest improvements and evaluate and respond to their suggestions)
💡 The ISM Code requires the company to encourage the crew to take part in improving the system, gathering suggestions through reports, meetings or other channels, assessing them and adopting them or explaining why not, so that the system is continuously improved with the practical experience of those at the sharp end.
✗
Question 50. What is the principle of zoning for a fixed fire detection and fire alarm system?
Your Answer: (Not answered)
Correct Answer: A (The system should detect by zone and indicate the affected zone so that the fire can be quickly located and action taken)
💡 Under SOLAS II-2/7 a fixed fire detection and fire alarm system should be arranged in sections so that the alarm indicates the section in which a fire or fault has occurred, enabling the crew quickly to locate the fire and take action. A fault in the detection system should be capable of being indicated, isolated and reset.
✗
Question 51. What is required for operating in ice in polar waters?
Your Answer: (Not answered)
Correct Answer: A (Control speed, enhance the look-out and monitor hull stress and changing ice conditions, stopping if conditions exceed the ship's capability)
💡 The Polar Code requires ice operations to control speed and course, enhance the look-out by radar and sight, continuously monitor hull stress and changes in the ice and stop or alter course if conditions exceed the ship's capability or the hull is damaged. Continuing regardless is not acceptable.
✗
Question 52. What cleaning of bilges is required?
Your Answer: (Not answered)
Correct Answer: D (Periodic removal of sludge and debris to keep suctions clear)
💡 Sludge and debris in the bilges block the suctions and reduce drainage capacity, so they should be removed periodically as part of the checks of the watertight doors and bilge system, with the strainers inspected. A record should be kept, particularly after carrying bulk cargoes that produce dust or debris.
✗
Question 53. What does SOLAS chapter II-2 require of the layout of fire mains and hydrants?
Your Answer: (Not answered)
Correct Answer: D (at least two jets reaching any part of the space protected, one of them on a single length of hose, with the specified fire pumps working)
💡 The chapter fixes the number of jets and the pressure by ship type: cargo ships as a rule require at least two jets from different hydrants, one of them available on a single length of hose to any part of the space protected, with separate requirements for machinery spaces. Main diameter, pump capacity and nozzle size have to match, or the far hydrant loses pressure. Layout follows coverage and simultaneous use, not ease of maintenance or a ratio of floor area, which tells nothing about jets.
✗
Question 54. What must the enclosed space entry testing record contain under SOLAS?
Your Answer: (Not answered)
Correct Answer: D (The date, location, parameters tested and results, and the issue of the permit)
💡 SOLAS and the IMO resolutions require records of enclosed space entry testing and permits, including the date, the space, the parameters tested — oxygen, toxic and flammable gases — the results and the permit issued, for traceability and inspection.
✗
Question 55. To which ship types does the Enhanced Programme of Inspections apply?
Your Answer: (Not answered)
Correct Answer: C (Oil tankers and bulk carriers)
💡 SOLAS XI-1/2 applies the enhanced programme of inspections to oil tankers and bulk carriers, imposing stricter survey requirements on these higher-risk ship types. It does not apply to all ships.
✗
Question 56. What should be noted in using sound and light signals to indicate intentions?
Your Answer: (Not answered)
Correct Answer: A (Use them as prescribed, watch for conflict with the other vessel's intentions and coordinate by VHF if necessary)
💡 Sound and light signals should be used as prescribed when vessels are in sight of one another to indicate manoeuvring intentions or to propose a course of action, but they do not replace actual avoiding action. After making a signal the other vessel's response should be watched and VHF used to coordinate if necessary, preventing conflicting intentions.
✗
Question 57. What must be done before a 406 MHz satellite EPIRB is brought into service?
Your Answer: (Not answered)
Correct Answer: C (Registered with the relevant authority with up-to-date information)
💡 406 MHz EPIRBs shall be registered with current information so that alerts can be verified and rescue coordinated.
✗
Question 58. An ECDIS is found using non-official electronic charts instead of official ENCs. The finding is?
Your Answer: (Not answered)
Correct Answer: B (Using non-official charts affects navigational safety, a navigational safety deficiency to be corrected)
💡 An ECDIS should use electronic navigational charts issued by an official hydrographic office, or approved equivalent data, to ensure that navigational information is accurate and official. Using non-official charts may lead to inaccurate information endangering navigational safety. It is a deficiency to be corrected.
✗
Question 59. Where shall the means of closing machinery space ventilation be located?
Your Answer: (Not answered)
Correct Answer: C (Outside the space for ready operation)
💡 It shall be capable of being operated from outside the space.
✗
Question 60. What precautions do SOLAS and good practice emphasise against the danger of overstressed mooring lines?
Your Answer: (Not answered)
Correct Answer: D (Ropes must be selected to match the safe working load of the fittings, and personnel must keep clear of the line of tension)
💡 Mooring lines must be matched to the safe working load of the equipment, and personnel must stand clear of the snap-back area. A parted line recoiling is a common fatal accident on board and requires attention from both ship and shore.
✗
Question 61. How many firefighter's outfits must a cargo ship of 1000 GT and above carry?
Your Answer: (Not answered)
Correct Answer: C (At least two)
💡 SOLAS II-2/10.10 requires at least two firefighter's outfits on cargo ships of 1000 GT and above. Tankers are additionally required to carry extra outfits, normally four.
✗
Question 62. An A-60 class division means a division capable of withstanding a standard fire test for:
Your Answer: (Not answered)
Correct Answer: D (60 minutes)
💡 SOLAS II-2/3: an A-60 class division is an A class division capable of withstanding a standard fire test for 60 minutes.
✗
Question 63. A newly built cargo ship undergoes an inclining test. What is the purpose of this test?
Your Answer: (Not answered)
Correct Answer: A (To determine the actual lightweight and position of the centre of gravity, providing the basis for stability information)
💡 The inclining test establishes the actual lightweight displacement and height of the centre of gravity by shifting known weights, forming the basis of the stability information. It is unrelated to speed, steering gear or tank capacity.
✗
Question 64. A steering gear compartment shall be provided with communication facilities:
Your Answer: (Not answered)
Correct Answer: B (two-way communication between the navigation bridge and the steering gear compartment)
💡 SOLAS II-1/29 requires two-way communication between the navigation bridge and the steering gear compartment.
✗
Question 65. What shall be done if radio equipment fails?
Your Answer: (Not answered)
Correct Answer: D (Repair it as soon as practicable and report as required)
💡 It shall be repaired as soon as practicable and reported as required.
✗
Question 66. What must be recorded for an abandon ship drill under SOLAS?
Your Answer: (Not answered)
Correct Answer: C (The date, the details of the drill, the survival craft used and the persons taking part)
💡 SOLAS requires the date, details, equipment used and participation of abandon ship and fire drills to be recorded in the deck log for verification at surveys and PSC. A date or a head count alone is incomplete.
✗
Question 67. What checking of survival craft markings is required?
Your Answer: (Not answered)
Correct Answer: A (Confirm the ship's name, port of registry and number of persons the craft can accommodate are clearly and completely marked)
💡 SOLAS requires survival craft to be clearly marked with the ship's name, port of registry and the number of persons it can accommodate. Inspection should confirm the markings are clear, durable and complete. Illegible markings hamper identification of the ship by rescuers and judgement of the craft's capacity, and are a common deficiency.
✗
Question 68. What must be considered in manning a ship for polar waters?
Your Answer: (Not answered)
Correct Answer: A (The greater difficulty of operations, the long search and rescue response times and the demands of working in low temperature)
💡 The Polar Code requires account to be taken of the greater difficulty of operations in polar regions, limited search and rescue resources with long response times and the demands of working and responding in low temperature, ensuring sufficient and trained personnel to cope in an emergency.
✗
Question 69. What manning of key positions is required?
Your Answer: (Not answered)
Correct Answer: D (The master and key positions must be manned in accordance with the minimum safe manning requirements, with substitutes arranged)
💡 A ship should carry the master and personnel for key positions such as chief officer, chief engineer and watchkeeping officers and engineers in accordance with the minimum safe manning document, with substitutes arranged for key positions. Reducing manning without authority or falling below the minimum leaves the ship non-compliant and affects emergency capability.
✗
Question 70. What attention must be paid to crew mental health and fatigue?
Your Answer: (Not answered)
Correct Answer: C (Attention to the effect of mental state and fatigue on safety, mitigated by sensible work and rest arrangements and communication)
💡 The MLC and STCW require attention to the mental health and fatigue of the crew, addressed by sensible arrangement of work and rest, maintained lines of communication and support and improved living conditions. Fatigue and mental stress affect judgement and performance and are major contributors to accidents.
✗
Question 71. Partially enclosed and fully enclosed lifeboats must have a capacity of at least:
Your Answer: (Not answered)
Correct Answer: D (All persons on board)
💡 SOLAS III/27: such lifeboats shall have a capacity for all persons on board and shall not be overloaded.
✗
Question 72. Which Code governs the stability of ships carrying grain in bulk?
Your Answer: (Not answered)
Correct Answer: C (The International Grain Code)
💡 The International Grain Code.
✗
Question 73. If the master finds a defect affecting safe navigation that cannot be repaired on board, the first action is to:
Your Answer: (Not answered)
Correct Answer: A (Report to the Company and arrange repair)
💡 The master should report to the Company so that repair can be arranged and the voyage adjusted.
✗
Question 74. A Polar Ship Certificate shall state:
Your Answer: (Not answered)
Correct Answer: A (the ship's operational limitations in polar waters, such as ice class and temperature range)
💡 SOLAS XIV/2: a Polar Ship Certificate states the ship's operational limitations in polar waters, such as ice class and temperature range.
✗
Question 75. A new chief officer needs to familiarise himself with the damage control plan. Where does SOLAS II-1/23 require it to be permanently exhibited?
Your Answer: (Not answered)
Correct Answer: B (On the navigation bridge, in the cargo control room and at the damage control station)
💡 SOLAS II-1/23 requires the damage control plan to be permanently exhibited at the positions where it will be needed, including the navigation bridge, cargo control room and damage control station.
✗
Question 76. What does security level 2 signify?
Your Answer: (Not answered)
Correct Answer: B (A heightened risk of a security incident requiring additional protective measures)
💡 Under the ISPS Code level 1 is the minimum in normal circumstances, level 2 additional measures when risk is heightened, and level 3 specific measures when an incident is probable or imminent. The measures escalate by level.
✗
Question 77. What is the principal means by which a flag State discharges its supervision?
Your Answer: (Not answered)
Correct Answer: A (Issuing valid certificates and carrying out surveys)
💡 Certification and survey are the principal means of flag State supervision.
✗
Question 78. Who shall approve the Cargo Securing Manual?
Your Answer: (Not answered)
Correct Answer: A (The Administration or its recognized organization)
💡 The Administration or its recognized organization.
✗
Question 79. A survey is carried out two months early. What is the effect under SOLAS?
Your Answer: (Not answered)
Correct Answer: C (The next due date is still counted from the original anniversary, not postponed by the early survey)
💡 The SOLAS window allows flexibility in scheduling but does not change the due date, which is counted from the certificate anniversary. An early survey does not postpone the next one, preventing effective extension of the certificate by surveying early.
✗
Question 80. When peak and deep tanks are used as ballast tanks, what does SOLAS II-1 require of the ballast system?
Your Answer: (Not answered)
Correct Answer: B (It must be capable of safely filling and emptying ballast tanks under all operating conditions)
💡 SOLAS II-1 requires the ballast system to fill and empty tanks safely under all operating conditions so that draught and stability can be controlled. It is not confined to port use.
✗
Question 81. What are the consequences if a similar serious deficiency recurs after a detention?
Your Answer: (Not answered)
Correct Answer: A (The ship's risk profile rises and she may be targeted for more frequent inspection)
💡 A recurrence of the same serious deficiency indicates a systemic problem in the system or management. The ship's risk profile rises and she may be targeted, for example as a high risk ship under the Tokyo MOU, with noticeably more frequent and stringent inspections.
✗
Question 82. What is the minimum number of fire pumps for a cargo ship of 1000 gross tonnage and above?
Your Answer: (Not answered)
Correct Answer: C (At least two independently driven fire pumps)
💡 Under SOLAS II-2/10 a cargo ship of 1000 gross tonnage and above should have at least two independently driven fire pumps so that water is still supplied if one fails. Each pump's capacity is not less than eighty per cent of the total required and the main pressure must be met.
✗
Question 83. What is required when checking the lighting at survival craft embarkation positions?
Your Answer: (Not answered)
Correct Answer: A (Confirm that the emergency lighting operates, covering the embarkation area and the water alongside)
💡 SOLAS requires the lighting of the embarkation stations, survival craft stowage positions and the water alongside, including emergency lighting, to be confirmed in working order and covering the required area, so that abandonment at night is adequately lit. An appearance check would not confirm availability during a blackout.
✗
Question 84. What is required for checking the tightness of hatch covers on a bulk carrier?
Your Answer: (Not answered)
Correct Answer: A (Periodic inspection of seals, cleats and drain channels with a hose test to verify weathertightness)
💡 SOLAS requires the hatch covers of a bulk carrier to remain weathertight, with periodic checks of seal ageing, the effectiveness of cleats and the clearance of drain channels, and a hose test where necessary to verify tightness, preventing sea water from entering the holds and damaging structure and cargo.
✗
Question 85. A VDR shall record:
Your Answer: (Not answered)
Correct Answer: D (date/time, position, speed, heading, bridge audio and other data)
💡 SOLAS V/20: a VDR records date/time, position, speed, heading, radar images and bridge audio.
✗
Question 86. A safety protection device of the main propulsion plant, such as the overspeed trip, is found bypassed in the engine room. The finding is?
Your Answer: (Not answered)
Correct Answer: D (Bypassing a safety protection device is a serious violation that may cause machinery casualties and lead to detention)
💡 Safety protection devices such as the overspeed trip and low lubricating oil pressure trip of the main engine are used to reduce speed or shut down automatically in abnormal conditions, protecting machinery and personnel. Bypassing them removes the protection and may cause damage to the main engine or even an engine room casualty. It is a serious violation that may normally lead to detention.
✗
Question 87. What does SOLAS address regarding stowage and immediate availability of survival craft?
Your Answer: (Not answered)
Correct Answer: C (Stowed where they can be reached and launched promptly, in a condition of immediate readiness)
💡 SOLAS requires survival craft to be stowed where they can be reached and launched promptly and to be in a condition of immediate readiness, with gravity davits able to be released without preparation. Dismantling them or stowing them in a hold makes them unusable on abandonment.
✗
Question 88. What does SOLAS address regarding product certification of life-saving appliances?
Your Answer: (Not answered)
Correct Answer: C (Appliances must hold type approval or product certificates from a recognised body attesting compliance with the performance standards)
💡 SOLAS requires life-saving appliances to comply with the performance standards such as the LSA Code and to hold type approval or product certificates. Approval marks and certificates are checked at survey and PSC, and equipment without an approval mark may not be accepted.
✗
Question 89. What electrical equipment is required in a pump room on a tanker?
Your Answer: (Not answered)
Correct Answer: B (Explosion-protected equipment, with the number of items and wiring minimised)
💡 A pump room is a high-risk space where hydrocarbon vapour can accumulate. SOLAS and the IBC Code require explosion-protected equipment with the number of items and wiring kept to a minimum, preventing electrical sparks from igniting vapour.
✗
Question 90. Before a towing operation, whether towing another vessel or being towed, what should be prepared in particular?
Your Answer: (Not answered)
Correct Answer: D (Check the strength and arrangement of the towline, define the towing force and means of communication, assess stability and manoeuvring safety and prepare contingency plans)
💡 Before a towing operation the strength and arrangement of the towline, including the emergency towline, should be checked, the towing force and speed determined, the manoeuvring and communication arrangements, including emergency signals, defined, the stability and manoeuvring safety of both vessels assessed and contingency plans for a towline failure prepared. A continuous lookout and communication should be maintained during the tow.
✗
Question 91. What is the principle for dealing with a risk of dragging anchor while at anchor?
Your Answer: (Not answered)
Correct Answer: D (Bring engines to readiness immediately, inform the bridge and master, and if necessary weigh or adjust the cable, warning nearby vessels)
💡 On a risk of dragging, engines should be brought to readiness at once, the bridge and master informed, cable veered or the anchor weighed as necessary, and nearby vessels warned, with the position monitored. Waiting or hesitating often leads to grounding or collision.
✗
Question 92. What is required for position monitoring when navigating in restricted waters?
Your Answer: (Not answered)
Correct Answer: B (Cross-check the position using several means such as visual bearings, radar and GPS, detecting any discrepancy early)
💡 SOLAS and good seamanship require the position in restricted waters to be cross-checked by several means, such as visual bearings, radar and GPS, detecting errors early. Reliance on a single means may lead to grounding through equipment error.
✗
Question 93. What is the purpose of the bilge water high level alarm in a machinery space?
Your Answer: (Not answered)
Correct Answer: C (To give an alarm when the bilge level rises abnormally, indicating flooding or failure of the drainage system)
💡 SOLAS II-1 requires a bilge water high level alarm in machinery spaces so that the watchkeeper is warned of abnormal accumulation, indicating flooding or a failure of the drainage system.
✗
Question 94. When a ship changes flag, which is required?
Your Answer: (Not answered)
Correct Answer: D (Both the former and new flag States must recognise the ship's safety status)
💡 Flag change requires formal recognition of safety status by both the former and new flag States.
✗
Question 95. A lifeboat shall be provided with at least how many hand flares?
Your Answer: (Not answered)
Correct Answer: B (6)
💡 SOLAS III/34 requires at least six hand flares in a lifeboat.
✗
Question 96. What do SOLAS and the related handbooks recommend for contact between survival craft after abandonment?
Your Answer: (Not answered)
Correct Answer: B (Maintain contact by two-way VHF, whistle or light and act together so as to be found more easily)
💡 SOLAS and the survival craft handbooks recommend that craft maintain contact by two-way VHF, whistle or light after abandonment, keeping together or close, acting in a coordinated way and conserving energy and supplies, improving the chance of detection by rescuers.
✗
Question 97. What work do the liferaft painter and the weak link in its falls each do?
Your Answer: (Not answered)
Correct Answer: A (the painter tensioning as the raft leaves the cradle to start inflation, the weak link parting when a sinking ship's pull exceeds its strength so the raft frees itself)
💡 The painter is made fast to the ship and to the raft: as the raft leaves the cradle the painter strains and pulls the inflation valve, so the raft is inflated at the water; if the ship goes down, the load on the painter exceeds the weak link and the link parts, freeing the raft instead of dragging it under. The hydrostatic release unit is the other route, releasing the lashings at about 15 metres of depth. The three work together, and the loss of any one may leave the raft down with the ship or unpumped on the surface.
✗
Question 98. What safety requirements apply to compressed air systems?
Your Answer: (Not answered)
Correct Answer: D (Safety valves and drains, preventing accumulation of oil causing explosion, with piping pressure rated and inspected periodically)
💡 SOLAS and good practice require compressed air systems to have safety valves and drains, with condensate and oil removed periodically, preventing overpressure of receivers and piping and accumulation of oil which can cause an explosion, a common cause of scavenge box explosions, with the piping and fittings inspected periodically.
✗
Question 99. The purpose of an inclining experiment is to:
Your Answer: (Not answered)
Correct Answer: B (determine the ship's stability elements such as the position of the centre of gravity)
💡 SOLAS II-1/5 requires an inclining experiment to determine stability elements for the master's stability information.
✗
Question 100. What do SOLAS and the related standards require regarding VHF transmitter power?
Your Answer: (Not answered)
Correct Answer: C (Power adequate for the required range, with adjustable power for close and longer range communication)
💡 SOLAS and the Radio Regulations require VHF equipment to have adequate power, normally not exceeding 25 watts, with adjustment available: low power close to shore to reduce interference and high power for longer range.