idship_idreport_datereported_bylocationnm_categorydescriptionimmediate_actionroot_causecorrective_actionnm_statusclosed_datecreated_at
112026-05-21C/E (CHEN YUANSHENG)ANCH - At AnchorsafetyOn 21st May 2026 at 0930 LT, while overhauling the FWG SW Pump motor, the electrician attempted to disconnect the power cables without switching off the main breaker or applying LOTO. This posed a severe risk of electric shock and arc flash to personnel.1. Halted the operation immediately; enforced strict LOTO application on the switchboard. 2. Conducted a mandatory Toolbox Talk for all engineers on Electrical Safety Standards.1. Failure to implement the Permit to Work (PTW) system for high-risk activities. 2. Lack of supervision by the Duty Engineer regarding electrical isolation protocols. 3. Complacency and inadequate risk awareness among the maintenance team.1. Halted the operation immediately; enforced strict LOTO application on the switchboard. 2. Conducted a mandatory Toolbox Talk for all engineers on Electrical Safety Standards. 3. Chief Engineer to conduct weekly audits of work permits.closed2026-06-042026-06-17 06:26:13
212026-05-25C/O (LI QIANG)Eastern Anchorage, SingaporesafetyWhile preparing for anchoring at Eastern Anchorage Singapore the OS was observed without safety goggles. During anchor lowering, the high tension on the chain and impact with the seabed can generate metal fragments/debris, posing a high risk of eye injury.1. Stopped the operation briefly, instructed OS to wear goggles, and checked other crew members PPE. 2. Conducted refresher training on "Anchor Handling Safety" for all deck crew.1. Inadequate Risk Assessment: The specific hazard of flying debris during anchor handling was not adequately addressed in the pre-task briefing. 2. Supervision Gap: The Officer on Watch failed to enforce PPE compliance before allowing the operation to start.1. Immediate: Stopped the operation briefly, instructed OS to wear goggles, and checked other crew members PPE. 2. Conducted refresher training on "Anchor Handling Safety" for all deck crew. 3. Increased frequency of safety rounds by Chief Officer during deck operations.closed2026-06-042026-06-17 06:26:13