Exam Home Website
中文 English
0
/100
FAIL
Correct: 0/100 Total Questions: 100 Time Spent: 60min0sec
Passing: 80
Retake History
Answer Review
✗
Question 1. What applies when security level 3 is set?
Your Answer: (Not answered)
Correct Answer: C (Further specific protective measures until the incident is resolved)
💡 Further specific protective measures until the incident is resolved.
✗
Question 2. What training in the use of firefighting equipment is required?
Your Answer: (Not answered)
Correct Answer: D (Crew must be familiar with the operation of each type of equipment, including extinguishers, hoses, fixed systems and breathing apparatus)
💡 SOLAS and STCW require those who would actually use firefighting equipment to know how to operate it, including selecting and using the different extinguishers, connecting hydrants and hoses, the conditions and procedure for releasing a fixed system and donning and checking breathing apparatus, ensured by training and drills.
✗
Question 3. What stability concern does SOLAS address when a ship encounters deck seas or ice accretion?
Your Answer: (Not answered)
Correct Answer: B (Assess the adverse effect of water on deck and ice accretion on stability and freeboard and take measures)
💡 SOLAS and the Load Line Convention require account to be taken of the added weight of water on deck and ice accretion and their effect on stability and freeboard, with measures such as reducing deck cargo or altering course to reduce risk.
✗
Question 4. What do SOLAS V and COLREG require when navigating in a narrow channel?
Your Answer: (Not answered)
Correct Answer: A (Keep as near to the outer limit on the starboard side as is safe and practicable, at a safe speed with an adequate look-out)
💡 COLREG Rule 9 requires a vessel in a narrow channel to keep as near to the outer limit on her starboard side as is safe and practicable, at a safe speed with an adequate look-out. High speed or occupying any part of the channel greatly increases the risk of collision.
✗
Question 5. SOLAS requires that the main propulsion machinery be:
Your Answer: (Not answered)
Correct Answer: A (controllable from the navigation bridge and also from the machinery space)
💡 SOLAS II-1 requires the main propulsion machinery to be controlled from the navigation bridge as well as from the machinery space.
✗
Question 6. What is the purpose of a heading transmission system?
Your Answer: (Not answered)
Correct Answer: C (Transmitting heading information to radar, AIS and similar equipment)
💡 It transmits heading information to radar, AIS and similar equipment.
✗
Question 7. Emergency lighting shall be capable of operating for at least:
Your Answer: (Not answered)
Correct Answer: B (18 hours)
💡 SOLAS II-1/42 requires the emergency source to provide emergency lighting for at least 18 hours.
✗
Question 8. Cargo ships of 1 000 GT and above shall be provided with at least how many independently driven fire pumps?
Your Answer: (Not answered)
Correct Answer: D (2)
💡 SOLAS II-2/10 requires at least two independently driven fire pumps for cargo ships of 1 000 GT and above.
✗
Question 9. What is the basic SOLAS II-1/42 requirement for the location of the emergency generator and its prime mover?
Your Answer: (Not answered)
Correct Answer: C (Outside category A machinery spaces, with an independent fuel supply)
💡 SOLAS II-1/42 requires the emergency source of power to be located outside category A machinery spaces so it remains available if that space is on fire, with a separate fuel supply.
✗
Question 10. Regarding launching and recovery of survival craft:
Your Answer: (Not answered)
Correct Answer: B (training shall be given in both launching and recovery)
💡 SOLAS III/19 requires training in both launching and recovery of survival craft.
✗
Question 11. What additional safety is required when carrying timber deck cargo?
Your Answer: (Not answered)
Correct Answer: A (Enhanced securing, safe access and unobstructed visibility, with attention to deck load and stability)
💡 Timber deck cargo requires enhanced securing with the prescribed methods and attention to the weight gained by water absorption, safe access for the crew and an unobstructed view from the bridge, with deck loading and stability calculated including the effects of water absorption and ice accretion, in accordance with the timber deck cargo requirements of the Load Line Convention.
✗
Question 12. What is the starting requirement for the emergency generator under list and trim?
Your Answer: (Not answered)
Correct Answer: D (It must start automatically and supply the emergency load under the prescribed angles of list and trim)
💡 SOLAS requires the emergency generator to start automatically and carry the emergency load under the prescribed angles of list and trim. Since a ship is often listed after damage, the emergency source must be available in that condition.
✗
Question 13. Steering trials are run at maximum service speed. Under SOLAS II-1/29, within what time must the main steering gear put the rudder over from 35 degrees on one side to 30 degrees on the other?
Your Answer: (Not answered)
Correct Answer: D (Not more than 28 seconds)
💡 SOLAS II-1/29 requires the main steering gear, at deepest seagoing draught and maximum service speed, to put the rudder over from 35 degrees to 30 degrees within 28 seconds. The 60-second limit applies to the auxiliary steering gear for 15 degrees to 15 degrees.
✗
Question 14. What do SOLAS and good practice address regarding the use of watertight doors to control heel after damage?
Your Answer: (Not answered)
Correct Answer: D (Act in accordance with the damage control information by isolating flooded compartments and, if necessary, counter-flooding to control heel)
💡 SOLAS requires action in accordance with the damage control information and booklet: isolating flooded compartments by closing watertight doors and valves, counter-flooding where necessary to reduce heel and assessing residual stability. Blind action may make the situation worse.
✗
Question 15. What are the key points in testing fire pumps during a drill?
Your Answer: (Not answered)
Correct Answer: C (Start the pumps in practice and check output and pressure, testing the emergency fire pump as well)
💡 In a fire drill the fire pumps should actually be started and the output and pressure checked against the requirement, with the starting and water supply capability of the emergency fire pump tested as well, so that the crew is familiar with the operation and the equipment is verified.
✗
Question 16. Each person in a lifeboat shall be provided with food of an energy value of not less than:
Your Answer: (Not answered)
Correct Answer: D (10 000 kJ)
💡 SOLAS III/34 requires food of not less than 10 000 kJ per person in a lifeboat.
✗
Question 17. Extension of a certificate is permitted:
Your Answer: (Not answered)
Correct Answer: B (only in special circumstances when the ship is not in a port of survey, as authorized by the Administration)
💡 SOLAS I/14: extension of a certificate is permitted only in special circumstances when the ship is not in a port of survey.
✗
Question 18. What radio communication measures are required when operating in polar regions?
Your Answer: (Not answered)
Correct Answer: A (Take account of limited satellite coverage and provide means such as HF unaffected by the region, with enhanced watchkeeping)
💡 Geostationary satellite coverage is limited in polar regions, above about 75 degrees latitude, so SOLAS and the Polar Code require means such as HF communication to be provided with a watch maintained and, where necessary, relaying through a coast station or another ship, ensuring that distress communication gets through.
✗
Question 19. What is required for closing appliances on overboard discharges below the load line?
Your Answer: (Not answered)
Correct Answer: B (Effective closing appliances operable from above the bulkhead deck, preventing back flooding)
💡 SOLAS and the Load Line Convention require discharges and inlets below the load line to have effective closing appliances such as non-return valves or cocks, operable from above the bulkhead deck, preventing sea water from entering. Temporary plugs of wood are not reliable.
✗
Question 20. After a collision, besides assisting the persons on the other vessel, what should be done?
Your Answer: (Not answered)
Correct Answer: C (Check the damage and flooding of own ship, assess safety and report to those concerned, preserving evidence as needed)
💡 After a collision, while assisting the persons on the other vessel provided own ship is safe, the damage and flooding should be checked, stability and safety assessed, those concerned informed and evidence preserved as needed, such as VDR data, logs and photographs. Leaving the scene or failing to assist may constitute an offence.
✗
Question 21. What emergency procedures should the PWOM contain?
Your Answer: (Not answered)
Correct Answer: B (Procedures for ice entrapment, hull damage, persons in the water and hypothermia and equipment failure at low temperature)
💡 The emergency procedures in the PWOM should address the risks specific to polar waters: ice entrapment and ice damage, hull cracking or flooding, persons overboard and hypothermia, failure of essential equipment at low temperature, loss of communication and the long response time of search and rescue, with responsibilities and resources identified.
✗
Question 22. What does SOLAS II-2 require regarding combustible materials in accommodation spaces?
Your Answer: (Not answered)
Correct Answer: B (Surface materials and furnishings must be restricted in combustibility and comply with prescribed flame spread requirements)
💡 SOLAS II-2 limits the combustibility of bulkheads, ceilings, deck coverings and furniture in accommodation spaces, reducing fire load and the rate of spread.
✗
Question 23. What fire precautions apply before entering a cargo tank or other enclosed space on a tanker?
Your Answer: (Not answered)
Correct Answer: C (Thorough ventilation and gas testing to confirm no flammable gas and acceptable oxygen content, with ventilation maintained during entry)
💡 Before entering a cargo tank, pump room or similar enclosed space on a tanker, thorough ventilation is required with testing of flammable gas, toxic gas and oxygen content all satisfactory, and an entry permit obtained, ventilation maintained during the entry and explosion-protected lighting and tools used, preventing ignition.
✗
Question 24. What does SOLAS address regarding the location of the main switchboard?
Your Answer: (Not answered)
Correct Answer: D (Located where it is accessible and protected from water, oil and fire, with appropriate guarding)
💡 SOLAS requires the main switchboard to be located where it is accessible, well ventilated and protected from water, oil and fire, with protective measures such as insulating mats in front, ensuring safe operation and reliable supply.
✗
Question 25. What happens to the statutory certificates when a ship changes to a new owner and flag?
Your Answer: (Not answered)
Correct Answer: B (The existing certificates cease to be valid and new ones must be issued by the new flag Administration or its authorised body after survey)
💡 SOLAS requires certificates to be issued by the Administration of the State whose flag the ship is entitled to fly. After a change of flag the existing certificates are no longer valid and new ones must be issued following survey by the new Administration. Using the old certificates is a serious deficiency.
✗
Question 26. Which ships does the International Safety Management Code reach?
Your Answer: (Not answered)
Correct Answer: A (every class of ship to which the Convention applies, together with their companies - passenger ships, tankers, chemical carriers and bulk carriers included)
💡 The Code runs along the Convention's own scope rather than sorting by ship type: passenger ships, cargo ships (tankers, chemical and gas carriers, bulk carriers among them) and mobile offshore drilling units required by the Convention, together with the companies that operate them, must all have a system. The certificate is issued to the ship (the Safety Management Certificate), but the system is built at company level, which is why companies and ships enter the scope together. Reading the Code as reaching one type of ship only usually means it has been confused with the ship-type technical provisions.
✗
Question 27. What additional safety measure does SOLAS require for remote closing of watertight doors from the bridge?
Your Answer: (Not answered)
Correct Answer: C (An audible and visual alarm before closing, so that persons can move clear)
💡 SOLAS requires an audible and visual alarm and a delay before remote closing of a watertight door from the bridge, giving persons nearby time to move clear and preventing injury. Visual confirmation is not sufficient when operating at a distance.
✗
Question 28. What is the principle for the inspection and maintenance of portable fire extinguishers?
Your Answer: (Not answered)
Correct Answer: B (Their pressure, seals, nozzles and securing should be checked regularly, with maintenance or recharging at the required intervals and records kept)
💡 Under SOLAS II-2/10 and the maintenance requirements portable fire extinguishers should have their pressure indication, seals, nozzles and securing checked regularly and be maintained or recharged at the required intervals, by an approved service provider where applicable, with records kept, ensuring they are always available.
✗
Question 29. What reporting is required if equipment fails within a VTS area?
Your Answer: (Not answered)
Correct Answer: A (Report the failure and the ship's movements to the VTS at once so traffic can be managed)
💡 A failure within a VTS area should be reported to the VTS promptly, enabling the traffic centre to warn and manage surrounding vessels. Concealing or delaying the report increases the risk of collision.
✗
Question 30. During the voyage the temperature records for a solid bulk cargo show a steady rise. What treatment of the matter is acceptable for the master?
Your Answer: (Not answered)
Correct Answer: C (testing made more frequent and the cause looked into, ventilation or sealing decided by what the cargo schedule requires, company and port informed)
💡 The Code prescribes different treatment by cargo: some self-heating materials want surface ventilation to carry heat off, others must have air restricted so the oxygen does not feed the reaction, and carbon dioxide is released in one dose to the designed concentration once the space is proved clear and tight. The basis is the proper name, the moisture and the trend, not the single clue of a rising thermometer; opening a hold can also bring smoke back over the working party. Closer record-keeping, report and measurement are the practical ship's side of it.
✗
Question 31. What should the radio personnel do when the abandon ship alarm is sounded?
Your Answer: (Not answered)
Correct Answer: D (Ensure a distress alert has been transmitted and maintain communication, taking portable radio equipment into the survival craft)
💡 On the abandon ship alarm, the personnel responsible for radio should ensure a distress alert has been sent with the position and nature of distress, attempt to establish communication and take the portable VHF and, where applicable, the EPIRB into the survival craft as prescribed, so that distress communication continues after abandonment.
✗
Question 32. What does SOLAS require for side scuttles in the shell below the freeboard deck?
Your Answer: (Not answered)
Correct Answer: D (Effective hinged closing appliances capable of maintaining watertightness at sea)
💡 SOLAS II-1/16 requires side scuttles below the freeboard deck to have effective hinged watertight closing appliances capable of maintaining watertightness at sea. Fixed windows or improvised timber blanking do not comply.
✗
Question 33. Within what period after embarkation must passenger ships conduct a muster and drill for passengers?
Your Answer: (Not answered)
Correct Answer: B (Within 24 hours)
💡 SOLAS III requires a muster and drill for passengers within 24 hours of embarkation so that passengers are familiar with their duties and muster stations.
✗
Question 34. Why should the length and diameter of fire hoses meet the requirements?
Your Answer: (Not answered)
Correct Answer: B (To ensure the hose reaches the protected space, is easy to handle and does not affect discharge pressure)
💡 A fire hose should be of appropriate length and diameter: too long increases friction loss and reduces pressure, too short cannot reach the protected space. Every hydrant's hose should reach any position in the protected space requiring it and be suitable for operation by two persons.
✗
Question 35. How must the loading instrument of a bulk carrier be used?
Your Answer: (Not answered)
Correct Answer: B (Compute strength and stability for the planned sequence before cargo work and monitor continuously during it)
💡 SOLAS requires the approved loading instrument to be used to compute hull strength and stability at each stage of the planned sequence before cargo work, with continuous monitoring during the operation and updating as it progresses, preventing excessive stress at any stage. Computing only at the end cannot prevent damage during the work.
✗
Question 36. During steering gear trials in port the change-over of power units between the machinery control room and the bridge was found unsatisfactory. What does SOLAS require?
Your Answer: (Not answered)
Correct Answer: B (Change-over of power shall be capable of being effected quickly from the bridge or the steering gear compartment)
💡 SOLAS II-1/35-1 requires that change-over of the steering gear power units be effected quickly, either from the bridge or from the steering gear compartment, so control can be restored rapidly.
✗
Question 37. What do SOLAS and the related conventions address regarding sewage treatment systems?
Your Answer: (Not answered)
Correct Answer: D (The plant must operate and discharge in accordance with the requirements, with attention to the risk of harmful gas)
💡 A sewage treatment plant must be operated and discharge in accordance with MARPOL, and attention paid to the harmful gases which may be produced in the process. The relevant spaces should be ventilated, entry restricted and testing carried out as prescribed to prevent poisoning.
✗
Question 38. What does SOLAS address regarding the quantity of extinguishing medium in a fixed system?
Your Answer: (Not answered)
Correct Answer: B (Calculated from the volume of the protected space with the prescribed margin)
💡 SOLAS requires the quantity of extinguishing medium to be calculated from the net volume of the protected space and to meet the prescribed minimum concentration and margin, ensuring an effective concentration after release.
✗
Question 39. Where must emergency lighting be provided, and what is it for?
Your Answer: (Not answered)
Correct Answer: C (escape routes and exits, muster and boarding stations and the places where work must go on, lighting that survives the failure)
💡 When the main supply has gone people evacuate through smoke and steam, and a route or an exit that is only painted is no use at all. Emergency lighting therefore covers the escape ways in the machinery and accommodation spaces, the exits, the muster and boarding stations, and the positions where work or watching must still go on, such as the steering gear, the fire pumps and the emergency source itself; spaces where passengers gather carry their own requirement. The lamps come on of themselves when the main supply fails and run from the emergency source for the period laid down, longer for passenger ships than for cargo. Luminous markers only assist, a hand lamp is not a substitute for fixed lighting, and neither takes the place of exit and stairway lit all the way out.
✗
Question 40. What should be done with firefighter's outfits after use?
Your Answer: (Not answered)
Correct Answer: D (Clean, dry, inspect for damage and return to stowage, replacing defective parts promptly)
💡 After use, including in drills, firefighter's outfits should be cleaned, dried and inspected for damage such as torn clothing, low cylinder pressure or perished face masks, with defective parts replaced and the outfit returned to its stowage, ready for the next use.
✗
Question 41. A PSCO tested ventilation closing devices and found some seized. What does SOLAS address?
Your Answer: (Not answered)
Correct Answer: A (Closing devices of machinery space ventilators must close rapidly to cut off ventilation and air supply)
💡 SOLAS II-2 requires machinery space ventilator closing devices to close rapidly and remain effective, cutting off the air supply in a fire. Seized devices or a lack of regular testing are common deficiencies.
✗
Question 42. Which Code governs the stability of ships carrying grain in bulk?
Your Answer: (Not answered)
Correct Answer: C (The International Grain Code)
💡 The International Grain Code.
✗
Question 43. A PSCO asks you to confirm the ship's permanent identification number on the hull. What does SOLAS XI-1/3 require?
Your Answer: (Not answered)
Correct Answer: A (The IMO ship identification number)
💡 SOLAS XI-1/3 requires the IMO ship identification number to be permanently marked. Unlike the registry number, call sign or MMSI, it does not change with the ship's name or flag.
✗
Question 44. What is the particular danger of a cargo leak on a gas carrier?
Your Answer: (Not answered)
Correct Answer: A (The cargo is often cryogenic, flammable or toxic; a leak vaporises rapidly and may form a flammable or toxic cloud)
💡 Gas carrier cargoes such as LPG and LNG are cryogenic, flammable, explosive or toxic. A leak vaporises rapidly and mixes with air to form a flammable or toxic cloud which may flash or explode on contact with a source of ignition, so the response must be by trained personnel.
✗
Question 45. What should be done if a cable penetration seal in a division is damaged?
Your Answer: (Not answered)
Correct Answer: B (Repair promptly with an approved penetration seal to restore the fire and smoke integrity of the division)
💡 A damaged cable penetration seal leaves an opening through the division and should be repaired promptly with an approved penetration seal. Filling it with cement, foam or unsuitable material does not provide equivalent fire and smoke performance and is a deficiency.
✗
Question 46. What does SOLAS require regarding the starting arrangements for fire pumps?
Your Answer: (Not answered)
Correct Answer: C (They must be capable of remote starting from the bridge or fire control station, with means at the hydrants to start a pump)
💡 SOLAS requires fire pumps to be capable of remote starting by the watchkeeper from the bridge or a fire control station, with means at the hydrants to start a pump, so water is available quickly in a fire.
✗
Question 47. What does SOLAS II-2 require where the length of an enclosed corridor in accommodation spaces exceeds a certain figure?
Your Answer: (Not answered)
Correct Answer: A (A corridor exceeding 13 m must have access to escape routes at both ends)
💡 SOLAS II-2/13 requires an enclosed corridor longer than 13 m to give access to escape routes at both ends, so that occupants are not trapped in a dead end.
✗
Question 48. How must the electrical system perform when the ship is listed?
Your Answer: (Not answered)
Correct Answer: A (It must operate normally under the prescribed angles of list and trim, unaffected by the arrangement or oil levels)
💡 SOLAS requires generator sets, switchboards and essential electrical equipment to operate normally under the prescribed angles of list and trim, including that lubrication and fuel supply are unaffected by the inclination and that relays and switches operate reliably, ensuring electrical supply when the ship is listed after damage.
✗
Question 49. In which spaces must a bulk carrier be fitted with water ingress detection and alarm systems?
Your Answer: (Not answered)
Correct Answer: C (Cargo holds, ballast tanks and dry spaces)
💡 SOLAS XII/12 requires water level detectors with alarms in cargo holds, ballast tanks and dry spaces so that flooding is detected early.
✗
Question 50. What is the purpose of the radar reflector among the lifeboat equipment?
Your Answer: (Not answered)
Correct Answer: C (To increase the radar echo of the boat so that it is detected by searching vessels)
💡 SOLAS requires a lifeboat to carry a radar reflector, increasing the radar echo so that searching vessels detect the boat at a greater distance, improving the chance of rescue.
✗
Question 51. What is required for the height of liferaft stowage?
Your Answer: (Not answered)
Correct Answer: A (Stowed at a height allowing the raft to float free and allowing persons to board and handle it)
💡 A liferaft should be stowed at a height that allows it to float free, clear of deck structures, and that permits persons to board and handle it, normally on a dedicated rack on the boat deck. Too high makes boarding difficult; too low risks damage by seas or prevents free floating.
✗
Question 52. How should training needs be identified and met?
Your Answer: (Not answered)
Correct Answer: C (Identified from the operation of the system, drills and inspections and then delivered)
💡 The ISM Code and STCW require the company and the ship to identify training needs from drill assessments, findings at inspection and the analysis of accidents and near misses, such as unfamiliarity with equipment or unclear emergency duties, and to organise targeted training and assessment, so that training matches the actual need.
✗
Question 53. On what basis do PSCOs judge whether there has been an ISM system failure?
Your Answer: (Not answered)
Correct Answer: A (Whether the system is effectively implemented in practice, not merely whether documents are complete)
💡 PSCOs judge system failure by whether the SMS works in practice, for example in maintenance, drills and handling of non-conformities. Complete documentation with ineffective implementation can still be a failure.
✗
Question 54. The purpose of ships' routeing systems is to:
Your Answer: (Not answered)
Correct Answer: B (promote safe navigation and reduce the risk of collision and grounding)
💡 SOLAS V/10 requires compliance with adopted routeing systems to promote safety of life at sea.
✗
Question 55. What is the usual SOLAS requirement for the number of portable extinguishers in a machinery space?
Your Answer: (Not answered)
Correct Answer: D (A prescribed number according to the volume and arrangement of the space, with at least a stated number in each space)
💡 SOLAS II-2/10.3 requires a prescribed number of portable extinguishers in machinery spaces according to volume and arrangement, with at least a stated number in each space. An inadequate number is a common deficiency.
✗
Question 56. Which Convention governs the ship's handling of ballast water?
Your Answer: (Not answered)
Correct Answer: B (The Ballast Water Management Convention)
💡 Ballast water is to be managed under the Ballast Water Management Convention.
✗
Question 57. An inert gas system shall be used:
Your Answer: (Not answered)
Correct Answer: A (to maintain cargo tanks inert during cargo operations, ballasting and while at sea)
💡 SOLAS II-2/5: the inert gas system shall be used to maintain cargo tanks inert during cargo operations, ballasting and while at sea.
✗
Question 58. A 4200 GT cargo ship on international voyages has three pumps in the machinery space. Under SOLAS II-2/10.2, what is the minimum fire pump arrangement?
Your Answer: (Not answered)
Correct Answer: B (At least two independently driven fire pumps)
💡 SOLAS II-2/10.2 requires cargo ships of 1000 GT and above to have at least two independently driven fire pumps. At 4200 GT the ship is well above the threshold, so two is the minimum.
✗
Question 59. What is the usual replacement interval for a hydrostatic release unit of an inflatable liferaft?
Your Answer: (Not answered)
Correct Answer: A (Not more than twelve months, checked or replaced with the annual liferaft service)
💡 A hydrostatic release unit should be checked together with the annual service of the liferaft and replaced at the required interval, normally not more than twelve months, so that it operates reliably and lets the liferaft float free when the ship sinks.
✗
Question 60. What does SOLAS address regarding the number of breathing apparatus?
Your Answer: (Not answered)
Correct Answer: B (Sufficient spare cylinders must be provided alongside the outfits, allowing extended use or a change while inside)
💡 SOLAS requires sufficient spare cylinders in addition to those with the firefighter's outfits, particularly on tankers, enabling rescuers to extend their working time inside or to supply a person being rescued. One cylinder per outfit would not meet the actual need.
✗
Question 61. The emergency steering position shall be located:
Your Answer: (Not answered)
Correct Answer: B (in the steering gear compartment)
💡 SOLAS V/13: the emergency steering position shall be located in the steering gear compartment.
✗
Question 62. What do SOLAS and the IMSBC Code address regarding cargo ventilation during a voyage?
Your Answer: (Not answered)
Correct Answer: A (Ventilation should be decided according to the cargo and dew point conditions, avoiding condensation or increased self-heating from incorrect ventilation)
💡 Ventilation should be decided by the nature of the cargo and the dew point. Ventilation is needed to remove heat, but if the outside dew point is higher than in the hold it causes condensation, wetting the cargo and possibly increasing self-heating. Incorrect ventilation can cause cargo damage and danger.
✗
Question 63. Which of the following defines sea area A2?
Your Answer: (Not answered)
Correct Answer: D (The area, excluding sea area A1, within the coverage of at least one MF coast station with DSC alerting)
💡 A1 is within coverage of at least one VHF coast station with DSC; A2 is, excluding A1, within coverage of at least one MF coast station with DSC. Both are defined by coast station coverage, not by distance offshore.
✗
Question 64. Which fixed fire-extinguishing system shall be provided for the cargo tank deck area of a tanker?
Your Answer: (Not answered)
Correct Answer: A (Deck foam system)
💡 SOLAS II-2/10.5: tankers shall be fitted with a fixed deck foam system for the cargo tank deck area.
✗
Question 65. What is required for the display of alarms from a fixed fire detection and fire alarm system?
Your Answer: (Not answered)
Correct Answer: A (The alarm must be displayed on the bridge or at a continuously manned central control station and indicate the space concerned)
💡 SOLAS requires fire alarms to be displayed on the bridge or at a continuously manned central control station and to indicate the space in which the alarm was initiated, so the fire can be located at once.
✗
Question 66. What does SOLAS require for electrical equipment used in hazardous areas of machinery spaces?
Your Answer: (Not answered)
Correct Answer: C (It must be of a type protected against the hazard appropriate to that area)
💡 SOLAS II-1 requires electrical equipment in machinery spaces and other hazardous areas to be of a type protected against the particular hazard, so as to prevent ignition.
✗
Question 67. What is required for operating in ice in polar waters?
Your Answer: (Not answered)
Correct Answer: A (Control speed, enhance the look-out and monitor hull stress and changing ice conditions, stopping if conditions exceed the ship's capability)
💡 The Polar Code requires ice operations to control speed and course, enhance the look-out by radar and sight, continuously monitor hull stress and changes in the ice and stop or alter course if conditions exceed the ship's capability or the hull is damaged. Continuing regardless is not acceptable.
✗
Question 68. Under the SOLAS chapter V requirements for the field of vision from the conning position, which statement about seeing the sea surface ahead of the bow is correct?
Your Answer: (Not answered)
Correct Answer: B (the field should run from dead ahead to 22.5 degrees abaft the beam on each side, the sea surface ahead being visible at not less than twice the ship's length and in any case 500 m)
💡 Regulation V/22 sets checkable figures: an arc from dead ahead to 22.5 degrees abaft the beam on each side, with the sea surface visible from an eye height of 1.5 times the maximum summer draft or 15 m, whichever is greater, at twice the ship's length but not less than 500 m — in both loaded and ballast conditions.
✗
Question 69. Which of the following is NOT required navigation equipment under SOLAS V/19?
Your Answer: (Not answered)
Correct Answer: A (facsimile machine)
💡 SOLAS V/19: a facsimile machine is not among the navigation equipment required by SOLAS V/19.
✗
Question 70. What is the purpose of the reference documents in a ship security plan, such as the security assessment report?
Your Answer: (Not answered)
Correct Answer: C (To provide the basis for the measures in the plan, showing the risks they address)
💡 The ISPS Code requires the ship security plan to contain reference documents such as the security assessment report, showing the risks that the measures in the plan address and the conclusions of the assessment, so that the measures are targeted. Without that basis the measures become a formality.
✗
Question 71. What are the key points of the monthly inspection of survival craft launching appliances?
Your Answer: (Not answered)
Correct Answer: B (Check the brake, release gear, falls and sheaves and the securing arrangements for operation and condition)
💡 SOLAS III/20 requires a monthly inspection of the launching appliances of survival craft: checking that the brake holds reliably, the release gear operates correctly, the falls and sheaves are free of broken wires and wear and the securing arrangements release properly, with any defects found and the action taken recorded.
✗
Question 72. What is the correct practice for ventilating an enclosed space before entry?
Your Answer: (Not answered)
Correct Answer: C (Continuous mechanical ventilation, followed by testing to confirm acceptable readings before entry)
💡 Continuous mechanical ventilation should be carried out before entry, followed by gas testing, if necessary after a settling period, to confirm acceptable readings. Natural ventilation through an open hatch, or ventilating without testing, does not ensure safety.
✗
Question 73. What is the purpose of the rudder angle indicator?
Your Answer: (Not answered)
Correct Answer: C (Showing the actual rudder angle)
💡 It shows the actual rudder angle.
✗
Question 74. Besides the damage control plan, what should the damage control information include?
Your Answer: (Not answered)
Correct Answer: D (A damage control booklet or notes for the master, including measures for cross-flooding, listing control and regaining stability)
💡 SOLAS II-1/23 requires, besides the damage control plan, information for the master such as a damage control booklet covering cross-flooding, heel control and restoring stability, for use in a damage situation.
✗
Question 75. What does the safety management system require in an emergency on board?
Your Answer: (Not answered)
Correct Answer: D (Report immediately and take action under the emergency procedures of the system, with shore-based support from the company)
💡 ISM Code 8 requires the company to establish emergency preparedness procedures. In an emergency the ship reports and acts under those procedures with shore support and resources from the company. Waiting for instructions delays the response.
✗
Question 76. What does SOLAS address regarding boiler feed water and water level control?
Your Answer: (Not answered)
Correct Answer: A (Water level indication with low water level alarm and protection, preventing damage from a dry boiler)
💡 SOLAS requires boilers to have water level indication with low water level alarm and protection, giving warning and shutting down the boiler if water is low, preventing overheating damage or explosion.
✗
Question 77. What is the purpose of the water ingress detection system required on a bulk carrier?
Your Answer: (Not answered)
Correct Answer: B (To give an alarm when water enters the cargo holds and fore and aft spaces, enabling the crew to detect and deal with it promptly)
💡 Under SOLAS XII/12 a bulk carrier should have water ingress detection and alarm systems for the cargo holds and the forepeak and similar spaces, giving an alarm on the bridge promptly when water enters so that the crew can detect the ingress early and take pumping, leak-hunting and damage control measures, preventing the situation from worsening. The testing of the system should be kept effective.
✗
Question 78. To which ship types does the Enhanced Programme of Inspections apply?
Your Answer: (Not answered)
Correct Answer: C (Oil tankers and bulk carriers)
💡 SOLAS XI-1/2 applies the enhanced programme of inspections to oil tankers and bulk carriers, imposing stricter survey requirements on these higher-risk ship types. It does not apply to all ships.
✗
Question 79. The garbage record book is found to disagree with the actual garbage categories and quantities and some discharge records are missing. The finding is?
Your Answer: (Not answered)
Correct Answer: B (False records make garbage management untraceable, a pollution prevention record deficiency)
💡 The garbage record book should truthfully record the category, quantity, means of disposal and time and place, being proof of compliance in garbage management. False or missing records make management untraceable. It is a pollution prevention record deficiency to be corrected and may lead to detention or penalty in serious cases.
✗
Question 80. A PSCO asks you to explain the term 'Administration' as used in SOLAS. What is the correct meaning?
Your Answer: (Not answered)
Correct Answer: B (The Government of the State whose flag the ship is entitled to fly)
💡 SOLAS I/2 defines 'Administration' as the Government of the State whose flag the ship is entitled to fly. A classification society acts only as a recognised organisation authorised by the Administration.
✗
Question 81. What information must the master have before departure?
Your Answer: (Not answered)
Correct Answer: B (Approved stability information including damage stability)
💡 Approved stability information, including damage stability, shall be available to the master.
✗
Question 82. What are the key points in starting a lifeboat engine?
Your Answer: (Not answered)
Correct Answer: A (Prepare for starting before launching as prescribed, then start promptly after entering the water and check the cooling water discharge)
💡 Before launching, the boat engine should be prepared as the manufacturer prescribes, such as checking fuel, battery and cooling water, and started promptly once in the water with the cooling water discharge and smooth running checked, so that the boat is under control. Preparing only after entering the water delays the getaway.
✗
Question 83. What does SOLAS require regarding operating instructions and illustrations for life-saving appliances?
Your Answer: (Not answered)
Correct Answer: C (Instructions and illustrations posted at the survival craft in the working language of the ship or English)
💡 SOLAS requires operating instructions and clear illustrations, such as the steps for lowering, releasing and starting the engine, to be posted at the survival craft in the working language of the ship or in English, so that the crew can act quickly from the diagram in an emergency.
✗
Question 84. When encountering ice or icebergs, a ship shall:
Your Answer: (Not answered)
Correct Answer: B (navigate with caution, report as necessary and keep a safe distance)
💡 SOLAS V/31-32 requires monitoring of ice, cautious navigation and reporting.
✗
Question 85. What does SOLAS address regarding the location of the emergency fire pump?
Your Answer: (Not answered)
Correct Answer: A (Located outside the machinery space with independent power and a separate suction)
💡 SOLAS requires the emergency fire pump to be located outside category A machinery spaces with an independent source of power and a separate suction, so that it is not affected by a fire in that space and can draw water independently.
✗
Question 86. What do SOLAS and the CSS Code address regarding deck cargo?
Your Answer: (Not answered)
Correct Answer: D (Deck loads must be checked against deck strength and their effect on stability, with securing under the securing manual)
💡 SOLAS requires the local strength of the deck and the effect on stability and freeboard to be checked when carrying cargo units on deck, with securing and protection in accordance with the securing manual, preventing overloading or loss of cargo overboard.
✗
Question 87. Dangerous goods shall be stowed:
Your Answer: (Not answered)
Correct Answer: A (in accordance with the IMDG Code, with segregation to prevent dangerous reactions)
💡 SOLAS VII/3 requires stowage and segregation of dangerous goods in accordance with the IMDG Code.
✗
Question 88. If a ship fails a survey because of an equipment deficiency, what may the Administration do?
Your Answer: (Not answered)
Correct Answer: B (Require rectification within a period and re-inspect afterwards, with the validity of the certificate possibly affected meanwhile)
💡 SOLAS I/12 permits the Administration to suspend or withdraw a certificate where the ship does not comply. In practice rectification within a period and re-inspection is required before validity is maintained or restored. A certificate must not be issued with a deficiency outstanding.
✗
Question 89. What is required in handling a work injury to a crew member?
Your Answer: (Not answered)
Correct Answer: D (Give first aid at once, arrange necessary treatment and report to the company, keeping records and evidence)
💡 A work injury requires immediate first aid and necessary treatment, with medical advice sought or an evacuation arranged where needed, prompt reporting to the company as required and retention of the accident record, medical records and relevant evidence such as photographs and statements, for the determination of the injury and the analysis of responsibility.
✗
Question 90. A certificate exempting a ship from certain convention requirements is called:
Your Answer: (Not answered)
Correct Answer: C (An Exemption Certificate)
💡 An Exemption Certificate is issued where special construction makes full compliance impracticable.
✗
Question 91. When loading solid bulk cargoes liable to liquefy, care must be taken to prevent:
Your Answer: (Not answered)
Correct Answer: B (Water accumulation in the holds)
💡 Accumulated water can cause liquefaction, so trimming and drainage are essential.
✗
Question 92. Which statement about the enhanced programme of inspections for tankers and bulk carriers is correct?
Your Answer: (Not answered)
Correct Answer: B (It prescribes stricter close-up examination and thickness measurement, and requires a survey planning document)
💡 The ESP requires a survey planning document identifying the extent of close-up surveys and thickness measurements, and is stricter than routine surveys. Its application is not determined solely by an age of 20 years.
✗
Question 93. How many hand flares must each survival craft carry?
Your Answer: (Not answered)
Correct Answer: A (Six)
💡 SOLAS III requires six hand flares in each survival craft, in addition to the four rocket parachute flares required separately. The two numbers are different.
✗
Question 94. What is the requirement for the safety lamp in a firefighter's outfit?
Your Answer: (Not answered)
Correct Answer: D (An electric safety lamp capable of continuous illumination for at least three hours)
💡 SOLAS requires an electric safety lamp giving continuous illumination for at least three hours, safe in smoke and flammable atmospheres. Ordinary torches and flame lamps are not acceptable.
✗
Question 95. For portable fire extinguishers, the most important check item is:
Your Answer: (Not answered)
Correct Answer: D (pressure indication and seal integrity)
💡 SOLAS II-2/10 requires extinguishers to be kept ready for use; checks include pressure indication and seal integrity.
✗
Question 96. When transiting a high-risk piracy area, which of the following is NOT among the measures recommended by Best Management Practices?
Your Answer: (Not answered)
Correct Answer: C (Switching off AIS and automatic identification to avoid being tracked)
💡 Best Management Practices recommend measures such as increasing speed and freeboard, fitting razor wire and physical barriers, providing and drilling a citadel, strengthening lookout and lighting, and reporting as required and reporting pirate activity. AIS should generally remain on, and switching it off may breach the rules and hinder search and rescue, so it is not a recommended measure.
✗
Question 97. What do GMDSS procedures require for the transmission of a DSC distress alert?
Your Answer: (Not answered)
Correct Answer: C (Select the nature of distress and the subsequent communication mode as designed, then move to the appropriate frequency at once)
💡 A DSC distress alert requires the nature of distress and the subsequent communication mode to be selected as designed, such as VHF channel 16 or MF 2182 kHz, followed immediately by a move to that frequency to establish distress traffic, with a watch maintained on the equipment.
✗
Question 98. The training manual shall be written in:
Your Answer: (Not answered)
Correct Answer: B (the working language of the ship, with translations where necessary)
💡 SOLAS III/35 requires the training manual in the working language of the ship, with translations where necessary.
✗
Question 99. What is the purpose of the magnetic compass?
Your Answer: (Not answered)
Correct Answer: D (Providing magnetic heading and acting as a back-up to the gyro compass)
💡 It provides the magnetic heading and backs up the gyro compass.
✗
Question 100. Under Chapter XI-1, the flag State shall discharge its supervision:
Your Answer: (Not answered)
Correct Answer: C (Through surveys and certification)
💡 Through surveys, certification and, where necessary, additional inspections.