Question 1. In addition to ventilation, what shall be fitted in paint lockers and flammable liquid stores?
Your Answer: (Not answered)
Correct Answer: D (A fixed fire-extinguishing system)
💡 SOLAS II-2/10.6.3: paint lockers and flammable liquid stores shall have a fixed fire-extinguishing arrangement.
✗
Question 2. How must the rated capacity of a lifeboat be marked under SOLAS?
Your Answer: (Not answered)
Correct Answer: A (Clearly and legibly marked on the boat, consistent with the capacity approved at survey)
💡 SOLAS requires the rated capacity to be clearly and durably marked on the boat so that the crew can tell at once whether it is overloaded. Recording it only on the certificate or advising orally does not comply.
✗
Question 3. What does SOLAS address regarding the subdivision of bilge drainage arrangements?
Your Answer: (Not answered)
Correct Answer: A (The bilge system must be arranged in sections so that water in any compartment can be drained independently)
💡 SOLAS requires the bilge system to be arranged in sections with independent suctions, so that water in any compartment can be drained on its own without affecting others, and the location of flooding can be identified. A single central suction does not meet the requirement.
✗
Question 4. Which abnormalities should the steering gear alarm system be capable of indicating on the bridge and in the steering gear compartment?
Your Answer: (Not answered)
Correct Answer: C (Power unit failure, loss of power, overload, low oil level in the tank and failure of the control system power supply)
💡 SOLAS requires the steering gear alarm system to indicate abnormalities such as power unit failure, loss of power, overload, low oil level and failure of the power supply to the control system, so that both the bridge and the engineers learn of a potential steering fault.
✗
Question 5. What should be noted when using HF for long range communication?
Your Answer: (Not answered)
Correct Answer: C (Choose the appropriate band according to time and distance, taking account of ionospheric conditions, and establish contact after a test call)
💡 HF communication relies on ionospheric reflection, and the suitable band differs by day and night and with distance, higher bands by day and lower bands at night. Contact should be established after the prescribed test call with the frequency watched. A single fixed frequency often means no contact at all.
✗
Question 6. What is the difference between the bulkhead deck and the freeboard deck under SOLAS II-1?
Your Answer: (Not answered)
Correct Answer: C (The bulkhead deck limits the extent of the main watertight bulkheads, while the freeboard deck is the datum for freeboard and load line)
💡 The bulkhead deck is the uppermost deck to which the main watertight bulkheads extend, whereas the freeboard deck is the datum for measuring freeboard and assigning load lines. Their roles in subdivision and load line calculations differ.
✗
Question 7. What does SOLAS require regarding the arrangement of scuppers, inlets and discharges on a ship's sides?
Your Answer: (Not answered)
Correct Answer: C (They must not lead water into spaces where it would be dangerous, and reliable means of closure must be fitted)
💡 SOLAS II-1 regulates the arrangement and closing appliances of overboard scuppers and inlets so that water cannot enter spaces where it would create a hazard through damage or inadvertent operation.
✗
Question 8. A free-fall lifeboat shall be capable of being launched safely:
Your Answer: (Not answered)
Correct Answer: C (within the specified range of trim and list)
💡 SOLAS III/16 requires a free-fall lifeboat to launch safely within the specified trim and list range.
✗
Question 9. What readiness of survival craft is required while the ship is in port?
Your Answer: (Not answered)
Correct Answer: C (Kept serviceable and ready; security measures may be applied but must be capable of rapid removal)
💡 While in port survival craft should remain serviceable and ready. Measures against theft may be taken, but they must be capable of being removed quickly to restore use. Locking them up completely or dismantling them would leave persons without the appliances in an emergency.
✗
Question 10. Pipes passing through the collision bulkhead shall be fitted with:
Your Answer: (Not answered)
Correct Answer: C (a valve operable from above the bulkhead deck, with the valve chest inside the forepeak)
💡 SOLAS II-1/12 requires pipes through the collision bulkhead to be fitted with a valve operable from above the bulkhead deck.
✗
Question 11. Which emergency information must a ship carrying dangerous goods carry under SOLAS VII?
Your Answer: (Not answered)
Correct Answer: A (The EmS Guide for fire and spill response together with MFAG for medical first aid)
💡 SOLAS VII requires both the EmS Guide, for fire and spill response, and MFAG, for medical first aid for chemical exposure. Neither replaces the other.
✗
Question 12. Which of the following is NOT required navigation equipment under SOLAS V/19?
Your Answer: (Not answered)
Correct Answer: A (facsimile machine)
💡 SOLAS V/19: a facsimile machine is not among the navigation equipment required by SOLAS V/19.
✗
Question 13. If a ship fails a survey because of an equipment deficiency, what may the Administration do?
Your Answer: (Not answered)
Correct Answer: B (Require rectification within a period and re-inspect afterwards, with the validity of the certificate possibly affected meanwhile)
💡 SOLAS I/12 permits the Administration to suspend or withdraw a certificate where the ship does not comply. In practice rectification within a period and re-inspection is required before validity is maintained or restored. A certificate must not be issued with a deficiency outstanding.
✗
Question 14. What does SOLAS address regarding the use of watertight doors in drills?
Your Answer: (Not answered)
Correct Answer: A (Closing and remote operation of watertight doors should be practised in drills so the crew is familiar with the procedure)
💡 SOLAS requires the closing and remote operation of watertight doors to be practised in drills, so that the crew is familiar with the procedure and the operating positions for closing doors in an emergency. A briefing alone does not ensure correct operation when it matters.
✗
Question 15. Which describes the periodical survey under SOLAS?
Your Answer: (Not answered)
Correct Answer: D (Carried out periodically and may replace an annual survey)
💡 The periodical survey may replace one of the annual surveys.
✗
Question 16. What is the main value of combining radar with ARPA?
Your Answer: (Not answered)
Correct Answer: C (Automatic tracking and computation of relative motion to assess collision risk)
💡 ARPA tracks targets automatically and computes CPA/TCPA to assess collision risk.
✗
Question 17. What do SOLAS and good practice address regarding operational testing of a fixed foam system?
Your Answer: (Not answered)
Correct Answer: C (Periodic inspection of piping and nozzles and, as required, a discharge test to confirm the system works)
💡 SOLAS and good practice require periodic inspection of the piping, valves and nozzles of a fixed foam system for obstruction, with a discharge test as required, confirming that the system will operate when needed.
✗
Question 18. What do SOLAS and good seamanship emphasise when navigating in a narrow channel or confined waters?
Your Answer: (Not answered)
Correct Answer: D (Reduce speed, keep engines ready, enhance the look-out and request a pilot if necessary)
💡 Navigation in confined waters requires reduced speed, engines ready for immediate manoeuvre, an enhanced look-out and readiness to manoeuvre, with a pilot requested if appropriate. High speed greatly increases the risk of collision and grounding.
✗
Question 19. What verification of the effectiveness of rectification is required?
Your Answer: (Not answered)
Correct Answer: B (Verify through re-inspection, testing or practical demonstration, not merely by documents or undertakings)
💡 After rectification its effectiveness should be verified by actual re-inspection, testing equipment or observing the crew, such as re-testing after a repair or checking the crew's operation after training, with evidence that the deficiency has been removed. A plan or an undertaking does not show that the work is done.
✗
Question 20. Where a fixed pressure water-spraying system is fitted in a machinery space, its nozzles shall cover:
Your Answer: (Not answered)
Correct Answer: B (all areas of the machinery space where fire may occur)
💡 SOLAS II-2/10 requires the fixed pressure water-spraying system to cover all areas of the machinery space where fire may occur.
✗
Question 21. Within an emission control area, what is the sulphur limit of fuel oil used on board?
Your Answer: (Not answered)
Correct Answer: A (0.10 per cent m/m)
💡 Within an emission control area the sulphur limit of fuel oil used on board is 0.10 per cent m/m. The ship should be able to show compliance through bunker delivery notes, changeover procedures and records, and should allow sufficient changeover time before entering the area.
✗
Question 22. What emergency preparedness is required while the ship is at anchor?
Your Answer: (Not answered)
Correct Answer: A (The emergency organisation and equipment must remain available, with the ship's condition monitored under the anchor watch)
💡 At anchor the emergency organisation must remain effective and emergency equipment such as survival craft, firefighting appliances and emergency communications available, with the position, weather and surroundings monitored under the anchor watch, ready at all times to respond to the unexpected.
✗
Question 23. How should the officer of the watch allow for wind and current when navigating in harbour waters?
Your Answer: (Not answered)
Correct Answer: A (Consider the drift caused by wind and current, keep a margin and apply rudder in good time)
💡 Harbour waters are confined and wind and current cause lateral drift. The officer should anticipate their direction and strength, adjust course and speed early and keep a handling margin, avoiding being set down onto a berth or into shoal water.
✗
Question 24. What is required when checking the lighting at survival craft embarkation positions?
Your Answer: (Not answered)
Correct Answer: A (Confirm that the emergency lighting operates, covering the embarkation area and the water alongside)
💡 SOLAS requires the lighting of the embarkation stations, survival craft stowage positions and the water alongside, including emergency lighting, to be confirmed in working order and covering the required area, so that abandonment at night is adequately lit. An appearance check would not confirm availability during a blackout.
✗
Question 25. Who shall approve the Cargo Securing Manual?
Your Answer: (Not answered)
Correct Answer: A (The Administration or its recognized organization)
💡 The Administration or its recognized organization.
✗
Question 26. What is required of an automatic pilot system?
Your Answer: (Not answered)
Correct Answer: D (It shall be possible to change over to manual steering quickly at any time)
💡 Change-over to manual steering shall be possible quickly at any time.
✗
Question 27. What does SOLAS require for quick closing valves in the fuel oil system of a machinery space?
Your Answer: (Not answered)
Correct Answer: A (Quick closing valves at fuel tank outlets and at fuel pumps, remotely operable from outside the space)
💡 SOLAS requires quick closing valves at fuel tank outlets and at fuel pumps, capable of remote operation from a readily accessible position, normally outside the space, so the fuel supply can be cut off rapidly in a machinery space fire.
✗
Question 28. The Polar Water Operational Manual (PWOM) is intended to:
Your Answer: (Not answered)
Correct Answer: A (provide the ship's operational limitations and procedures for operating in polar waters)
💡 SOLAS XIV/2: the Polar Water Operational Manual provides the ship's operational limitations and procedures for operating in polar waters.
✗
Question 29. What is required of drinking water containers in survival craft?
Your Answer: (Not answered)
Correct Answer: D (Hygienic containers preventing contamination, with the water renewed as prescribed)
💡 SOLAS requires survival craft to have hygienic containers for fresh water, preventing contamination and deterioration, with the water renewed at the prescribed servicing intervals. Water not renewed for a long time becomes undrinkable and affects survival.
✗
Question 30. From what source must radio equipment be supplied when the main source of power fails?
Your Answer: (Not answered)
Correct Answer: D (From the emergency source or a dedicated reserve source, maintaining distress communication capability)
💡 SOLAS IV/9 requires radio equipment to be supplied from the emergency source or a dedicated reserve source for at least one hour, so that distress alerting capability is not lost.
✗
Question 31. After a marine casualty such as a collision or grounding with serious loss, what is required of the master as to reporting?
Your Answer: (Not answered)
Correct Answer: C (Report to the flag Administration as required and, where necessary, to the nearest coastal State, and preserve the relevant records and information)
💡 Under SOLAS I/21 and related requirements, after a marine casualty the ship should report to the flag Administration as required and, where necessary, to the nearest coastal State, and should preserve evidence, the official log book and related records for the investigation. Concealing or delaying a report aggravates liability.
✗
Question 32. What safety is required for work at height at sea?
Your Answer: (Not answered)
Correct Answer: C (Use of safety harness and fall arrest equipment, warning signs and a standby person, taking account of ship movement)
💡 Work at height such as on masts, cranes and hatch coamings requires a safety harness and fall arrest equipment secured to a reliable point, warning signs and a standby person, with account taken of ship movement and wind. Hazardous work in heavy weather is prohibited.
✗
Question 33. What is required for the display of alarms from a fixed fire detection and fire alarm system?
Your Answer: (Not answered)
Correct Answer: A (The alarm must be displayed on the bridge or at a continuously manned central control station and indicate the space concerned)
💡 SOLAS requires fire alarms to be displayed on the bridge or at a continuously manned central control station and to indicate the space in which the alarm was initiated, so the fire can be located at once.
✗
Question 34. Besides the emergency duties of each crew member, what else must the muster list specify?
Your Answer: (Not answered)
Correct Answer: B (The muster stations)
💡 SOLAS III/37: the muster list shall specify duties and muster stations.
✗
Question 35. What do SOLAS and good practice address regarding insulation resistance of ship's electrical equipment?
Your Answer: (Not answered)
Correct Answer: A (Periodic measurement and recording of insulation resistance, investigating and rectifying any decline)
💡 SOLAS and good practice require periodic measurement and recording of insulation resistance. A fall in insulation resistance usually indicates moisture, ageing or damage, and early detection prevents short circuits and electrical fire.
✗
Question 36. What must the enclosed space entry testing record contain under SOLAS?
Your Answer: (Not answered)
Correct Answer: D (The date, location, parameters tested and results, and the issue of the permit)
💡 SOLAS and the IMO resolutions require records of enclosed space entry testing and permits, including the date, the space, the parameters tested — oxygen, toxic and flammable gases — the results and the permit issued, for traceability and inspection.
✗
Question 37. What measures must be taken when shipping a bulk cargo which may release toxic or flammable gas?
Your Answer: (Not answered)
Correct Answer: B (Increased ventilation, gas testing and restriction of entry into the holds as necessary)
💡 The IMSBC Code and SOLAS require increased ventilation and gas testing for cargoes that may release toxic or flammable gas, and gas testing with an entry permit before anyone enters a hold, preventing poisoning and explosion.
✗
Question 38. In what form shall the fire control plan be presented?
Your Answer: (Not answered)
Correct Answer: D (Plans, with symbols, showing divisions, control stations and fire-fighting appliances on each deck)
💡 Plans with standard symbols showing divisions, control stations and appliances on each deck.
✗
Question 39. What pressure testing does the fire main require?
Your Answer: (Not answered)
Correct Answer: B (Periodic pressure testing, normally annually, confirming no leakage in the piping and valves at the rated pressure)
💡 SOLAS and good practice require periodic pressure testing of the fire main, normally annually at not less than the design working pressure, confirming that the piping, valves and joints show no leakage or deformation under pressure, ensuring a reliable water supply in a fire.
✗
Question 40. Trading at high latitudes: what more does the radio installation need?
Your Answer: (Not answered)
Correct Answer: B (alerting and watch resting chiefly on high and medium frequencies, the beacon being one that works through polar-orbiting satellites)
💡 Those waters lie outside the view of a geostationary satellite, so distress alerting and the safety traffic fall mainly on digital selective calling in the medium and high frequencies, and maritime safety information comes by narrow-band direct printing on high frequencies, receivers being required to work there. The beacon depends on the polar-orbiting system, so its fit and its stowage are settled with a high-latitude alert in mind. Beyond the gear itself: propagation in those frequencies changes with the hour and with solar activity, an antenna can fail under ice, and the run from the bridge to that antenna matters. The equipment list, the frequencies watched and the back-ups, a usable source of power and a second means of alerting among them, are checked against the radio record and the certificates rather than judged from experience earned further south or north.
✗
Question 41. What is the main purpose of ship reporting systems?
Your Answer: (Not answered)
Correct Answer: A (To provide information on ship movements for search and rescue and safety of navigation)
💡 SOLAS V/11 establishes ship reporting systems to supply movement information for search and rescue and safety of navigation, not for commercial or charging purposes.
✗
Question 42. A crew member's actual rank does not match the certificate held, a junior certificate being used for a senior post. The finding is?
Your Answer: (Not answered)
Correct Answer: A (Serving with a mismatched certificate is an illegal manning arrangement, a serious deficiency to be corrected)
💡 A crew member's certificate of competency should match the rank held. Using a lower-grade certificate for a higher post is an illegal manning arrangement. It weakens the capability of the post and violates the safe manning requirements. It is a serious deficiency to be corrected, normally by changing personnel or supplying properly certificated crew.
✗
Question 43. A ship trades between 60 degrees north and south within Inmarsat coverage but too far offshore to receive MF coast station DSC. In which sea area is she?
Your Answer: (Not answered)
Correct Answer: B (Sea area A3)
💡 Sea area A3 is the area, excluding A1 and A2, within the coverage of an Inmarsat geostationary satellite, approximately between 70 degrees north and south. A2 requires coverage of at least one MF coast station DSC.
✗
Question 44. What does SOLAS address regarding openings in fire divisions?
Your Answer: (Not answered)
Correct Answer: A (The fire performance of an opening must be not less than that of the division, with closing appliances of equivalent rating)
💡 SOLAS requires openings such as doors, windows and manholes in a fire division to have fire performance not less than that of the division and to be fitted with closing appliances of equivalent rating. Any weak opening defeats the protection of the whole division.
✗
Question 45. For how long shall the emergency source of power on a passenger ship be capable of supplying the emergency services?
Your Answer: (Not answered)
Correct Answer: B (36 hours)
💡 SOLAS II-1/42: 36 hours on passenger ships; 18 hours on cargo ships.
✗
Question 46. What must the VDR record?
Your Answer: (Not answered)
Correct Answer: B (Position, course, speed, radar images, bridge audio and alarms)
💡 SOLAS requires the VDR to record data relevant to investigation, including date and time, position, course, speed, radar images with AIS, bridge audio, alarms and rudder orders, enabling the navigation and operation at the time to be reconstructed.
✗
Question 47. Each ship shall carry how many lifejackets for every person on board?
Your Answer: (Not answered)
Correct Answer: D (one per person)
💡 SOLAS III/7 requires one lifejacket for every person on board, with additional child lifejackets as required.
✗
Question 48. What checking of survival craft stowage cradles is required?
Your Answer: (Not answered)
Correct Answer: C (Check the structure for corrosion and deformation and the lashings and limiters for reliability)
💡 Survival craft cradles should be checked for serious corrosion or deformation of the structure and for the reliability of the lashings and limiters, with the sliding surfaces smooth so that launching is unobstructed. Structural failure would prevent launching or allow the craft to move in a seaway, a serious hazard.
✗
Question 49. What applies when security level 3 is set?
Your Answer: (Not answered)
Correct Answer: C (Further specific protective measures until the incident is resolved)
💡 Further specific protective measures until the incident is resolved.
✗
Question 50. Which is the 4 MHz band DSC distress frequency among the HF frequencies?
Your Answer: (Not answered)
Correct Answer: A (4207.5 kHz)
💡 HF DSC distress frequencies are 4207.5, 6312, 8414.5, 12577 and 16804.5 kHz. 2187.5 kHz is an MF frequency and 6312 kHz belongs to the 6 MHz band.
✗
Question 51. What checking of hours of work and rest is required?
Your Answer: (Not answered)
Correct Answer: A (Daily records of hours of work and rest must be kept, meeting the minimum rest requirements and available for inspection)
💡 STCW and the MLC require daily records of hours of work and rest to be kept and retained for inspection for the prescribed period, truthfully reflecting what happened and meeting the minimum rest requirements, such as not less than 10 hours in any 24-hour period and 77 hours in any seven-day period. Falsified records are a serious breach.
✗
Question 52. What is required for stability calculation after loading is completed?
Your Answer: (Not answered)
Correct Answer: C (Calculate the stability for the departure and arrival conditions and confirm compliance with the stability information)
💡 SOLAS requires the stability for departure and arrival conditions to be calculated and confirmed against the stability information, checking parameters such as metacentric height and righting levers. Any exceedance requires adjustment.
✗
Question 53. What does the ISM Code require regarding maintenance of the ship and equipment?
Your Answer: (Not answered)
Correct Answer: A (The company must establish maintenance arrangements with inspections and servicing of critical equipment at the prescribed intervals, recorded)
💡 ISM Code 10 requires the company to establish planned maintenance arrangements, inspecting and servicing critical equipment at the prescribed intervals with records kept, preventing failures from lack of maintenance. Breakdown repair alone does not comply.
✗
Question 54. Where shall the emergency generator and its fuel supply be located?
Your Answer: (Not answered)
Correct Answer: B (In a position not readily affected by main engine failure or fire)
💡 It must be sited away from the main engine and fire risk, with an independent fuel supply.
✗
Question 55. What protection is required for personnel handling chemicals and oils?
Your Answer: (Not answered)
Correct Answer: C (Appropriate personal protective equipment provided and correctly used, with prompt washing after contact and health surveillance where necessary)
💡 Personnel handling chemicals, oils or paints should be provided with and correctly use personal protective equipment as the safety data sheets require, including eye and face protection, gloves, protective clothing and respiratory protection, washing promptly after contact, with health surveillance and records where exposure is prolonged or symptoms appear.
✗
Question 56. A portable gas detector is found beyond its calibration validity. The finding is?
Your Answer: (Not answered)
Correct Answer: C (An uncalibrated detector gives untrustworthy readings, a deficiency affecting enclosed space safety)
💡 A portable gas detector is essential for judging whether the atmosphere is safe before entering an enclosed space or carrying out hot work. Beyond its calibration validity its readings cannot be trusted and may lead to a wrong judgement that endangers personnel. It is a deficiency to be corrected.
✗
Question 57. What does 'international voyage' mean in SOLAS?
Your Answer: (Not answered)
Correct Answer: B (A voyage from a port in one country to a port outside that country)
💡 It means a voyage from a port of one country to a port outside that country.
✗
Question 58. What nautical publications must be carried under SOLAS V/27?
Your Answer: (Not answered)
Correct Answer: B (Sailing directions, lists of lights and fog signals, tide tables and notices to mariners as required for the voyage)
💡 SOLAS V/27 requires all nautical publications necessary for the voyage, including sailing directions, lists of lights, tide tables and notices to mariners, kept corrected. Charts alone do not satisfy the requirement.
✗
Question 59. What reporting is required after a detention by PSC?
Your Answer: (Not answered)
Correct Answer: A (Report the detention, the deficiencies and the rectification arrangements to the flag State, the recognised organisation and the company as required)
💡 After a detention the ship should report the detention, the deficiencies and the plan to rectify to the flag State, the recognised organisation where relevant and the company, keeping the records. The flag State normally requires a detention report and evidence of rectification; this is mandatory.
✗
Question 60. After sending a distress alert in the GMDSS, what should the subsequent communication be?
Your Answer: (Not answered)
Correct Answer: B (Maintain watch and communication under the distress procedures, using distress frequencies as necessary and accepting coordination by coast stations)
💡 After sending a distress alert the watch and communication should be maintained under the distress procedures, using the distress and safety frequencies such as VHF channel 16 and MF/HF 2182 and accepting coordination by coast stations and rescue centres until the rescue is complete or the distress is closed. Breaking the watch after the alert delays rescue.
✗
Question 61. When must the first drill after leaving port be held?
Your Answer: (Not answered)
Correct Answer: D (Within 24 hours of leaving port, including abandon ship and fire drills)
💡 SOLAS III/19 requires the first drill, including abandon ship and fire drills and, on passenger ships, the participation of passengers, to be held within 24 hours of the ship leaving port, so that newly joined personnel and the whole crew have their emergency duties clear from the start of the voyage.
✗
Question 62. Where an enclosed means of escape is provided from a category A machinery space, what minimum fire protection does SOLAS II-2/13.4.3 require?
Your Answer: (Not answered)
Correct Answer: C (A-60 class division)
💡 SOLAS II-2/13.4.3 requires the enclosed means of escape from a category A machinery space to be of A-60 standard so that the route remains usable during a machinery space fire.
✗
Question 63. What are the core documents of the safety management system required by SOLAS Chapter IX?
Your Answer: (Not answered)
Correct Answer: A (A safety management manual together with supporting procedures covering the elements of the system)
💡 SOLAS IX and the ISM Code require a safety management manual with supporting procedures covering the elements of the Code. A policy statement or a single plan does not constitute a complete system.
✗
Question 64. An inflatable liferaft shall be serviced at intervals not exceeding:
Your Answer: (Not answered)
Correct Answer: D (12 months)
💡 SOLAS III/36 (LSA Code) requires inflatable liferafts to be serviced at intervals not exceeding 12 months.
✗
Question 65. What is required for checking the tightness of hatch covers on a bulk carrier?
Your Answer: (Not answered)
Correct Answer: A (Periodic inspection of seals, cleats and drain channels with a hose test to verify weathertightness)
💡 SOLAS requires the hatch covers of a bulk carrier to remain weathertight, with periodic checks of seal ageing, the effectiveness of cleats and the clearance of drain channels, and a hose test where necessary to verify tightness, preventing sea water from entering the holds and damaging structure and cargo.
✗
Question 66. Who decides to abandon ship?
Your Answer: (Not answered)
Correct Answer: B (The master, after assessing the condition of the ship; no one else may abandon her)
💡 The decision to abandon ship rests with the master, taken after assessing flooding, fire, stability and the possibility of rescue. Abandoning without authority would squander the chance of saving the ship and expose persons to the dangers of the sea, a serious breach.
✗
Question 67. What is the requirement for the international shore connection?
Your Answer: (Not answered)
Correct Answer: B (At least one must be carried on board with gasket, bolts and other fittings)
💡 SOLAS II-2/19 requires at least one standard international shore connection with fittings to be carried on board so that water can be supplied from shore or another ship. The ship cannot rely on the port providing it.
✗
Question 68. What does SOLAS require regarding the marking of the rated capacity of survival craft?
Your Answer: (Not answered)
Correct Answer: B (It must be clearly marked on the craft and must not be exceeded)
💡 SOLAS requires the rated capacity to be clearly marked on the craft and not to be exceeded. Overloading seriously affects buoyancy and stability.
✗
Question 69. For a cargo ship of 100 m and above, the number of lifebuoys with self-igniting lights shall be not less than:
Your Answer: (Not answered)
Correct Answer: B (8)
💡 SOLAS III/32 requires not less than eight lifebuoys with self-igniting lights for cargo ships of 100 m and above.
✗
Question 70. What is the purpose of protecting stairway enclosures on passenger ships?
Your Answer: (Not answered)
Correct Answer: D (Preventing spread of smoke and flame through the vertical shaft)
💡 To prevent smoke and flame spreading through the vertical shaft.
✗
Question 71. What is required for testing the emergency lighting system?
Your Answer: (Not answered)
Correct Answer: A (Periodic testing of automatic operation and duration, with records kept)
💡 SOLAS and good practice require periodic testing of the automatic operation of the emergency lighting and of its duration, for example by simulating failure of the main source, observing the lighting come on and timing it, verifying the prescribed period with records kept, preventing failure during an actual blackout.
✗
Question 72. Survival craft stowage positions shall be such that:
Your Answer: (Not answered)
Correct Answer: A (the craft can be boarded and launched safely and quickly)
💡 SOLAS III/13 requires stowage positions permitting safe and rapid boarding and launching.
✗
Question 73. What do SOLAS and COLREG emphasise about radar use in restricted visibility?
Your Answer: (Not answered)
Correct Answer: D (Switch on the radar early, use the longer range scales, observe continuously and interpret echoes correctly)
💡 COLREG and SOLAS require the radar to be switched on early in restricted visibility, used on the longer range scales and observed continuously, supplementing visual look-out. Radar must never replace the look-out.
✗
Question 74. Under GMDSS, what standing watches must the ship keep for distress and safety communications?
Your Answer: (Not answered)
Correct Answer: B (the watches the ship's fit requires — DSC on the distress and safety frequencies and reception of safety broadcasts, with a listening watch on VHF channel 16)
💡 The point of the watches is that another ship's alert and the shore's safety broadcasts reach the bridge: DSC on the designated distress and safety frequencies at MF/HF, maritime safety information by NAVTEX or the satellite EGC service, and a listening watch on VHF channel 16 under way, with someone answerable for alarms, printed receipts and updates. No exemption arises from being in port, from rest hours or from trading in one area, and the duty cannot be handed to the shore, which cannot know when this ship needs the message.
✗
Question 75. What safety is required for personnel entering a fire?
Your Answer: (Not answered)
Correct Answer: C (Enter in teams of two or more, maintain communication and keep within the air supply of the cylinders, following a known route)
💡 Entry for search and rescue requires teams of two or more, communication maintained with the command and outside, time strictly limited to the air supply of the breathing apparatus with allowance for the return, a known route followed and marked and a lifeline used where necessary. Entry alone and without communication is never permitted.
✗
Question 76. How many buoyant smoke signals shall each survival craft carry?
Your Answer: (Not answered)
Correct Answer: A (2)
💡 Two.
✗
Question 77. What should be done if a watertight door cannot be closed after damage?
Your Answer: (Not answered)
Correct Answer: A (Take measures to plug or otherwise limit the flooding, assess stability and decide the further course of action)
💡 A watertight door that cannot be closed allows flooding to spread. Measures to plug it, such as with leak-stopping material or wedges, or to limit the flooding should be taken at once, the stability and rate of flooding assessed and the further course decided, whether to beach, pump out or seek outside assistance, with the company informed.
✗
Question 78. What should be noted about using the lifeboat compass at night?
Your Answer: (Not answered)
Correct Answer: A (It must have a light enabling it to be read at night without impairing night vision)
💡 A lifeboat compass should have a light that does not impair night vision, such as red or dimmable illumination, so that a course can be kept at night after abandonment. A compass without a light is unusable at night and greatly reduces the chance of being found.
✗
Question 79. When is the urgency signal PAN PAN used?
Your Answer: (Not answered)
Correct Answer: D (For urgent communication not involving immediate danger to life, such as medical advice for a seriously ill person)
💡 PAN PAN is the urgency signal, used for a matter concerning safety which does not amount to distress, such as medical advice for a seriously ill person. MAYDAY is for grave and imminent danger to the ship or persons, and SECURITE for safety information.
✗
Question 80. The quantity of extinguishing medium stored for a fixed gas fire-extinguishing system shall be sufficient for:
Your Answer: (Not answered)
Correct Answer: B (the volume of the largest protected space)
💡 SOLAS II-2/10 requires the stored quantity of medium to be sufficient for the largest protected space.
✗
Question 81. What is the recommended action if a ship develops a list while under way?
Your Answer: (Not answered)
Correct Answer: B (Establish the cause, such as cargo shift, flooding or uneven ballast, and correct it promptly to prevent increasing list)
💡 An abnormal list at sea requires the cause to be established and corrective action taken, such as adjusting ballast or checking for flooding in a hold. A list of unknown cause or increasing may be the precursor of cargo shift or flooding, and ignoring it endangers the ship.
✗
Question 82. What is the maximum extension the Administration may grant to an expired certificate?
Your Answer: (Not answered)
Correct Answer: B (5 months)
💡 An extension of not more than 5 months may be granted.
✗
Question 83. What should be done before abandoning ship under SOLAS and good practice?
Your Answer: (Not answered)
Correct Answer: A (Transmit a distress alert where possible, take necessary emergency equipment and documents and close relevant openings)
💡 SOLAS and good practice require a distress alert to be transmitted where possible with the position given, necessary equipment and documents such as copies of certificates and the crew list to be taken, and watertight openings closed, improving the chance of rescue and later handling.
✗
Question 84. During anchoring in an anchorage, what is the basic watchkeeping requirement?
Your Answer: (Not answered)
Correct Answer: A (A continuous watch should be kept, monitoring the position and dragging risk, weather and surrounding traffic and keeping engines and steering available)
💡 During anchoring a continuous watch should be kept, monitoring the position, anchor chain loading and the risk of dragging, changes in tide, wind and current and surrounding traffic, with the engines, steering and communications available at all times. If dragging occurs the master should be informed promptly and measures taken.
✗
Question 85. What is the usual SOLAS requirement for the number of portable extinguishers in a machinery space?
Your Answer: (Not answered)
Correct Answer: D (A prescribed number according to the volume and arrangement of the space, with at least a stated number in each space)
💡 SOLAS II-2/10.3 requires a prescribed number of portable extinguishers in machinery spaces according to volume and arrangement, with at least a stated number in each space. An inadequate number is a common deficiency.
✗
Question 86. What protection is required when taking shore power in port?
Your Answer: (Not answered)
Correct Answer: A (Confirm voltage, frequency and phase sequence match, with insulation checked and proper earthing, preventing damage and electric shock)
💡 Before taking shore power, the voltage, frequency and phase sequence should be confirmed to match, with the cable insulation checked, reliable earthing established and earth leakage protection fitted. Once connected, the phase sequence should be verified to prevent motors running backwards and the equipment confirmed to operate normally, preventing damage and electric shock.
✗
Question 87. What measures do SOLAS and the IMSBC Code require for solid bulk cargoes liable to self-heat or release harmful gas?
Your Answer: (Not answered)
Correct Answer: A (Obtain full cargo information before loading, increase ventilation and gas testing and restrict entry into the holds)
💡 The IMSBC Code requires precautions for cargoes liable to self-heat or release harmful gas: full cargo information, increased ventilation and gas testing, restricted entry into the holds and emergency preparation, preventing spontaneous combustion, poisoning or explosion.
✗
Question 88. The inert gas system shall keep the oxygen content in cargo tanks below:
Your Answer: (Not answered)
Correct Answer: A (8%)
💡 Below 8% by volume.
✗
Question 89. What is required if a particular drill cannot be held in a month?
Your Answer: (Not answered)
Correct Answer: B (It should be held as soon as conditions permit, normally within 24 hours, with the reason for the delay recorded in the log)
💡 SOLAS requires a drill not held in a month because of navigational conditions to be held as soon as conditions permit, normally within the following 24 hours, with the reason for the delay recorded in the deck log. Missing drills over several months is a serious deficiency.
✗
Question 90. Which statement about the remote starting of fire pumps is correct?
Your Answer: (Not answered)
Correct Answer: C (Fire pumps should be capable of being started remotely from the bridge or fire control station, or readily started locally, for prompt water supply)
💡 Under SOLAS II-2/10 fire pumps should be capable of being started from the bridge or fire control station, or otherwise ensured to start promptly and supply the fire main in a fire. The means of starting should be stated in the operating instructions, with which the crew should be familiar. The emergency fire pump should have an independent source of power and self-priming capability.
✗
Question 91. In which circumstances must the ship security assessment be updated?
Your Answer: (Not answered)
Correct Answer: C (On major changes to the ship's structure, manning or operations, or on a change in the security situation)
💡 ISPS Code Part A/6 requires the ship security assessment to be reviewed and updated on major changes to the ship's structure, personnel or operations, or on a security incident or change of security level, keeping it consistent with the actual situation.
✗
Question 92. The garbage record book is found to disagree with the actual garbage categories and quantities and some discharge records are missing. The finding is?
Your Answer: (Not answered)
Correct Answer: B (False records make garbage management untraceable, a pollution prevention record deficiency)
💡 The garbage record book should truthfully record the category, quantity, means of disposal and time and place, being proof of compliance in garbage management. False or missing records make management untraceable. It is a pollution prevention record deficiency to be corrected and may lead to detention or penalty in serious cases.
✗
Question 93. What do SOLAS and the CSS Code address regarding inspection of securing equipment?
Your Answer: (Not answered)
Correct Answer: B (Periodic inspection of lashing rods, chains and turnbuckles for wear and corrosion, replaced promptly when defective)
💡 SOLAS and the CSS Code require securing equipment to be inspected periodically, with worn, corroded, deformed or cracked items replaced promptly. Defective securing gear fails in heavy weather and allows cargo to shift.
✗
Question 94. What do SOLAS and the IMDG Code require for marking and labelling of dangerous goods packages?
Your Answer: (Not answered)
Correct Answer: D (The proper shipping name, UN number and the relevant hazard class label)
💡 SOLAS VII and the IMDG Code require dangerous goods packages to show the proper shipping name, the UN number and the relevant hazard class label, including the marine pollutant mark, so that the crew can identify the hazard and act accordingly.
✗
Question 95. What should be done if oil overflows during bunkering?
Your Answer: (Not answered)
Correct Answer: C (Stop the operation at once, take emergency measures to contain the spill and prevent it entering the water)
💡 On overflow during bunkering the operation should be stopped at once by the agreed signal and emergency measures taken, such as absorbents and booms, with the spill collected and reported as required. Continuing would increase the quantity spilled and create pollution and fire risk.
✗
Question 96. How many lifebuoys must be fitted with a buoyant lifeline under SOLAS?
Your Answer: (Not answered)
Correct Answer: B (A prescribed number must have a buoyant lifeline, not fewer than the stated figure)
💡 SOLAS requires a prescribed number of lifebuoys to be fitted with a buoyant lifeline for recovering a person overboard. Not every lifebuoy needs one; fitting a lifeline and fitting a light are two separate requirements.
✗
Question 97. What is required of maintenance records?
Your Answer: (Not answered)
Correct Answer: B (Record the item, date, person carrying it out and the result, with reasons given and rescheduling for items not completed)
💡 A maintenance record should contain the item, the date it was done, who did it and the result with any problems found. Items not completed on time should have the reason stated, the risk assessed and a new date set, so that the system reflects the true maintenance state of the equipment.
✗
Question 98. What do SOLAS and good practice require if remote control of the main engine fails?
Your Answer: (Not answered)
Correct Answer: D (Transfer promptly to local or emergency control and inform the bridge so that appropriate measures can be taken)
💡 If remote control of the main engine fails, the change-over to local or emergency control should be made promptly and the bridge informed at once so that measures such as reducing speed, stopping or anchoring can be taken. In confined waters manoeuvring capability must be restored as quickly as possible.
✗
Question 99. What does SOLAS Chapter IX apply to?
Your Answer: (Not answered)
Correct Answer: C (Passenger ships and cargo ships of 500 GT and above, among others)
💡 Passenger ships and cargo ships of 500 GT and above, among others.
✗
Question 100. What expansion ratio is generally required for a tanker deck foam system?
Your Answer: (Not answered)
Correct Answer: C (Not exceeding about 12)